(F) Reprint permit | | | 8/8/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/20/2005 | | DONE |
|
|
|
|
BLD-Final | 6/17/2005 | 6/17/2005 | 6/17/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/17/2005 at 8:31:57 AM. Contact: ###-####.
|
DOC - Permit Finaled | 6/17/2005 | 6/17/2005 | 6/17/2005 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 6/13/2005 | 6/13/2005 | 6/13/2005 | P | NR |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore complete correction notice on rear handrail
|
BLD-Final | 6/10/2005 | 6/10/2005 | 6/10/2005 | P | FAIL |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles all complete except handrail at rear does not comply with sec 315 of 2000 irc
|
BLD-Final | 5/25/2005 | 5/25/2005 | 5/25/2005 | P | FAIL |
Tom Arcoraci
|
|
|
c/n mike ###-####
|
BLD-Final | 5/24/2005 | 5/25/2005 | 5/25/2005 | A | CANC |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Energy code compliance | 2/23/2005 | 2/25/2005 | 2/25/2005 | A | PASS |
Tom Arcoraci
|
|
|
###-#### chris
|
BLD-Framing/Rough-in | 2/22/2005 | 2/23/2005 | 2/23/2005 | P | PASS |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/22/2005 at 3:49:06 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/15/2005 | 2/18/2005 | 2/18/2005 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/15/2005 at 10:30:09 AM. Contact: ###-####. needs rough ins insp 2/18/2005 9:58:21 AM
|
BLD-Other | 2/10/2005 | 2/10/2005 | 2/10/2005 | A | PASS |
Tom Arcoraci
|
|
|
new pins set appears to be five ft from prop line
|
BLD-Conference | 2/3/2005 | 2/3/2005 | 2/3/2005 | P | PASS |
Tom Arcoraci
|
|
|
talked to builder informed him of complaint of side set back required him survey lot lines. talked to complaintent and told her i have required builder to survey lot lines and call for a inspection.
|
BLD-Foundation | 1/11/2005 | 1/12/2005 | 1/12/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/11/2005 at 6:40:51 PM. Contact: ###-####.
|
BLD-Footing | 1/11/2005 | 1/11/2005 | 1/11/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/11/2005 at 6:35:38 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 1/5/2005 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 12/21/2004 | 12/21/2004 | 12/21/2004 | | PASS |
|
|
|
12/21/2004 10:24:47 DJO - activity updated through activity BLDA022 from case BLD04-02918.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/21/2004 | | |
|
|
|
|
Plan Review Report | | | 12/21/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/21/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/21/2004 | | DONE |
|
|
|
tlk to chris sabala ###-#### that his permit and fees are ready to be picked up
|
Pending Assignment by DJO | 12/16/2004 | | 12/21/2004 | | DONE |
|
|
|
12/21/2004 10:24:38 DJO - activity updated through activity BLDA169 from case BLD04-02918.
|
Plans ACCEPTED BY PLAN CHECK | | | 12/21/2004 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/17/2004 | | 12/20/2004 | | PASS |
|
|
|
|
Routing - PLANNING | 12/16/2004 | | 12/17/2004 | | PASS |
|
|
|
verify previous structure demolished.
|
Application received | | | 12/16/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 12/20/2004 | | | | |
|
|
|
|