Permit Information
Permit NumberBLD05-00116
StatusFinaled
Name TRIP TAYLOR BOOKSTORE
Site Address 210 N 10TH ST
Project NameTAYLOR BLDG
Customer Number 
ePlanReviewNo
Description
(TRIP TAYLOR BOOK STORE) This building is NOT fire sprinklered. Interior nonstructural demolition work was done under permit BLD05-00284. To combine 2 existing tenant spaces into one 2,262 square foot, 2 story, retail sales tenant space (1,381 square foot 1st story and 881 square foot 2nd story). Work is to include 2 restrooms accessible to the disabled, an open stairway to serve the 2nd story, a 1-hr enclosed stairway to serve the 2nd story, new beams, new columns, new floor joists, exterior wall infills, and interior finishes all per approved drawings, engineering, and plan review report on file. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD2/7/20062/7/20064/3/2006 DONE
Second Notice has not been responded to.
Second Notice BLD1/13/20061/13/20062/7/2006 DONE
First Notice has not been responded to.
First Notice 12/6/20051/13/2006 DONE
Third Notice BLD12/6/200512/6/20051/10/2006 DONE
did not send as no info on GC so started with 1st notice with Architect///1/10/06
Second Notice BLD7/13/20057/13/200512/6/2005 DONE
First Notice has not been responded to.
First Notice 6/1/20057/13/2005 DONE
Permanent occupancy  6/1/2005 DONE
Perm. Occ. Cert. # 10610 issued 6-1-05 to the Trip Taylor Book Store.
BLD-Final5/27/20055/31/20055/31/2005APASS
DetailsDave Hannah
shawn; Phone #: ###-#### Note: please call 1/2 hr prior to inspection Internet Inspection Request from: Cathy Chiles ok for perm occ
Permanent Occupancy 5/31/20055/31/2005 DONE
Details
FIRE-Final Inspection5/27/20055/27/20055/27/2005PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final5/24/20055/25/20055/25/2005PNR
DetailsDave Hannah
sean; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa needs other trades sign off
FIRE-Final Inspection5/24/20055/25/20055/25/2005AFAIL
DetailsForrest France
Need to install one fire ext. per floor level. Provide emergency lighting for stair landing at ground floor east exit. Test and verify operation of two duct smoke detectors. Provide correct building address. Provide approved sign above main entry/exi
BLD-Framing/Rough-in4/11/20054/12/20054/12/2005APASS
DetailsDave Hannah
shawn ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie stairs ok all fire blocking ok to cover 4/12/2005 9:29:40 AM
BLD-Energy code compliance4/7/20054/8/20054/8/2005APART
DetailsDave Hannah
shawn; Phone #: ###-#### Internet Inspection Request from: Barbara Moorerest room walls 4/8/2005 9:28:07 AM
BLD-Framing/Rough-in4/6/20054/7/20054/7/2005PPART
DetailsDave Hannah
shawn; Phone #: ###-#### Internet Inspection Request from: Barbara Moore need fire blocking on ext walls of restrooms note both sets of stairs are wrong and need tobe rebuilt ok to rock columns and office area 4/7/2005 2:17:47 PM
Inspection Record Card- Bld  3/8/2005 DONE
Print Occupancy Form  3/8/2005 DONE
Telephone call  3/8/2005 DONE
glenn robinette ###-#### and earl gafford at ###-#### is ready
Issue PAID IN FULL permit  3/8/2005  
Plan assigned to (CJW)1/25/2005 3/7/2005 PASS
3/7/2005 14:40:07 CJW - activity updated through activity BLDA022 from case BLD05-00116.
Routing - PLAN CHECK2/10/2005 3/7/2005 PASS
Drawings failed 1st resubmittal review. Drawings approved after 2nd resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  3/7/2005 DONE
Permit Ready to Issue  3/7/2005  
Plan resubmittals received  3/3/2005 DONE
Received resubmittals including a cover letter, 2 copies of structural engineering calcs, and 3 copies of sheets A3.0, A3.1, S1.0 and S2.0 and forwarded them to Carl W.
Plan resubmittals received  2/23/2005 DONE
Received Transmittal ,1 Response sheet, 2 Responses to structural cals, & 3 Copys of sheets A3.0,A3.1,A4.0,A4.1,S1.0,S2.0,M1.0,M2.0,M3.0,E0,E1 Taken to Carl W.
Routing - FIRE2/9/2005 2/10/2005 PASS
1st review completed  2/10/2005 FAIL
failed plan review
Routing - PLAN CHECK2/4/2005 2/9/2005 FAIL
The IBC plan review was started on February 4, 2005 and was finished on February 9, 2005. Resubmitted drawings were required. See the plan review report.
Routing - PLUMBING2/4/2005 2/4/2005 PASS
per plans and 2003 upc
Routing - PLANNING1/27/2005 2/4/2005 PASS
Approved.
Routing - PUBLIC WORKS1/25/2005 1/27/2005 PASS
Plan resubmittals received  1/25/2005 DONE
Received Transmittal , 3 Structural Calcs, & 3 Copys of sheets S1.0, S2.0 Inserted into plans and taken back to Marlene..
Plan resubmittals received  1/24/2005 DONE
Received 3 Copys of sheets M1.0, M2.0, M3.0 Have been inserted into plans & taken back to Marlene to route.
Plans ACCEPTED BY PLAN TECH  1/21/2005 DONE
MEC COMP SHOWS 2001 CODE MAYBE A TYPO ERROR AS THE LIGHTING SHOWS 2003 CODE.
Application received  1/20/2005  
Recd Pcfee & Taken To Pln CK  1/20/2005 DONE