Third Notice BLD | 6/14/2006 | 6/14/2006 | 11/7/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/25/2006 | 5/25/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/12/2006 | 5/25/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/12/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11018 issued 5-12-06 to the Idaho Shakespeare Festival warehouse.
|
BLD-Final | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PASS |
Dave Hannah
|
|
|
kevin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for perm occ
|
Permanent Occupancy | | 5/10/2006 | 5/10/2006 | | DONE |
|
|
|
|
BLD-Final | 5/8/2006 | 5/9/2006 | 5/9/2006 | P | FAIL |
Dave Hannah
|
|
|
Kevin, ###-#### needs signage at restrooms and mirrir lowered
|
FIRE-Final Inspection | 5/8/2006 | 5/9/2006 | 5/9/2006 | A | PASS |
Forrest France
|
|
|
Inspection passed, fire life safety is acceptable. No permit card available on site for sign-off at the time of inspection.
|
Code Occupancy Approval | 5/9/2006 | 5/9/2006 | 5/9/2006 | P | PASS |
Wm. Michael Meloy
|
|
|
compliance met.
|
FIRE-Final Inspection | 5/1/2006 | 5/2/2006 | 5/2/2006 | A | DONE |
Forrest France
|
|
|
Duplicate inspection request already completed.
|
FIRE-Final Inspection | 5/1/2006 | 5/2/2006 | 5/2/2006 | A | FAIL |
Forrest France
|
|
|
The project related fire sprinkler permit must be finaled prior to life safety approval, some items noted on walk through include exit sign at the SW door needs repaired, manual flush bolts on the inactive leaf at the north exit are not allowed, need to test emergency lights, provide lever hardware at the paint room door, provide approved building plans and review notes at the next inspection, not all items reviewed at this time.
|
BLD-Framing/Rough-in | 2/17/2006 | 2/17/2006 | 2/17/2006 | P | PASS |
Tom Arcoraci
|
|
|
ceiling insp kevin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 2/15/2006 | 2/15/2006 | 2/15/2006 | P | FAIL |
Dave Hannah
|
|
|
Kevin -- for ceiling; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong fail wire not 1in6 and one side rivited
|
BLD-Framing/Rough-in | 1/9/2006 | 1/10/2006 | 1/11/2006 | P | PASS |
Dave Hannah
|
|
|
kevin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover int walls
|
BLD-Framing/Rough-in | 12/29/2005 | 12/30/2005 | 12/30/2005 | P | PART |
Tony Young
|
|
|
kevin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover interior single walls,, need a fix /detail from architect on fire blocking and window openings,,, etc,,my note is on plans
|
BLD-Aging Inspection | 10/5/2005 | 10/5/2005 | 10/5/2005 | | PASS |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 7/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/16/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/16/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/16/2005 | | DONE |
|
|
|
Spoke with Jackie and told her that permit is ready & fees///6/16/05 1:30pm BAS
|
Plan assigned to (M_P) | 12/30/2004 | | 6/15/2005 | | PASS |
|
|
|
6/15/2005 09:47:26 M_P - activity updated through activity BLDA022 from case BLD04-03034.
|
Routing - PLAN CHECK | 6/14/2005 | | 6/15/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/15/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/15/2005 | | DONE |
|
|
|
|
Routing - FIRE | 6/9/2005 | | 6/14/2005 | | PASS |
|
|
|
resubmittal acceptable. Revised comments faxed to architect.
|
Routing - PLAN CHECK | 1/31/2005 | | 6/9/2005 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 6/6/2005 | | DONE |
|
|
|
Received 1 Transmittal,2 Structural Calcs,& 2 Copys of sheets A1,A2,A3,A4,M1,M2,M3,M4 Taken to Mike P.
|
1st review completed | | | 1/31/2005 | | FAIL |
|
|
|
failed plan review and fire.
|
Routing - FIRE | 1/25/2005 | | 1/31/2005 | | FAIL |
|
|
|
lacks information regarding haz mat's, storage, and painting op's. Review faxed to architect.
|
Routing - PLAN CHECK | 1/10/2005 | | 1/25/2005 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 1/4/2005 | | 1/10/2005 | | PASS |
|
|
|
Approved.
|
Routing - Erosion and Sediment | 1/3/2005 | | 1/4/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Plan resubmittals received | | | 1/3/2005 | | DONE |
|
|
|
Received ESC waiver letter with application and letter to Karen G. Taken to Mike P.
|
Routing - PUBLIC WORKS | 12/30/2004 | | 1/3/2005 | | PASS |
|
|
|
|
Application received | | | 12/29/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/29/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/29/2004 | | DONE |
|
|
|
ok per Mike P. Lighting compliance is on 81/2 X 11 not plan size & needs esc application with waiver request letter.
|