Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/2/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/29/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/29/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11113 issued 6-29-06 to the Hampton Estates.
|
Permanent Occupancy | | 6/27/2006 | 6/27/2006 | | DONE |
|
|
|
|
Temporary occupancy | | | 3/9/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5380 issued 3-9-06 to the Hampton Estates 4-plex.
|
BLD-Final | 3/7/2006 | 3/8/2006 | 3/8/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/7/2006 at 2:40:21 PM. Contact: ###-####. OK for Temp Occ.......OK for Perm Occ. when Code Enf Perms.
|
FIRE-Final Inspection | 3/7/2006 | 3/8/2006 | 3/8/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Energy code compliance | 12/13/2005 | 12/14/2005 | 12/14/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/13/2005 at 10:09:23 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/12/2005 at 2:32:58 PM. Contact: ###-####.
|
BLD-Foundation | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/31/2005 at 7:43:27 AM. Contact: ###-####.
|
BLD-Footing | 10/27/2005 | 10/27/2005 | 10/27/2005 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/27/2005 at 10:08:40 AM. Contact: ###-####.ok per jim sly
|
Plan Reviewer's activity | | | 8/25/2005 | | DONE |
|
|
|
Non build agreement satified removed parcel hold.
|
Issue PAID IN FULL permit | | | 8/25/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/11/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/11/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/11/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/11/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (M_P) | 12/28/2004 | 12/28/2004 | 4/6/2005 | | PASS |
|
|
|
4/6/2005 13:14:23 M_P - activity updated through activity BLDA022 from case BLD04-03013.
|
Routing - PLAN CHECK | 4/6/2005 | | 4/6/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/6/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/6/2005 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 3/31/2005 | | 4/5/2005 | | PASS |
|
|
|
final plat recorded 3/31/05
|
Routing - PLAN CHECK | 3/15/2005 | | 3/31/2005 | | |
|
|
|
Routing to Land Division.
|
Routing - PLAN CHECK | 3/11/2005 | | 3/15/2005 | | FAIL |
|
|
|
Waiting for different design for stairway enclosures, penetration of trusses not permitted.
|
Plan resubmittals received | | | 3/15/2005 | | |
|
|
|
Received calculations
|
Routing - PLANNING Land Div | 3/4/2005 | | 3/11/2005 | | FAIL |
|
|
|
MUST RECORD FINAL PLAT
|
Routing - PLANNING | 2/14/2005 | | 3/4/2005 | | PASS |
|
|
|
2/28/05 - Approved per DRH04-00073 Mod. #1. Approved per CUP04-00024 Mod #1 - copies for CUP submitted 3-4-2005.kg
|
Routing - PLUMBING | 2/7/2005 | | 2/14/2005 | | PASS |
|
|
|
see bld04-02991
|
Routing - PLAN CHECK | 1/27/2005 | | 2/7/2005 | | |
|
|
|
Routing to plumbing.
|
1st review completed | | | 1/27/2005 | | FAIL |
|
|
|
failed planning land div., planning, plumbing, and plan check.
|
Routing - FIRE | 1/21/2005 | | 1/27/2005 | | PASS |
|
|
|
|
Print permit w/o conditions | | | 1/21/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 1/5/2005 | | 1/21/2005 | | FAIL |
|
|
|
Plan review complete, sent correction report to architect requesting additional informatio be submitted for futher review prior to issuing permit.
|
Routing - PLANNING | 1/4/2005 | | 1/5/2005 | | FAIL |
|
|
|
Failed both the DR and the CUP review. Landscape plan needs to be prepared by a licensed landscape architect and address the vegetation along Hampton Street. The trash enclosures are required to be CMU and the detail shows cedar fencing. No bike racks are shown. There are no notes regarding the amenities and Karen still needs documentation showing that a minimum of 30% of the site is open space.
|
Routing - PLUMBING | 1/4/2005 | | 1/4/2005 | | FAIL |
|
|
|
see bld04-02991 for comments
|
Routing - Erosion and Sediment | 1/3/2005 | | 1/4/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 12/28/2004 | | 1/3/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 12/28/2004 | | 12/28/2004 | | FAIL |
|
|
|
Do not issue permit until final plat of O'Neal Sub is recorded
|
Recd Pcfee & Taken To Pln CK | | | 12/28/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/28/2004 | | DONE |
|
|
|
|
Application received | | | 12/27/2004 | | |
|
|
|
|
Fee Review-notes | 12/28/2004 | 12/28/2004 | | | |
|
|
|
|