Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/2/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/29/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/29/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11110 issued 6-29-06 to the Hampton Estates
|
Permanent Occupancy | | 6/27/2006 | 6/27/2006 | | DONE |
|
|
|
|
BLD-Final | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/16/2006 at 8:17:23 AM. Contact: ###-####. OK for Temp Occ. OK for Perm when Code Enforce Perms
|
FIRE-Final Inspection | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
BLD-Final | 3/15/2006 | 3/16/2006 | 3/16/2006 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/15/2006 at 10:03:20 AM. Contact: ###-####.
|
Temporary occupancy | | | 3/16/2006 | | DONE |
|
|
|
Temp. Occ. cert. # 5384 issued 3-16-06 to the Hampton Estates.
|
FIRE-Final Inspection | 3/15/2006 | 3/15/2006 | 3/15/2006 | P | FAIL |
Troy Cobbley
|
|
|
doors are not closing on apartments
|
BLD-Energy code compliance | 12/27/2005 | 12/29/2005 | 12/29/2005 | A | PASS |
Tom Arcoraci
|
|
|
pete; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 12/27/2005 | 12/28/2005 | 12/28/2005 | A | FAIL |
Tony Young
|
|
|
pete; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa need to nail hangers on hip girder on south ends
|
BLD-Footing | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/9/2005 at 9:12:39 AM. Contact: ###-####.
|
Plan Reviewer's activity | | | 8/25/2005 | | DONE |
|
|
|
Non build agreement satified removed parcel hold.
|
Issue PAID IN FULL permit | | | 8/25/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/8/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2005 | | |
|
|
|
|
Telephone call | | | 4/8/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 4/6/2005 | | 4/6/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/6/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/6/2005 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 3/31/2005 | | 4/5/2005 | | PASS |
|
|
|
final plat recorded 3/31/05
|
Routing - PLAN CHECK | 3/15/2005 | | 3/31/2005 | | |
|
|
|
Routing to Land Division.
|
Routing - PLAN CHECK | 3/11/2005 | | 3/15/2005 | | FAIL |
|
|
|
Waiting for different design for stairway enclosures, penetration of trusses not permitted.
|
Plan resubmittals received | | | 3/15/2005 | | |
|
|
|
Received calculations
|
Routing - PLANNING Land Div | 3/4/2005 | | 3/11/2005 | | FAIL |
|
|
|
MUST RECORD FINAL PLAT
|
Routing - PLANNING | 2/14/2005 | | 3/4/2005 | | PASS |
|
|
|
2/28/05 - Approved per DRH04-00073 Mod. #1. Approved per CUP04-00024 Mod #1 - copies for CUP submitted 3-4-2005.kg
|
Routing - PLUMBING | 2/7/2005 | | 2/14/2005 | | PASS |
|
|
|
see bld04-02991
|
Routing - PLAN CHECK | 1/27/2005 | | 2/7/2005 | | |
|
|
|
Routing to plumbing.
|
1st review completed | | | 1/27/2005 | | FAIL |
|
|
|
failed planning land div., planning, plumbing, and plan check.
|
Routing - FIRE | 1/21/2005 | | 1/27/2005 | | PASS |
|
|
|
|
Print permit w/o conditions | | | 1/21/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 1/5/2005 | | 1/21/2005 | | FAIL |
|
|
|
Plan review complete, sent correction report to architect requesting additional informatio be submitted for futher review prior to issuing permit.
|
Routing - PLANNING | 1/4/2005 | | 1/5/2005 | | |
|
|
|
DRH04-00073 Sarah Schafer
CUP04-00024 Karen Gallagher
Failed both the DR and the CUP review. Landscape plan needs to be prepared by a licensed landscape architect and address the vegetation along Hampton Street. The trash enclosures are required to be CMU and the detail shows cedar fencing. No bike racks are shown. There are no notes regarding the amenities and Karen still needs documentation showing that a minimum of 30% of the site is open space.
|
Routing - PLUMBING | 1/4/2005 | | 1/4/2005 | | FAIL |
|
|
|
see bld04-02991 for comments
|
Routing - Erosion and Sediment | 1/3/2005 | | 1/4/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 12/28/2004 | | 1/3/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 12/28/2004 | | 12/28/2004 | | FAIL |
|
|
|
Do not issue permit until final plat of O'Neal Sub is recorded
|
Recd Pcfee & Taken To Pln CK | | | 12/28/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/28/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 12/28/2004 | | DONE |
|
|
|
|
Application received | | | 12/27/2004 | | |
|
|
|
|
Fee Review-notes | 12/28/2004 | 12/28/2004 | | | |
|
|
|
|