BLD-Final | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PASS |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/25/2005 at 10:08:30 AM. Contact: ###-####.
|
DOC - Permit Finaled | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PASS |
Lane Manuel
|
|
|
Finaled by inspector at 2/25/2005 3:31:45 PM
|
BLD-Framing/Rough-in | 1/31/2005 | 1/31/2005 | 1/31/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 7:07:11 AM. Contact: ###-####.
|
BLD-Energy code compliance | 1/31/2005 | 1/31/2005 | 1/31/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 7:12:52 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/27/2005 | 1/28/2005 | 1/28/2005 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 10:31:40 PM. Contact: ###-####. rolled to pm 1/28/2005 10:21:15 AM
|
BLD-Energy code compliance | 1/27/2005 | 1/28/2005 | 1/28/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 10:32:19 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/28/2005 | 1/28/2005 | 1/28/2005 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 10:31:40 PM. Contact: ###-####. c/n stands 1/28/2005 2:43:05 PM
|
BLD-Framing/Rough-in | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 8:09:23 AM. Contact: ###-####. c/n on site 1/27/2005 4:34:49 PM
|
BLD-Foundation | 1/4/2005 | 1/5/2005 | 1/5/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/4/2005 at 2:23:41 PM. Contact: ###-####.
|
BLD-Footing | 1/3/2005 | 1/4/2005 | 1/4/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/3/2005 at 7:56:24 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 12/7/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/29/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/29/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/29/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Pending Assignment by DJO | 11/17/2004 | | 11/26/2004 | | DONE |
|
|
|
11/26/2004 08:04:39 PEP - activity updated through activity BLDA176 from case BLD04-02727.
|
Plan assigned to (PEP) | 11/26/2004 | | 11/26/2004 | | PASS |
|
|
|
11/26/2004 15:52:06 PEP - activity updated through activity BLDA022 from case BLD04-02727.
|
Case Summary (BLD) | | | 11/26/2004 | | |
|
|
|
|
Plan Review Report | | | 11/26/2004 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2004 | | DONE |
|
|
|
|
Routing - PLANNING | 11/17/2004 | | 11/22/2004 | | PASS |
|
|
|
Meets the requirements of CVA03-00042.
|
Routing - PUBLIC WORKS | 11/22/2004 | | 11/22/2004 | | PASS |
|
|
|
|
Application received | | | 11/17/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 11/23/2004 | | | | |
|
|
|
|