Permit Information
Permit NumberBLD04-02927
StatusFinaled
Name MORGAN CONSTRUCTION
Site Address 3157 S BOWN WAY
Project NameBOWN CROSSING-DR TIM HUFF
Customer Number 
ePlanReviewNo
Description
(DR TIM HUFF)(BOWN CROSSING) To construct a new 5,800 sq.ft. two-story, multi tenant, office building. The first floor is 5,177 sq.ft. and the second floor is 623 sq.ft. There are three tenant spaces within this building. The north 1,407 sq.ft. and the south 1,407 sq.ft are each single story and are being constructed as shells, for future tenant spaces. NOTE: Separate plans, permits and Certificate of Occupancies must submitted and be approved prior to finishing and occupying each of the two future tenant space. All construction per the approved plans and attached comment list. The center section is being finished under this permit and will be occupied as a dentist office. This section is the two story portion of the building. The first floor of this section is 2,363 sq.ft the second floor is 623 sq.ft. Refer to MIS 05-00033 for the Certificate of Occupancy. Parking lot put in under BLD05-01405. MJP DRH04-00277
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 5/23/20065/23/2006 DONE
Details
Letter of compliance  5/23/2006 DONE
Letter of Compliance issued 5-23-06.
Code Occupancy Approval  5/22/2006 PASS
DRH04-00277 was modified to allow the landscaping to exist as completed. This means that the brick area at the main entrance was eliminated and allowed to remain with bark, per modification approved my Cody Riddle.
Temporary occupancy  5/2/2006 DONE
Temp. Occ. Cert. #5400 issued 5-2-06 to Dr. Tim Huff.
BLD-Final4/30/20065/1/20065/1/2006PPART
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: scott Hawker final ok pending all sign offs.
BLD-Final4/18/20064/19/20064/20/2006PFAIL
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: scott Hawker fire stop/ada signage and pocket door hardware.
FIRE-Final Inspection4/18/20064/19/20064/19/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection4/13/20064/14/20064/17/2006AFAIL
DetailsForrest France
Remove deadbolts at two locations on exit doors that are not the main entry/exit, provide address numbers facing Bown Way, repair emergency discharge light at the main entry, the project related fire sprinkler permit for the medical gas closet must be requested for inspection and approved prior to building life safety final (it appears there are some defficiencies related to the fire sprinkler at this time).
FIRE-Final Inspection4/14/20064/14/20064/14/2006PDONE
DetailsForrest France
###-#### - scott
BLD-Framing/Rough-in3/27/20063/28/20063/28/2006APART
DetailsJim Storey
ceiling insp- scott; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie need to remove pop rivets.
BLD-Aging Inspection3/23/20063/23/20063/23/2006 PASS
DetailsJim Storey
wip
BLD-Energy code compliance1/20/20061/20/20061/20/2006PPART
DetailsJim Storey
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore center ti space.ok
BLD-Framing/Rough-in1/17/20061/18/20061/18/2006PPASS
DetailsJim Storey
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore pending mech.
BLD-Framing/Rough-in12/7/200512/8/200512/8/2005APASS
DetailsJim Storey
shear wall inspection////scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Aging Inspection12/5/200512/5/200512/5/2005 PASS
DetailsJim Storey
wip plm
BLD-Aging Inspection10/3/200510/3/200510/3/2005 PASS
DetailsJim Storey
wip
BLD-Foundation8/2/20058/3/20058/3/2005APASS
DetailsMike Jordan
scott; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing7/25/20057/25/20057/25/2005PPASS
DetailsJim Storey
terry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
(F) Reprint permit  7/11/2005  
Print Occupancy Form  7/8/2005 DONE
Issue PAID IN FULL permit  7/8/2005 DONE
Telephone call  7/6/2005 DONE
received new cert of value had to adjust fees-called tim huff to give new fee amount
Telephone call  6/29/2005 DONE
talked to neccia at ###-#### that permit is ready & will let scott hawker know this-also need achd before picking up permit.
Telephone call  5/17/2005 DONE
called left message for scott hawks permit is ready and fees and achd needed
Telephone call  4/20/2005 DONE
called talked to Scott he said tenant having problem with financing and will pick up permit as soon as possible. Told him have until 6/16/05 to pick up 4/20/05 2:10pm
Plan assigned to (M_P)12/17/200412/17/20043/16/2005 PASS
3/16/2005 08:18:44 M_P - activity updated through activity BLDA022 from case BLD04-02927.
Routing - PLAN CHECK3/14/2005 3/16/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  3/16/2005 DONE
Permit Ready to Issue  3/16/2005 DONE
Inspection Record Card- Bld  3/16/2005 DONE
Inspection Record Card- Bld  3/16/2005 DONE
Telephone call  3/16/2005 DONE
called 1-###-#### left a msg plans are ready & quoted fees///JRR
Routing - PLANNING3/11/2005 3/14/2005 PASS
Approved per DRH04-000277 and per revised landscape plan attached to DR approval letter.
Routing - PLAN CHECK3/7/2005 3/11/2005 PEND
Waiting for others to approve prior to isuing permit.
Routing - PLUMBING3/4/2005 3/4/2005 PASS
approved per plan ond 2003 UPC. possible point of use backflow may be required
Routing - PLUMBING2/23/2005 3/3/2005 FAIL
Talked to Newall with Sundberg and he will have engineer submit a roof and overflow drain plan on plumbing plan.
Routing Off Site - STRUCTURAL2/28/2005 3/2/2005 PASS
Called PDQ for pick up.
Routing - FIRE2/17/2005 2/23/2005 PASS
resubmittal acceptable conditioned upon satisfactory field modification to the southeast planter curb in the parking lot as annotated in "red" on resubmitted sheet SD1of 1 and Grading and Drainage sheet 1 of 2. Revised comments faxed to architect.
Plan resubmittals received  2/22/2005 DONE
Received 3 Copys of sheets S8 OF 10,S6 OF 10 Taken to Mike P.
Additional plans submitted  2/17/2005 DONE
Received UW water info re-submittal from archtitect.
Routing Off Site - STRUCTURAL1/31/2005 2/15/2005 FAIL
Called PDQ for pick -up
Second review failed faxed comments to architect.
Routing - PLANNING2/11/2005 2/14/2005 FAIL
Applicant has not supplied a detailed landscape plan or the easement agreement with the properties to the north.
Routing - FIRE2/14/2005 2/14/2005 FAIL
still no UW water info; not reviewed further.
Routing - PLAN CHECK1/10/2005 2/11/2005  
Routing to planning
Plan resubmittals received  2/1/2005 DONE
Received 4 Letters , 4 Copys of sheets P-1,P-2 3Copys of sheets 1 OF 3 , 2 OF 3, 3 OF 3 Take to Mike P.
Plan resubmittals received  1/25/2005 DONE
Received Letter, 3 Structural Calcs & 3 Copys of sheets 1 OF 2, SD1 OF 1 , A1 OF 10 , A2 OF 10, A3 OF 10, A5 OF 10, A7 OF 10, A8 OF 10, A10 OF 10, S3 OF 10 , S4 OF 10 , S5 OF 10 ,S6 OF 10 , S9 OF 10. Taken to Mike P.
Routing - FIRE1/5/2005 1/10/2005 FAIL
lacks FD access and hydrants. review faxed to architect.
1st review completed  1/10/2005 FAIL
failed plan check, plumbing, planning, structural and fire.
Routing Off Site - STRUCTURAL12/16/2004 1/5/2005 FAIL
Additional informaiton is required to be submitted for further review.
Contacted PDQ to take plans to outside engineering. kmm
Routing - PLAN CHECK12/28/2004 1/5/2005 FAIL
Plan review completed, sent correction report to architect requesting additional informaitom be submitted for further review prior to issuing permit.
Routing - PLUMBING12/23/2004 12/28/2004 FAIL
architectural and plumbing plans do not match, verify service sink requirements with structural plan reviewer, premise and vacuum r.p.s must be installed over a floor sink. roof drains may not connect to the overflow drains.
Routing - PLANNING12/22/2004 12/23/2004 FAIL
Failed. Conditions of approval for the DR have not been met.
Routing - Erosion and Sediment12/23/2004 12/23/2004 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS12/16/2004 12/22/2004 PASS
Routing - PLANNING Land Div12/16/2004 12/16/2004 PASS
Lot 10, Block 1 of Riverwalk Subdivision No. 1
Application received  12/16/2004  
Override - Parcel Holds  12/16/2004  
Override - Parcel Holds  12/16/2004  
Recd Pcfee & Taken To Pln CK  12/16/2004  
Plans ACCEPTED BY PLAN TECH  12/16/2004 DONE