BLD-Final | 6/14/2005 | 6/15/2005 | 6/15/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/14/2005 at 3:51:08 PM. Contact: ###-####. C/C issued.
|
DOC - Permit Finaled | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | PASS |
Jim Sly
|
|
|
C/C issued
|
BLD-Energy code compliance | 2/28/2005 | 3/1/2005 | 3/1/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/28/2005 at 2:49:19 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 2/25/2005 at 8:25:28 AM. Contact: ###-####.
|
BLD-Foundation | 1/14/2005 | 1/18/2005 | 1/18/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/14/2005 at 9:23:26 AM. Contact: ###-####.
|
BLD-Footing | 1/14/2005 | 1/14/2005 | 1/14/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/14/2005 at 9:23:04 AM. Contact: ###-####. MG.... W. on Ustick... L. dalton. 1/14/2005 1:46:06 PM
|
Issue PAID IN FULL permit | | | 1/14/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 12/14/2004 | | 1/13/2005 | | PASS |
|
|
|
1/13/2005 09:24:07 SAM - activity updated through activity BLDA022 from case BLD04-02837.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/13/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/13/2005 | | DONE |
|
|
|
called Steve Heart ###-#### quoted fees/permit ready
|
Permit Ready to Issue | | | 1/13/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/15/2004 | | |
|
|
|
|
Plan Review Report | | | 12/15/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 12/10/2004 | | 12/15/2004 | | PASS |
|
|
|
Plan review is done I'm waiting for the Fire Department to release the subdivision.
|
Pending Assignment by DJO | 12/6/2004 | | 12/14/2004 | | DONE |
|
|
|
12/14/2004 15:54:20 SAM - activity updated through activity BLDA183 from case BLD04-02837.
|
Routing - PUBLIC WORKS | 12/10/2004 | | 12/10/2004 | | PASS |
|
|
|
|
Routing - PLANNING | 12/10/2004 | | 12/10/2004 | | PASS |
|
|
|
Verified landcaping through email sent by applicant. Plans meet the requirements of CUP03-00072.
|
Telephone call | | | 12/9/2004 | | DONE |
|
|
|
Received telephone call from applicant. They will be sending photos of the landscaping which has already been installed. We will need to verify landscaping prior to reviewing plans.
|
Routing - PLANNING Land Div | 12/7/2004 | | 12/7/2004 | | PASS |
|
|
|
Lot 3, Block 1 of Deschutes Subdivision recorded on November 17, 2004.
|
Routing - PLANNING | 12/7/2004 | | 12/7/2004 | | FAIL |
|
|
|
Spoke w/ applicant. Requested photos of installed landscape.
|
Application received | | | 12/6/2004 | | |
|
|
|
|