Case Summary (BLD) | | | 7/19/2010 | | DONE |
|
|
|
|
BLD-Final | 10/4/2006 | 10/5/2006 | 10/5/2006 | A | DONE |
Dave Hannah
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Final | 10/5/2006 | 10/5/2006 | 10/5/2006 | P | PASS |
Dave Hannah
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
DOC - Permit Finaled | 10/5/2006 | 10/5/2006 | 10/5/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Grading Inspection | 10/5/2006 | 10/5/2006 | 10/5/2006 | | DONE |
|
|
|
The rough grading and drainage has been completed. However, revegetation and the drainage ponds have not been completed. For this the engineer has recommended a bond of $4,000.00. Upon receipt of this bond the grading and drainage is conditionally approved
|
BLD-Conference | 10/3/2006 | 10/3/2006 | 10/3/2006 | P | DONE |
Dave Hannah
|
|
|
call 1 hour prior to going; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Final | 9/29/2006 | 10/2/2006 | 10/2/2006 | A | NR |
Tony Young
|
|
|
don; Phone #: ###-#### Please call gate/garage code Internet Inspection Request from: Cathy Chiles need trades,, hillside,, etc.. phone conf. w/ Don on this
|
BLD-Energy code compliance | 12/7/2005 | 12/8/2005 | 12/8/2005 | A | PART |
Tony Young
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa need to finish or justify frame around fireplaces,, also need to re-inspect mech for fireplace
|
BLD-Energy code compliance | 12/5/2005 | 12/6/2005 | 12/6/2005 | P | NR |
Tony Young
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore need mech pass 1st
|
BLD-Framing/Rough-in | 11/7/2005 | 11/8/2005 | 11/8/2005 | P | PART |
Tony Young
|
|
|
don ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie c/n posted,, ok to insulate,, will need to get more trades
|
BLD-Framing/Rough-in | 11/7/2005 | 11/7/2005 | 11/7/2005 | P | NR |
Tony Young
|
|
|
don//plans on on the main level on top of fireplace; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa need seal pack,, finish framing around b-vent,, etc
|
Plan resubmittals received | | | 8/30/2005 | | |
|
|
|
Received resubmittal of plans and structural calculations for revised second floor framing plan. Routed to Steve M.
|
BLD-Framing/Rough-in | 8/17/2005 | 8/18/2005 | 8/18/2005 | P | PART |
Mike Jordan
|
|
|
shear wall//don; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. All hold downs in place as per plans. All strapping in place and nailed as per plans. TONY- Check your box for the paper work approving the use og staples, 36 guage used 1 7/8 inches long. Gave ok to cover based on what contractor noted and noting that the patern was still over what he had noted. Paper work should be faxed by 8-19-05. Also had paper work on site.
|
BLD-Framing/Rough-in | 8/12/2005 | 8/15/2005 | 8/15/2005 | A | FAIL |
Tony Young
|
|
|
shear wall//call for access code for gate//don; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa need letter from structural engineer on " OK AS BUILT" or do as plans,, lots of detail,,, conf. only
|
BLD-Framing/Rough-in | 5/2/2005 | 5/3/2005 | 5/3/2005 | A | PART |
Tony Young
|
|
|
under floor inspection//don; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
wip on underfloor,, point loads in/ marked 5/3/2005 12:26:51 PM
|
Case Summary (BLD) | | | 4/25/2005 | | |
|
|
|
|
BLD-Footing | 4/5/2005 | 4/6/2005 | 4/6/2005 | A | PART |
Tony Young
|
|
|
don ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Grading Inspection | 4/4/2005 | 4/4/2005 | 4/4/2005 | | DONE |
|
|
|
footing subgrade approved by the geotyechnical engineer
|
PubWorks Subgrade Approval | 1/26/2005 | 1/26/2005 | 4/4/2005 | | DONE |
|
|
|
A letter from the applicants geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####
|
Override - Activity Holds | | | 3/18/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/18/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 2/11/2005 | | 3/15/2005 | | PASS |
|
|
|
3/15/2005 13:54:24 SAM - activity updated through activity BLDA022 from case BLD05-00097.
|
Routing - FIRE | 3/15/2005 | | 3/15/2005 | | PASS |
|
|
|
Approved without fire sprinklers based on the following repsonse from Dave Miller. "The Fire Department finds that the water supply and access requirements stipulated for this project by the direction of Council appear to have been sufficiently satisfied for Fire to issue a preliminary approval. Therefore, Fire has no objection to the plat being finalized or to building construction permits being processed. Please note that the final acceptance of fire hydrants and any unfinished or temporary features is not possible at this time. In the interest of customer service however the fire department can issue this preliminary approval. Please note that this preliminary approval applies only to water supply and access requirements of the IFC. The requirements of other City departments, codes, permits, and ordinances (including the IFC) may not yet be completely satisfied. Specific items for which final approval has not been issued include, but are not limited to, temporary street signs; temporary access roads; actual building construction type, code requirements, and area; and hydrant depth and clearance as may be affected by landscaping."
|
Case Summary (BLD) | | | 3/15/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/15/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/15/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 3/15/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 3/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/15/2005 | | DONE |
|
|
|
called cory ###-#### advised permit is ready & quoted fees///JRR
|
Routing - PLAN CHECK | 1/31/2005 | | 3/8/2005 | | PASS |
|
|
|
Plan review is done. Plans are waiting for Fire to pass.
|
Plan Reviewer's activity | | | 2/15/2005 | | DONE |
|
|
|
2/15/05 16:35 I e-mailed Dave Miller to find out the progress of the fire department approval.
|
Routing - Erosion and Sediment | 2/12/2005 | | 2/14/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 1/28/2005 | | 1/31/2005 | | FAIL |
|
|
|
1/28/05 - appears it will require AS due to inadequate FD access. Refered to D. Miller to review with architect. Dave will advise decision on AS within next day or two.
1/31/05 - emai from Dave Miller : "I just met with an architect on a proposed house for this lot. There are several problems. First there appears to be a non-build agreement on Lots 1 & 3 which has not yet been released. Second, there is no SAT memo for Lots 2 & 4. Lastly, the aforementioned house shows a sub standard fire access lane. The applicant's choices are to make the driveway 20 ft wide along the entire length and expand the turnaround to fire code standards; or fire sprinkler the house. Of course, these choices are mute until the SUB conditions of issuing a SAT memo and releasing the non-build are satisfied."
|
Routing - Erosion and Sediment | 1/28/2005 | | 1/28/2005 | | FAIL |
|
|
|
ESC plan not per requirements outlined in BMC 8-17. Informed PD. Checklist completed.
|
Routing - PLANNING | 1/26/2005 | | 1/27/2005 | | PASS |
|
|
|
Routed to Carl Miller per CFH02-00012.
|
Routing - PUBLIC WORKS GRADING | 1/20/2005 | | 1/26/2005 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS | 1/26/2005 | | 1/26/2005 | | PASS |
|
|
|
|
Application received | | | 1/19/2005 | | |
|
|
|
|