Permit Information
Permit NumberBLD04-02698
StatusExpired
Name SPRINGHILL SUITES SWIMMING POOL
Site Address 6325 N CLOVERDALE RD
Project NameSpringhill Suites by Marriott
Customer Number 
ePlanReviewNo
Description
Springhill Suites by Marriott - Swimming Pool - To construct a new 15' X 25' 575 sq.ft. outdoor swimming pool and a 9'-8" X 6'-6" 60 sq.ft. indoor spa at the existing Spring hill Suites hotel being constructed under BLD 04-01267. The pool equipment will be located in a separate structure permitted with the hotel. All construction per the approved plans. MJP DRH04-00044 CUP04-00016
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/5/20082/27/20082/27/2008PDONE
DetailsJim Sly
Check to see if Custom Pools called for finals. Nope.....EXP.

DOC - Permit Expired2/27/20082/27/20082/27/2008PPASS
DetailsJim Sly
Check to see if Custom Pools called for finals.
BLD-Final2/5/20082/14/20082/14/2008PDONE
DetailsJim Sly
EXP.
DOC - Permit Expired2/14/20082/14/20082/14/2008PPASS
DetailsJim Sly
Check to see if Custom pools called for finals. Left VM....................No response from Custom pools......Expired.
BLD-Aging Inspection2/1/20082/1/20082/5/2008 NR
DetailsJim Sly
Need all req finals Called custom pools....left VM
BLD-Footing3/7/20053/8/20053/8/2005APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 3/7/2005 at 9:10:15 AM. Contact: ###-####. Pool OK pending special insp tests and approvals. 3/8/2005 1:45:25 PM
Issue PAID IN FULL permit  12/3/2004 DONE
Permit Ready to Issue  12/2/2004  
Inspection Record Card- Bld  12/2/2004 DONE
Telephone call  12/2/2004 DONE
left mess for steve chandler at ###-#### that permit is ready
Plan assigned to (M_P)11/16/2004 11/30/2004 PASS
11/30/2004 12:54:44 M_P - activity updated through activity BLDA022 from case BLD04-02698.
Routing - PLAN CHECK11/29/2004 11/30/2004 PEND
Waiting for others to approve prior to issuing permit.
Routing - PLAN CHECK11/30/2004 11/30/2004  
Routing to ESC.
Routing - Erosion and Sediment11/30/2004 11/30/2004 PASS
ESC approved with attached conditions.
Routing - PLAN CHECK11/30/2004 11/30/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/30/2004 DONE
Print Pending Permit.LaserJet4  11/30/2004 DONE
Case Summary (BLD)  11/30/2004 DONE
Routing - FIRE11/22/2004 11/29/2004 PASS
1st review completed  11/29/2004 FAIL
failed Plan check and ESC
Routing - PLANNING11/22/2004 11/22/2004 PASS
Approved by Tempra Wilson for DRH04-00044. Further CU approval not needed per KG.
Routing - PLAN CHECK11/22/2004 11/22/2004  
Routing to fire
Routing - PLAN CHECK11/18/2004 11/22/2004 FAIL
Need plans detailing reinforcement for pool ansd spa. Called pool constractor and left message.
Routing to planning
Routing - PLUMBING11/18/2004 11/18/2004 PASS
Routing - PUBLIC WORKS11/16/2004 11/18/2004 PASS
Routing - Erosion and Sediment11/18/2004 11/18/2004 FAIL
RP not listed. Informed pool contractor that certified rp is required.
Plan routing begun/NEW & ADDTN  11/16/2004  
Recd Pcfee & Taken To Pln CK  11/16/2004 DONE
Plans ACCEPTED BY PLAN TECH  11/16/2004  
Application received  11/15/2004