Agreement of Future work | 4/21/2005 | 4/15/2007 | 5/28/2008 | | DONE |
Jason Blais
|
|
|
Upgrade Agreement to Sprinkler Warehouse #1 and the North Loading Dock area within a 2 year time frame. Openings in the existing 2-hour rated fire wall between the office and Warehouse #1 to also be addressed. See attached document to the case.
2/21/07 Sent letter to owner stating the Upgrade Agreement will expire on April 15, 2007. No records or permits on file indicating any of the work or issues have been addressed.
6/15/07 Refer to permit FIR07-00374 for fire sprinkler permit. Still needs Building Permit submittal to be turned in for some issues. Should be coming soon.
6/20/07 Zoning Certificate for new sprinkler riser room addition approved on 6/19/07 under CZC07-00154. Building permit now needs to be turned in for review and approval.
2/13/08 Permits to complete the work have been applied for and reviewed. Applicant has not picked up and paid for the Building Permit. Bob Archibald has met with the tenant and they will be picking up their permit.
5/28/07 Permits to complete the upgrade work are finaled. Refer to permits BLD07-01957, FIR07-00929, and FIR08-00122.
|
Case Summary (BLD) | | | 9/7/2007 | | |
|
|
|
|
BLD-Final | 9/6/2005 | 9/6/2005 | 9/6/2005 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/6/2005 at 7:51:08 AM. Contact: ###-####. Final ok.
|
FIRE-Final Inspection | 8/31/2005 | 8/31/2005 | 8/31/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety is satisfactory.
|
FIRE-Final Inspection | 8/29/2005 | 8/29/2005 | 8/29/2005 | P | FAIL |
Forrest France
|
|
|
Remove locking hardware at SW door, provide additional fire extinguisher as discussed.
|
FIRE-Final Inspection | 8/25/2005 | 8/26/2005 | 8/26/2005 | P | CANC |
Forrest France
|
|
|
Spoke with Steve to reschedule inspection for Monday the 29th.
|
Code Occupancy Approval | 8/26/2005 | 8/26/2005 | 8/26/2005 | P | PASS |
Scott M.Brown
|
|
|
OK FINAL SIGNED OFF
|
BLD-Final | 8/25/2005 | 8/25/2005 | 8/25/2005 | P | NR |
Jim Sly
|
|
|
please call 15 min prior to meet///steve; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Talked to Steve K2......He needs Fire Life/Safety and Zoning signed off.......and Final affidavit from Special insp agency for structural CMU, welding, epoxy, etc.
|
BLD-Aging Inspection | 7/28/2005 | 7/28/2005 | 7/28/2005 | | NR |
Jim Sly
|
|
|
Called....WIP
|
Inspection Record Card- Bld | | | 4/27/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/27/2005 | | DONE |
|
|
|
lft vm with skip wingfield ###-#### - that permit and fees are ready to be picked up
|
Issue PAID IN FULL permit | | | 4/27/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/26/2005 | | 4/26/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 4/25/2005 | | 4/26/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Plan assigned to (JCB) | 1/25/2005 | | 4/26/2005 | | PASS |
|
|
|
4/26/2005 14:17:29 JCB - activity updated through activity BLDA022 from case BLD05-00127.
|
Plan resubmittals received | | | 4/25/2005 | | DONE |
|
|
|
Received Transmittal & 1 Discription & History of buldg book Taken to Jason B.
|
Routing - PLAN CHECK | 4/22/2005 | | 4/25/2005 | | PEND |
|
|
|
Plans to route to Erosion/Sediment Control.
|
Telephone call | | | 4/22/2005 | | DONE |
|
|
|
Contacted Dave Bliss of Trout Architects to obtain final code analysis for buildings on this site. He said it would be submitted in on Monday, 4/25/2005.
|
Routing - PLAN CHECK | 3/4/2005 | | 4/22/2005 | | FAIL |
|
|
|
Still need final code analysis for buildings on the site and still need ESC permit and information. Contacted architect and contractor.
|
Telephone call | | | 4/21/2005 | | DONE |
|
|
|
Called Skip at K2 Construction concerning the required ESC permit. No information pertaining to ESC has been provided with the resubmittals. He said he would look into it.
|
Plan resubmittals received | | | 4/21/2005 | | DONE |
|
|
|
Resubmittals received and forwarded to Jason: Comment sheet addressing plan review revisions, 1 letter of transmittal requesting extended time for code upgrade, and 2 copies of plan sheet 2.0.
|
Meeting | | | 4/6/2005 | | |
|
|
|
Met with Dave Bliss of Trout Architects concerning some code issues with the code analysis provided for the buildings on the site. Some options and solutions were discussed such as downgrading construction types and expanding the sprinkler system into some building areas. Mr. Bliss said he would take the information to the owner and get back to me. It appears as if an upgrade agreement may be requested for expanding the sprinkler system into non-sprinklered building areas.
|
Telephone call | | | 4/5/2005 | | DONE |
|
|
|
Dave Bliss called back and a meeting to discuss code analysis will occur on 4/6/05.
|
Telephone call | | | 4/4/2005 | | DONE |
|
|
|
Called architect representative Dave Bliss concerning some issues with the code analysis presented. He said he would get with Steve Trout and get back to me tomorrow to set up a meeting.
|
Plan resubmittals received | | | 4/3/2005 | | |
|
|
|
Received 2 Responses, 2 site plan ,2 office floor plan,2 north elevation,2 S1 & S2 sheets 1 S4,S5,SHEET , 1revised exterior,1 truck repair elevation view,2 plan view sheets,1 warehouse elevation,1 specifications,1 floor plan 1of 3,3 of 3,2 of 3, Taken to Jason B.
|
1st review completed | | | 3/4/2005 | | FAIL |
|
|
|
failed plan chec and ESC.
|
Routing - FIRE | 2/24/2005 | | 3/4/2005 | | PASS |
|
|
|
approved subject to conditions-review faxed to applicant
|
Routing - PLAN CHECK | 1/28/2005 | | 2/24/2005 | | FAIL |
|
|
|
Plan review report sent and faxed to design engineer and to contractor. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Plan resubmittals requested | | | 2/24/2005 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - Erosion and Sediment | 2/24/2005 | | 2/24/2005 | | FAIL |
|
|
|
Talked with Steve Webb of Erosion/Sediment Control and he stated that an ESC Permit is required. Left message with Skip Wingfield of K2 Construction concerning this requirement.
|
Plan resubmittals received | | | 2/23/2005 | | DONE |
|
|
|
Received 2 Structural Calcs. Taken to Jason B.
|
Routing - PLANNING | 1/27/2005 | | 1/28/2005 | | PASS |
|
|
|
Sarah Schafer CZC05-00007
Approved per CZC05-00007.
|
Routing - PUBLIC WORKS | 1/25/2005 | | 1/27/2005 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/24/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/24/2005 | | DONE |
|
|
|
Ok to take in plans per Marlene before the DRH goes through, as per Evelyn G.
|
Application received | | | 1/21/2005 | | |
|
|
|
|