Third Notice BLD | 12/7/2005 | 12/7/2005 | 12/9/2005 | | DONE |
|
|
|
no current contact information
|
Second Notice | | 7/13/2005 | 12/7/2005 | | DONE |
|
|
|
|
First Notice | | 6/2/2005 | 7/13/2005 | | DONE |
|
|
|
|
BLD-Final | 6/2/2005 | 6/2/2005 | 6/2/2005 | | DONE |
|
|
|
Final, ok for perm. occ.
|
Permanent Occupancy | | 6/2/2005 | 6/2/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/2/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10618 issued 6-2-05 to Springhill Suites by Marriott.
|
BLD-Final | 5/25/2005 | 5/26/2005 | 5/26/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 3:53:08 PM. ok for temp ok for perm when others sign perm occ
|
Temporary occupancy | | | 5/26/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5245 issued 5-26-05 to the Springhill Suites by Marriott for the pool enclosure bldg.
|
FIRE-Final Inspection | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
Print Occupancy Form | | | 5/4/2005 | | DONE |
|
|
|
|
Issue & PRINT permit | | | 2/11/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/31/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/31/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/31/2005 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 12/23/2004 | 12/23/2004 | 1/28/2005 | | PASS |
|
|
|
1/28/2005 14:12:08 M_P - activity updated through activity BLDA022 from case BLD04-02967.
|
Routing - PLAN CHECK | 1/20/2005 | | 1/28/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/28/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/28/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/28/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/21/2005 | | |
|
|
|
Recewived Transmittal & 5 Letters 2 Copys of sheets A001,A103, A300, A312, A400A, A514, A600, A610, PS1, PS2, PS3, ME0.1 ME0.2, M0.2,M0.3,M2.7,M3.0,M3.1,M4.3, E2.0,E2.6 Taken to Mike P.
|
Routing - FIRE | 1/11/2005 | | 1/20/2005 | | PASS |
|
|
|
Review discussed with and comments faxed to, architect. No change required to comments for main hotel review (bld04-01267) relative to Haz Mat's. Per architect these are to be delivered on site by outside service firm. However, building review comments indicate the maximum limit of 10 lbs of highly toxic material allowed on site.
|
1st review completed | | | 1/20/2005 | | FAIL |
|
|
|
failed plan check.
|
Routing - PLAN CHECK | 12/29/2004 | | 1/11/2005 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 12/28/2004 | | 12/29/2004 | | PASS |
|
|
|
Approve per DRH04-44 / Mod.
|
Routing - PUBLIC WORKS | 12/23/2004 | | 12/28/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 12/28/2004 | | 12/28/2004 | | PASS |
|
|
|
ESC prior approval under ESC04-00738 is applicable.
|
Routing - PLUMBING | 12/28/2004 | | 12/28/2004 | | PASS |
|
|
|
per plans and 2003 upc
|
Plans ACCEPTED BY PLAN TECH | | | 12/23/2004 | | DONE |
|
|
|
Per Mike Phillips we will be using ESC04-00738 and grading bld04-01270 . The lighting, mech and envelope compliance certs. are ok as 81/2 x 11's. kmm
|
Routing - PLANNING Land Div | 12/23/2004 | | 12/23/2004 | | PASS |
|
|
|
Lots 19-22 combined into one parcel.
|
Plan routing begun/NEW & ADDTN | | | 12/23/2004 | | DONE |
|
|
|
|
Application received | | | 12/22/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/22/2004 | | |
|
|
|
|
Fee Review-notes | 12/22/2004 | 12/22/2004 | | | |
|
|
|
|