Permit Information
Permit NumberBLD04-02772
StatusFinaled
Name BOISE AIR TERMINAL (REMODEL & WALKWAY)
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT
Customer Number 
ePlanReviewNo
Description
(BOISE AIR TERMINAL - CONCOURSE B AND AIRCRAFT LOADING WALKWAY) Both Concourse B buildings are fire sprinklered to substitute for 1-hr fire-resistance rated construction. To construct a new entrance vestibule and support structure to serve a new aircraft loading walkway at "Original Concourse B". Work is to include a concrete foundation, cantilevered beams, concrete floor deck, spray applied fire-proofing, steel roof deck, welding, and equipment. Also, to remodel the interior of "Original Concourse B" and "Concourse B Extension". An elevated concrete floor/ramp will be constructed over the existing floor AND the 4 existing restrooms will be remodeled. At least one of each type of fixture in each restroom shall be accessible to the disabled. Work is to include strengthening existing steel floor beams, welding, new floor finishes, new wall finishes, new ceilings finishes, and new ceiling tile. All work shall comply with the approved drawings and the plan review report on file. The fire sprinkler systems shall comply with NFPA 13-2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD7/7/20067/7/20067/7/2006 DONE
First Notice has not been responded to.
First Notice5/16/20065/16/20067/7/2006 DONE
DetailsJim Storey
Letter of compliance  6/9/2006 DONE
Letter of Compliance issued 6-9-06.
BLD-Final5/15/20065/16/20065/16/2006APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/15/2006 at 5:31:38 PM. Contact: ###-####.
DOC - Permit Finaled5/16/20065/16/20065/16/2006PPASS
DetailsJim Storey
BLD-Final3/20/20063/21/20063/20/2006ADEFR
DetailsJim Storey
BLD-Final3/17/20063/20/20063/20/2006ADEFR
DetailsJim Storey
jeff miller; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa pending ada signage rolled to tue am.
FIRE-Final Inspection3/17/20063/20/20063/20/2006APASS
DetailsForrest France
Fire life safety is satisfactory, project related fire sprinkler and fire alarm permits have been finaled.
BLD-Aging Inspection1/31/20061/31/20061/31/2006 NR
DetailsJim Storey
pending fire.
BLD-Aging Inspection12/1/200512/1/200512/1/2005 NR
DetailsJim Storey
pending fire
BLD-Final9/26/20059/27/20059/27/2005PNR
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/26/2005 at 1:22:40 PM. Contact: ###-####.pending fire alarm permit and insp.
BLD-Framing/Rough-in7/22/20057/25/20057/25/2005APASS
DetailsJim Storey
BLD-Framing/Rough-in7/20/20057/22/20057/22/2005PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/20/2005 at 12:33:20 PM.
BLD-Framing/Rough-in5/23/20055/24/20055/24/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/23/2005 at 4:26:40 PM. Contact: ###-####.
BLD-Footing5/23/20055/24/20055/24/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/23/2005 at 4:25:04 PM. Contact: ###-####.
Case Summary (BLD)  4/13/2005 DONE
Issue & PRINT to be Invoiced  3/22/2005 DONE
(F) Reprint permit  3/16/2005  
Telephone call  1/12/2005 DONE
left mess for ted isbell ###-#### is ready
Inspection Record Card- Bld  12/21/2004 DONE
Permit Ready to Issue  12/21/2004 DONE
Telephone call  12/21/2004 DONE
lft vm with ted isbbell ###-#### the fees and permit is ready to be picked up
Routing - FIRE12/15/2004 12/20/2004 PASS
Plan assigned to (CJW)11/26/2004 12/20/2004 PASS
12/20/2004 16:35:11 CJW - activity updated through activity BLDA022 from case BLD04-02772.
1st review completed  12/20/2004 PASS
Routing - PLAN CHECK12/20/2004 12/20/2004  
PLANS/APPL TAKEN TO FRONT DESK  12/20/2004 DONE
Routing - PLAN CHECK12/2/2004 12/15/2004 PASS
The IBC plan review was started December 8, 2004 and was finished December 15, 2003. The drawings were approved with clarifications. See the plan review report.
Routing - PLANNING11/30/2004 12/2/2004 PASS
Routing - PUBLIC WORKS11/26/2004 11/30/2004 PASS
Plans ACCEPTED BY PLAN TECH  11/24/2004  
No ELE Compliance Sheet...
Application received  11/24/2004  
Fee Review-notes11/24/200411/24/2004