Third Notice BLD | 12/7/2005 | 12/7/2005 | 12/29/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice | | 5/20/2005 | 12/7/2005 | | DONE |
|
|
|
|
First Notice | | 4/4/2005 | 4/26/2005 | | DONE |
|
|
|
|
BLD-Final | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | PASS |
Troy James
|
|
|
dee; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Permanent Occupancy | | 4/4/2005 | 4/4/2005 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 4/4/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10517 issued 4-4-05 to the Men's Warehouse.
|
BLD-Final | 3/28/2005 | 3/29/2005 | 3/29/2005 | P | PART |
Troy James
|
|
|
dee; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
temp final, need mechanical and electrical to final, new mech. and electrical permit for press machine to be installed 3/29/2005 3:14:00 PM 3/29/2005 3:15:58 PM
|
FIRE-Final Inspection | 3/29/2005 | 3/29/2005 | 3/29/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 3/29/2005 2:13:03 PM
|
BLD-Final | 3/24/2005 | 3/28/2005 | 3/28/2005 | A | NR |
Jim Sly
|
|
|
dee; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Need Fire final. 3/28/2005 10:21:38 AM
|
FIRE-Final Inspection | 3/28/2005 | 3/28/2005 | 3/28/2005 | P | FAIL |
Troy Cobbley
|
|
|
Repair three exit signs and one emergency light. Repair remote annunciators and provide one additional duct smoke to the hvac unit number three. 3/28/2005 3:59:05 PM
|
FIRE-Final Inspection | 3/24/2005 | 3/25/2005 | 3/25/2005 | P | CANC |
Troy Cobbley
|
|
|
Not ready 3/25/2005 3:05:10 PM
|
BLD-Other | 3/16/2005 | 3/17/2005 | 3/17/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/16/2005 at 4:43:52 PM. Contact: ###-####. ceiling cover drafstop and ipods ok ok to drop in ceiling panels 3/17/2005 1:48:48 PM
|
BLD-Wall cover | 3/15/2005 | 3/16/2005 | 3/16/2005 | P | PART |
Troy James
|
|
|
###-#### - dee - Note: ceiling cover
seal draft stop and need ipods at front of store, back room not ready 3/16/2005 4:11:08 PM
|
FIRE-Conference | 3/10/2005 | 3/10/2005 | 3/10/2005 | P | DONE |
Troy Cobbley
|
|
|
Contractor had questions about the fire rated corridor. 3/10/2005 4:35:47 PM
|
BLD-Other | 3/2/2005 | 3/3/2005 | 3/3/2005 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 3/2/2005 at 1:59:49 PM. Contact: ###-####. ok screws corridor walls and framing for draft stop. 3/3/2005 2:59:18 PM
|
BLD-Framing/Rough-in | 3/1/2005 | 3/2/2005 | 3/2/2005 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 3/1/2005 at 2:06:55 PM. Contact: ###-####. ok to cover walls only, need nailing inspection to corridor walls 3/2/2005 1:17:22 PM
|
Issue PAID IN FULL permit | | | 2/22/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/31/2005 | | 2/16/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan assigned to (JCB) | 12/10/2004 | | 2/16/2005 | | PASS |
|
|
|
2/16/2005 11:08:47 JCB - activity updated through activity BLDA022 from case BLD04-02887.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2005 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 2/16/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/16/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/16/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/16/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/10/2005 | | DONE |
|
|
|
Received Transmittal, 1 Letter, 1 Registered Design Professional in Responsible Charge, & 2 Copys of sheets T1.0,GN1.0,D1.0,S1.0,A1.0,A1.01,A2.0,A3.0,A3.01,A3.02,A3.03,A3.1,A4.0,A4.1,A5.0,A5.1,F1.0,M1.0,M2.0,M3.0,E1.0,E2.0 Taken to Jason B.
|
Routing - PLAN CHECK | 12/23/2004 | | 1/31/2005 | | FAIL |
|
|
|
Second plan review report e-mailed to architect. Some issues were not adequately addressed and some were not addressed at all. A written response and resubmittal plans are required for further review.
|
Plan resubmittals requested | | | 1/31/2005 | | |
|
|
|
Plan resubmittals and written response required again for further review.
|
Telephone call | | | 1/28/2005 | | |
|
|
|
Talked with structural engineer Keith Jones concerning the welds on the roof joists to be verified. These will be verified by Atwood Hinzman Jones Engineers, the engineer of record, and written verification for adequacy will be provided to the Inspector in the field.
|
Plan resubmittals received | | | 1/24/2005 | | DONE |
|
|
|
Received Transmittal ,2 Letters , 3 Structural Calculations, & 3 Copys of sheets T1.0,S1.0,A1.0,A1.01,A2.0,A3.0,A3.02,A3.03,A4.0,A4.1,A5.1,F1.0,M1.0,M2.0,E2.0,E3.0,P1.0 Taken to Jason B.
|
Routing - FIRE | 12/21/2004 | | 12/23/2004 | | PASS |
|
|
|
|
1st review completed | | | 12/23/2004 | | FAIL |
|
|
|
failed Plan check.
|
Routing - PLAN CHECK | 12/13/2004 | | 12/20/2004 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept.
|
Plan resubmittals requested | | | 12/20/2004 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PUBLIC WORKS | 12/10/2004 | | 12/13/2004 | | PASS |
|
|
|
|
Application received | | | 12/10/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/10/2004 | | |
|
|
|
|
Fee Review-notes | 12/10/2004 | 12/10/2004 | | | |
|
|
|
|