Permit Information
Permit NumberBLD05-00236
StatusFinaled
Name ESI
Site Address 4576 N EAGLE RD
Project NameParcel 6 at McMillan's Corner
Customer Number 
ePlanReviewNo
Description
Parcel 6 at McMillan's Corner - To construct a new 6,480 square foot, one story, multi-tenant retail building. This building is constructed of masonry exterior walls, metal roof joist, metal roof deck and metal interior stud construction. This building is proposed to have six future 1140 square foot retail stores (A1 - A6). There is no occupancy allowed under this permit. Tenant spaces A1 & A5 will have a vanilla finish with restroom and will require an MIS permit for occupancy. Tenant spaces A2, A3, A4 & A6 will required separate tenant improvement permits to finish each space for occupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/6/200512/6/20052/13/2006 DONE
Second Notice has not been responded to.
Second Notice BLD10/27/200510/27/200512/6/2005 DONE
First Notice has not been responded to.
First Notice10/12/200510/12/200510/27/2005 DONE
DetailsJim Sly
BLD-Final10/11/200510/12/200510/12/2005APASS
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
C/C issued
DOC - Permit Finaled10/12/200510/12/200510/12/2005PPASS
DetailsJim Sly
C/C issued
BLD-Final9/29/20059/30/20059/30/2005ANR
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Need Letter from Eng addressing discrepancies per special insp final report. and Fire/life safety final.
BLD-Final9/28/20059/28/20059/28/2005PNR
DetailsMike Jordan
terry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection8/23/20058/24/20058/24/2005APASS
DetailsForrest France
Fire life safety passed inspection.
FIRE-Final Inspection8/19/20058/19/20058/19/2005PCANC
DetailsTroy Cobbley
jamal; Phone #: ###-####
Code Occupancy Approval8/19/20058/19/20058/19/2005PFAIL
DetailsCarol Montgomery
Landscape at the se corner of the building needs to be replaced/reworked. Also need to have a gate on the trash enclosure.
FIRE-Final Inspection8/17/20058/18/20058/18/2005PFAIL
DetailsTroy Cobbley
Provide the correct remote annunciators for the duct smoke detectors and turn the sample tubes per the manufacturers recommendations into the airstream for proper sampling.
PubWorks Occupancy Approval8/17/20058/17/20058/17/2005 DONE
Drainage project complete, signed permanent occupancy 8/17/05. G.Fitts
BLD-Wall cover8/3/20058/4/20058/4/2005APASS
DetailsJim Sly
###-#### - GIL NOTE: CEILING grid ok
Override - Condition Holds  8/3/2005  
BLD-Framing/Rough-in8/1/20058/1/20058/1/2005PNR
DetailsJim Sly
###-#### - GIL NOTE: CEILING
NR
Override - Condition Holds  8/1/2005  
BLD-Framing/Rough-in6/15/20056/15/20056/15/2005APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/15/2005 at 7:29:49 AM. Contact: ###-####.
Framing at Ext walls OK.
BLD-Framing/Rough-in6/2/20056/3/20056/3/2005APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/2/2005 at 12:40:38 PM. Contact: ###-####. Welding completed and special insp done on front Canopy.
BLD-Framing/Rough-in5/31/20056/1/20056/1/2005PFAIL
DetailsJim Sly
per your request Internet Inspection Request from: Letitia Mesa
C/N... Connection of vertical studs at awning (front) to cantilevered roof to be welded, not shot on. See S-2 detail 15.
BLD-Framing/Rough-in5/31/20055/31/20055/31/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/31/2005 at 9:54:28 AM. Contact: ###-####. re-call for frame insp when all trades approved.
BLD-Conference4/20/20054/20/20054/20/2005PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/20/2005 at 8:57:48 AM. Contact: ###-####. looked at re-submittal that they would like me to approve for changes in restroom locations and additional restroom added. 4/20/2005 4:11:33 PM
BLD-Footing4/8/20054/12/20054/12/2005APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/8/2005 at 9:42:35 AM. Contact: ###-####. Footing OK pending MTI special insp, tests, and approvals. 4/12/2005 10:37:46 AM
BLD-Conference4/8/20054/8/20054/8/2005PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/8/2005 at 9:33:06 AM. Contact: ###-####. Met with Gil.....Next to Albertsons. 4/8/2005 2:57:15 PM
(F) Reprint permit  3/31/2005  
Issue PAID IN FULL permit  3/30/2005  
Telephone call  3/10/2005 DONE
tlk to jim marsh ###-#### that permit and fees are ready but does not copy for the ACHD
Inspection Record Card- Bld  3/9/2005 DONE
Permit Ready to Issue  3/9/2005 DONE
Plan resubmittals received  3/9/2005 DONE
Received Transmittal & 1 Copy of sheet 1.1 Taken to John M . Plans are in the ready mode.
Telephone call  3/9/2005 DONE
lft vm with CSCQA that permit and fees are ready - had some questions concerning the permit
Routing - PLAN CHECK3/4/2005 3/8/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  3/8/2005 DONE
Plan assigned to (JCM)2/2/2005 3/8/2005 PASS
3/8/2005 09:59:03 JCM - activity updated through activity BLDA022 from case BLD05-00236.
Plan resubmittals received  3/7/2005 DONE
Received Transmittal Letter, 3 Structural Design Calcs, & 3 Copys of sheet S2 Taken to John M.
Routing Off Site - STRUCTURAL3/3/2005 3/4/2005 FAIL
Resubmittals sent via PDQ on 3/3/2005 - Received comment list from consulting structural engineer requesting addtional revisions.JCM
Plan resubmittals requested  3/4/2005 DONE
Faxed the engineer of record a ocpy of the comment list from the consulting structural engineer requesting additional revisions. JCM
Routing - PLAN CHECK3/3/2005 3/4/2005 PASS
Routing - Erosion and Sediment3/4/2005 3/4/2005 PASS
ESC approved with attached conditions.
Routing - PLANNING3/4/2005 3/4/2005 PASS
Plans comply with CUP04-00089, which includes DR staff review per CUP conditions of approval.
1st review completed  3/3/2005 FAIL
failed planning, plan check, structural, ESC and fire.
Routing - FIRE2/24/2005 3/3/2005 PASS
resubmittal acceptable. Revised review faxed to architect.
Plan resubmittals received  3/2/2005 DONE
Received cover letter responding to resubmittals, 2 copies of supplemental structural design calcs, 1 copy soil & foundation evaluation, and 2 copies of sheets G0.1, A1.3, A4.1, A10.1, ASP1, S1, S2 and E1.1 and forwarded to John M. Received 1 copy of Site Development Plan and forwarded to Sam Rogers.
Plan resubmittals received  2/25/2005 DONE
Received ESC Application, 2 ESC Narratives & 2 Copys of sheet C1.1 Taken to John M.
Plan resubmittals requested  2/24/2005 DONE
E-mailed the architect a copy of the plan review comment list requesting revisions. JCM
Routing - PLAN CHECK2/15/2005 2/24/2005 FAIL
Plan resubmittals requested  2/22/2005 DONE
Faxed the project engineer a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL2/2/2005 2/21/2005 FAIL
Called PDQ for pick up ---- Received a faxed copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing - FIRE2/10/2005 2/15/2005 FAIL
lacks site plan showing FD access and hydrants, hardware issue.
Routing - PLANNING2/9/2005 2/10/2005 FAIL
Need site plan showing all easements, and need compliance with Design Review Staff comments (includes wall light height and 6' decorative wall). Karen G. CUP04-00089
Routing - PLUMBING2/7/2005 2/9/2005 PASS
Thermal expansion tank and Prv piped to approved location as required by 2003 UPC 608.3 Approved as noted,per plan and 2003 UPC
Routing - Erosion and Sediment2/7/2005 2/7/2005 FAIL
Incomplete application, no rp, no address and no applicant listed. Complete and re-submit. Plan is incomplete as well. Informed PD.
Routing - PUBLIC WORKS2/3/2005 2/7/2005 PASS
Routing - PLANNING Land Div2/2/2005 2/3/2005 PASS
Lot 6, Block 1 of Lowell Plaza Subdivision.
Plans ACCEPTED BY PLAN TECH  2/2/2005  
Plan routing begun/NEW & ADDTN  2/2/2005  
Application received  2/1/2005  
Recd Pcfee & Taken To Pln CK  2/1/2005  
Fee Review-notes2/1/20052/1/2005