BLD-Final | 9/8/2005 | 9/8/2005 | 9/8/2005 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
|
DOC - Permit Finaled | 9/8/2005 | 9/8/2005 | 9/8/2005 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 9/6/2005 | 9/7/2005 | 9/7/2005 | P | FAIL |
Tony Young
|
|
|
maybe confirm w/ titus before arriving to make sure everything ready; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam c/n posted
|
BLD-Grading Inspection | 9/7/2005 | 9/7/2005 | 9/7/2005 | | BOND |
|
|
|
Rough grading is complete however fine grading and installation of a roof drain pipe are not complete. For this a $2,000.00 bond is required. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Energy code compliance | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | NR |
Tony Young
|
|
|
Internet Inspection Request from: Titus Gilliam
need trades 5/4/2005 10:45:07 AM
|
BLD-Energy code compliance | 5/4/2005 | 5/4/2005 | 5/4/2005 | P | PASS |
Tony Young
|
|
|
Internet Inspection Request from: Titus Gilliam
|
BLD-Framing/Rough-in | 5/2/2005 | 5/2/2005 | 5/2/2005 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
frame ok, ok to insulate pending mech. rough 5/2/2005 2:02:00 PM
|
BLD-Framing/Rough-in | 4/29/2005 | 4/29/2005 | 4/29/2005 | P | NR |
Tony Young
|
|
|
Tony, HVAC should be done AM. Framers will be on job at noon to pick up details from Thursday. If possible and in area try to catch them around one PM in the afternoon Friday. thanks; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
|
BLD-Framing/Rough-in | 4/28/2005 | 4/28/2005 | 4/28/2005 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
|
BLD-Framing/Rough-in | 4/20/2005 | 4/20/2005 | 4/20/2005 | P | PART |
Tony Young
|
|
|
titus --shear ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
ext. shear ok 4/20/2005 4:04:29 PM
|
BLD-Framing/Rough-in | 4/18/2005 | 4/19/2005 | 4/19/2005 | A | FAIL |
Tony Young
|
|
|
titis - Note: shear only; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
need approved plans 4/19/2005 11:47:24 AM
|
BLD-Foundation | 1/25/2005 | 1/26/2005 | 1/26/2005 | A | PART |
Tony Young
|
|
|
jed; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
basement wall 1/26/2005 12:57:16 PM
|
BLD-Footing | 1/19/2005 | 1/20/2005 | 1/20/2005 | P | PART |
Tony Young
|
|
|
JED; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Grading Inspection | 1/19/2005 | 1/19/2005 | 1/19/2005 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
PubWorks Subgrade Approval | 12/22/2004 | 12/22/2004 | 1/19/2005 | | DONE |
|
|
|
A LETTER FROM THE APPLICANTS GEOTECHNICAL ENGINEER INDICATING THAT THE FOOTING SUBGRADE IS ACCEPTABLE MUST BE APPROVED BY PUBLIC WORKS PRIOR TO SCHEDULING A FOOTING INSPECTION. ALL TERRY RECORDS AT ###-#### OR FAX AT ###-####
|
Override - Activity Holds | | | 1/12/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/12/2005 | | |
|
|
|
|
Pending Assignment by DJO | 12/16/2004 | | 1/7/2005 | | DONE |
|
|
|
1/7/2005 08:31:17 SAM - activity updated through activity BLDA183 from case BLD04-02920.
|
Routing - PLAN CHECK | 12/27/2004 | | 1/7/2005 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 1/6/2005 | | 1/7/2005 | | PASS |
|
|
|
1/7/2005 09:31:47 SAM - activity updated through activity BLDA022 from case BLD04-02920.
|
Case Summary (BLD) | | | 1/7/2005 | | |
|
|
|
|
Plan Review Report | | | 1/7/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 1/7/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 1/7/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 1/7/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/7/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/7/2005 | | DONE |
|
|
|
Left message that permit is ready & fees///1/7/05 2:30pm BAS
|
Routing - Erosion and Sediment | 12/29/2004 | | 12/30/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 12/30/2004 | | 12/30/2004 | | PASS |
|
|
|
No fire sprinklers required. (Arrowhead Ridge sub)
|
Routing - PLANNING | 12/22/2004 | | 12/27/2004 | | PASS |
|
|
|
holiday
|
Routing - PUBLIC WORKS | 12/22/2004 | | 12/22/2004 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 12/22/2004 | | 12/22/2004 | | PASS |
|
|
|
APPROVED AS CATEGORY 3
|
Routing - PUBLIC WORKS GRADING | 12/16/2004 | | 12/17/2004 | | FAIL |
|
|
|
Geotechnical report must be revised. Contacted engineer and contractor.
|
Application received | | | 12/16/2004 | | |
|
|
|
|