Letter of compliance | | | 6/1/2005 | | DONE |
|
|
|
Letter of Compliaince issued 6-1-05.
|
BLD-Final | 5/13/2005 | 5/13/2005 | 5/13/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/13/2005 at 6:59:50 AM. Contact: ###-####.
|
DOC - Permit Finaled | 5/13/2005 | 5/13/2005 | 5/13/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/13/2005 at 6:59:50 AM. Contact: ###-####.
|
FIRE-Final Inspection | 5/11/2005 | 5/11/2005 | 5/11/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
Issue & PRINT to be Invoiced | | | 3/9/2005 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 1/28/2005 | | 3/8/2005 | | PASS |
|
|
|
3/8/2005 09:45:51 DRS - activity updated through activity BLDA022 from case BLD05-00166.
|
Routing - FIRE | 3/1/2005 | | 3/8/2005 | | PASS |
|
|
|
|
1st review completed | | | 3/8/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/8/2005 | | 3/8/2005 | | PASS |
|
|
|
Reviewed for code compliance per IBC
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2005 | | PASS |
|
|
|
To permit desk to issue.
|
Inspection Record Card- Bld | | | 3/8/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/31/2005 | | 3/1/2005 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst.
|
Routing - PLUMBING | 1/28/2005 | | 1/31/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 1/28/2005 | | 1/28/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/26/2005 | | |
|
|
|
|
Application received | | | 1/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/25/2005 | | DONE |
|
|
|
|