Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD04-02964
StatusFinaled
Name ASBESTOS ABATEMENT INC
Site Address 420 S CAPITOL BLVD
Project NameWINTHER MUSIC DEMO
Customer Number 
ePlanReviewNo
Description
(WINTHER MUSIC-DEMOLITION) To demolish an existing 5,600 sq. ft. building which is currently adjacent to another building on the north and east walls per approved plans and DRH04-00309. The east wall is a common wall and will remain. Additional epoxy/adhesive anchors will be installed in the existing ledger board in this east wall on the adjacent tenant side. Special Inspection is required for epoxy/adhesive anchor installations. The east wall will now be the exterior wall of the adjacent building and it encloses unconditioned warehouse space. The north wall will be demolished and the adjacent building wall will remain. The adjacent building wall is an existing furred wall on the interior per architect. Bond set at $5,000.00. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/19/20055/20/20055/23/2005APASS
DetailsDave Hannah
corey; Phone #: ###-#### Internet Inspection Request from: Cathy Chileswork completed
Issue PAID IN FULL permit  3/8/2005  
Routing - PLAN CHECK2/28/2005 3/4/2005 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  3/4/2005 PASS
Permit Ready to Issue  3/4/2005 DONE
Telephone call  3/4/2005 DONE
Spoke with Korey and told him that permit is ready & fees////3/4/05 4:00pm BAS
Plan assigned to (JCB)12/23/2004 3/4/2005 PASS
3/4/2005 08:26:58 JCB - activity updated through activity BLDA022 from case BLD04-02964.
Routing - PLANNING2/23/2005 2/28/2005 PASS
Approve per DRH04-309
Routing - PLAN CHECK1/31/2005 2/23/2005 PEND
Plans to route to Planning again for approval.
1st review completed  1/31/2005 FAIL
Failed in Planning.
Routing - PLAN CHECK1/25/2005 1/31/2005 PEND
Permit approval pending on project approval by Planning and verification of the bond being set. Architect has stated that they will not know if the project will happen until Feb. 15th, 2005. Planning and Building divisions will be notified at that time.
Telephone call  1/31/2005  
Talked with architect Steve Turney concerning if this project was still going to proceed. He said he should know on February 15th, 2005.
Routing - PLANNING12/27/2004 1/25/2005 FAIL
Planning has been waiting for applicant to submit a letter from the adjacent property owner approving modifications to his building once demolition occurs. Owner has indicated he will be waiting until February 15, 2005 to pursue.

Approved under DRH04-00309.
Routing - Erosion and Sediment12/23/2004 12/27/2004 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS12/23/2004 12/23/2004 PASS
Application received  12/21/2004  
Recd Pcfee & Taken To Pln CK  12/21/2004 DONE
Plans ACCEPTED BY PLAN TECH  12/21/2004 DONE
DR staff level, per P&Z may route concurrent with BLD. Do not issue building permit until DR is approved. kmm
Fee Review-notes12/21/200412/21/2004