Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/2/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/29/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/29/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11107 issued 6-29-06 to the Hampton Estates.
|
Permanent Occupancy | | 6/27/2006 | 6/27/2006 | | DONE |
|
|
|
|
Temporary occupancy | | | 11/10/2005 | | DONE |
|
|
|
Temp. Occ. Cert. #5304 issued 11-10-05 to Hampton Estates.
|
BLD-Final | 11/4/2005 | 11/7/2005 | 11/7/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/4/2005 at 4:24:25 PM. Contact: ###-####. OK for Temp Occ......Perm Occ OK if all signatures and no bonds. ():
|
FIRE-Final Inspection | 11/4/2005 | 11/7/2005 | 11/7/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled.
|
Plan Reviewer's activity | | | 8/25/2005 | | DONE |
|
|
|
Non build agreement satified removed parcel hold.
|
BLD-Energy code compliance | 8/2/2005 | 8/3/2005 | 8/3/2005 | P | PASS |
Jim Sly
|
|
|
pete; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 8/1/2005 | 8/1/2005 | 8/1/2005 | P | PASS |
Jim Sly
|
|
|
PETE; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Foundation | 6/9/2005 | 6/9/2005 | 6/9/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/9/2005 at 11:01:50 AM. Contact: ###-####.
|
BLD-Footing | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/8/2005 at 6:11:56 AM. Contact: ###-####.
|
(F) Reprint permit | | | 5/25/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/24/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/7/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/7/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/7/2005 | | |
|
|
|
|
Telephone call | | | 4/7/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (M_P) | 12/28/2004 | 12/28/2004 | 4/6/2005 | | PASS |
|
|
|
4/6/2005 09:39:43 M_P - activity updated through activity BLDA022 from case BLD04-03007.
|
Routing - PLAN CHECK | 4/6/2005 | | 4/6/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/6/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/6/2005 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 3/31/2005 | | 4/5/2005 | | PASS |
|
|
|
final plat recorded 3/31/05
|
Routing - PLAN CHECK | 3/15/2005 | | 3/31/2005 | | |
|
|
|
Routing to Land Division.
|
Routing - PLAN CHECK | 3/11/2005 | | 3/15/2005 | | FAIL |
|
|
|
Waiting for different design for stairway enclosures, penetration of trusses not permitted.
|
Plan resubmittals received | | | 3/15/2005 | | |
|
|
|
Received calculations
|
Routing - PLANNING Land Div | 3/4/2005 | | 3/11/2005 | | FAIL |
|
|
|
MUST RECORD FINAL PLAT
|
Routing - PLANNING | 2/14/2005 | | 3/4/2005 | | PASS |
|
|
|
2/28/05 - Approved per DRH04-00073 Mod. #1. Approved per CUP04-00024 Mod #1 - copies for CUP submitted 3-4-2005.kg
|
Routing - PLUMBING | 2/7/2005 | | 2/14/2005 | | PASS |
|
|
|
see bld04-02991
|
Routing - PLAN CHECK | 1/27/2005 | | 2/7/2005 | | |
|
|
|
Routing to plumbing.
|
1st review completed | | | 1/27/2005 | | FAIL |
|
|
|
failed planning land div., planning, plumbing, and plan check.
|
Routing - FIRE | 1/21/2005 | | 1/27/2005 | | PASS |
|
|
|
|
Print permit w/o conditions | | | 1/21/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 1/5/2005 | | 1/21/2005 | | FAIL |
|
|
|
Plan review complete, sent correction report to architect requesting additional informatio be submitted for futher review prior to issuing permit.
|
Routing - PLANNING | 1/4/2005 | | 1/5/2005 | | FAIL |
|
|
|
DRH04-00073 Sarah Schafer
CUP04-00024 Karen Gallagher
Failed both the DR and the CUP review. Landscape plan needs to be prepared by a licensed landscape architect and address the vegetation along Hampton Street. The trash enclosures are required to be CMU and the detail shows cedar fencing. No bike racks are shown. There are no notes regarding the amenities and Karen still needs documentation showing that a minimum of 30% of the site is open space.
|
Routing - Erosion and Sediment | 1/3/2005 | | 1/4/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLUMBING | 1/4/2005 | | 1/4/2005 | | FAIL |
|
|
|
see bld04-02991 for comments
|
Routing - PUBLIC WORKS | 12/28/2004 | | 1/3/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 12/28/2004 | | 12/28/2004 | | FAIL |
|
|
|
Do not issue permit until final plat of O'Neal Sub is recorded
|
Plan routing begun/NEW & ADDTN | | | 12/28/2004 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/28/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/28/2004 | | DONE |
|
|
|
|
Application received | | | 12/27/2004 | | |
|
|
|
|
Fee Review-notes | 12/28/2004 | 12/28/2004 | | | |
|
|
|
|