Permit NumberBLD05-00127
StatusFinaled
Name MERCHANTS MOVING & STORAGE
Site Address 11345 W EXECUTIVE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
(MERCHANTS MOVING & STORAGE) To construct 81 lineal feet of CMU wall that is 14 feet in height with three roll up overhead doors and a 3' man door to enclose the north side of an existing 6,490 sq. ft. storage shed building for an existing warehouse tenant per approved engineered plans and CZC05-00007. This building is separated from adjacent buildings on each side (east and west) with existing 2-hour rated fire walls with 90 minute rated doors. Work will also include some new metal siding above wall, some new pipe bollards, and some electrical work. Special Inspection required for structural masonry, structural welding, and for epoxy/adhesive anchor installations. No steel storage racks exceeding 8' in height in this area. This building was originally constructed in Ada County and later annexed into Boise City. An Upgrade Agreement is on file for this tenant. This is a Scope of Work Permit. A Letter of Completion is to be issued when completed and approved. NOTE: This building is fully fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Agreement of Future work4/21/20054/15/20075/28/2008 DONE
DetailsJason Blais
Upgrade Agreement to Sprinkler Warehouse #1 and the North Loading Dock area within a 2 year time frame. Openings in the existing 2-hour rated fire wall between the office and Warehouse #1 to also be addressed. See attached document to the case.
2/21/07 Sent letter to owner stating the Upgrade Agreement will expire on April 15, 2007. No records or permits on file indicating any of the work or issues have been addressed.
6/15/07 Refer to permit FIR07-00374 for fire sprinkler permit. Still needs Building Permit submittal to be turned in for some issues. Should be coming soon.
6/20/07 Zoning Certificate for new sprinkler riser room addition approved on 6/19/07 under CZC07-00154. Building permit now needs to be turned in for review and approval.
2/13/08 Permits to complete the work have been applied for and reviewed. Applicant has not picked up and paid for the Building Permit. Bob Archibald has met with the tenant and they will be picking up their permit.
5/28/07 Permits to complete the upgrade work are finaled. Refer to permits BLD07-01957, FIR07-00929, and FIR08-00122.
Case Summary (BLD)  9/7/2007  
BLD-Final9/6/20059/6/20059/6/2005PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/6/2005 at 7:51:08 AM. Contact: ###-####. Final ok.
FIRE-Final Inspection8/31/20058/31/20058/31/2005PPASS
DetailsForrest France
Fire life safety is satisfactory.
FIRE-Final Inspection8/29/20058/29/20058/29/2005PFAIL
DetailsForrest France
Remove locking hardware at SW door, provide additional fire extinguisher as discussed.
FIRE-Final Inspection8/25/20058/26/20058/26/2005PCANC
DetailsForrest France
Spoke with Steve to reschedule inspection for Monday the 29th.
Code Occupancy Approval8/26/20058/26/20058/26/2005PPASS
DetailsScott M.Brown
OK FINAL SIGNED OFF
BLD-Final8/25/20058/25/20058/25/2005PNR
DetailsJim Sly
please call 15 min prior to meet///steve; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Talked to Steve K2......He needs Fire Life/Safety and Zoning signed off.......and Final affidavit from Special insp agency for structural CMU, welding, epoxy, etc.
BLD-Aging Inspection7/28/20057/28/20057/28/2005 NR
DetailsJim Sly
Called....WIP
Inspection Record Card- Bld  4/27/2005 DONE
Permit Ready to Issue  4/27/2005 DONE
Telephone call  4/27/2005 DONE
lft vm with skip wingfield ###-#### - that permit and fees are ready to be picked up
Issue PAID IN FULL permit  4/27/2005 DONE
Routing - PLAN CHECK4/26/2005 4/26/2005 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/26/2005 PASS
Routing - Erosion and Sediment4/25/2005 4/26/2005 PASS
ESC plan waiver request approved with attached conditions.
Plan assigned to (JCB)1/25/2005 4/26/2005 PASS
4/26/2005 14:17:29 JCB - activity updated through activity BLDA022 from case BLD05-00127.
Plan resubmittals received  4/25/2005 DONE
Received Transmittal & 1 Discription & History of buldg book Taken to Jason B.
Routing - PLAN CHECK4/22/2005 4/25/2005 PEND
Plans to route to Erosion/Sediment Control.
Telephone call  4/22/2005 DONE
Contacted Dave Bliss of Trout Architects to obtain final code analysis for buildings on this site. He said it would be submitted in on Monday, 4/25/2005.
Routing - PLAN CHECK3/4/2005 4/22/2005 FAIL
Still need final code analysis for buildings on the site and still need ESC permit and information. Contacted architect and contractor.
Telephone call  4/21/2005 DONE
Called Skip at K2 Construction concerning the required ESC permit. No information pertaining to ESC has been provided with the resubmittals. He said he would look into it.
Plan resubmittals received  4/21/2005 DONE
Resubmittals received and forwarded to Jason: Comment sheet addressing plan review revisions, 1 letter of transmittal requesting extended time for code upgrade, and 2 copies of plan sheet 2.0.
Meeting  4/6/2005  
Met with Dave Bliss of Trout Architects concerning some code issues with the code analysis provided for the buildings on the site. Some options and solutions were discussed such as downgrading construction types and expanding the sprinkler system into some building areas. Mr. Bliss said he would take the information to the owner and get back to me. It appears as if an upgrade agreement may be requested for expanding the sprinkler system into non-sprinklered building areas.
Telephone call  4/5/2005 DONE
Dave Bliss called back and a meeting to discuss code analysis will occur on 4/6/05.
Telephone call  4/4/2005 DONE
Called architect representative Dave Bliss concerning some issues with the code analysis presented. He said he would get with Steve Trout and get back to me tomorrow to set up a meeting.
Plan resubmittals received  4/3/2005  
Received 2 Responses, 2 site plan ,2 office floor plan,2 north elevation,2 S1 & S2 sheets 1 S4,S5,SHEET , 1revised exterior,1 truck repair elevation view,2 plan view sheets,1 warehouse elevation,1 specifications,1 floor plan 1of 3,3 of 3,2 of 3, Taken to Jason B.
1st review completed  3/4/2005 FAIL
failed plan chec and ESC.
Routing - FIRE2/24/2005 3/4/2005 PASS
approved subject to conditions-review faxed to applicant
Routing - PLAN CHECK1/28/2005 2/24/2005 FAIL
Plan review report sent and faxed to design engineer and to contractor. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
Plan resubmittals requested  2/24/2005  
Plan resubmittals and written response required for further review.
Routing - Erosion and Sediment2/24/2005 2/24/2005 FAIL
Talked with Steve Webb of Erosion/Sediment Control and he stated that an ESC Permit is required. Left message with Skip Wingfield of K2 Construction concerning this requirement.
Plan resubmittals received  2/23/2005 DONE
Received 2 Structural Calcs. Taken to Jason B.
Routing - PLANNING1/27/2005 1/28/2005 PASS
Sarah Schafer CZC05-00007

Approved per CZC05-00007.
Routing - PUBLIC WORKS1/25/2005 1/27/2005 PASS
Recd Pcfee & Taken To Pln CK  1/24/2005  
Plans ACCEPTED BY PLAN TECH  1/24/2005 DONE
Ok to take in plans per Marlene before the DRH goes through, as per Evelyn G.
Application received  1/21/2005