Third Notice BLD | 12/28/2005 | 12/28/2005 | 1/9/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 1/9/2006 | | DONE |
|
|
|
Left message for Stan (Hometown Electric) regarding final value difference///1/9/06 @11:20am BAS
|
Second Notice BLD | 12/5/2005 | 12/5/2005 | 12/28/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/16/2005 | 12/5/2005 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 11/16/2005 | | |
|
|
|
Final - OK. Meets compliance with CUP04-00139 (X-Ref CU85-92-Mod #1) and DRH04-00304
|
Permanent occupancy | | | 11/16/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10804 issued 11-16-05 to Idaho High School Activities.
|
BLD-Final | 11/14/2005 | 11/15/2005 | 11/15/2005 | A | PASS |
Jim Sly
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa OK for Perm Occ as far as Structural...... ():
|
Permanent Occupancy | | 11/15/2005 | 11/15/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide verification of the cfm rating for the roof top units and lower and tag the fire extinguisher in the storage room.
|
BLD-Final | 8/11/2005 | 8/12/2005 | 8/12/2005 | P | NR |
Jim Storey
|
|
|
memmelaar; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa fire failled no insp. performed .
|
FIRE-Final Inspection | 8/11/2005 | 8/12/2005 | 8/12/2005 | A | FAIL |
Troy Cobbley
|
|
|
Provide emergency lighting in main corridor and lobby. See sheet A2.01. Provide emergency lighting in each of the conference rooms. See sheet A2.01. Provide exit discharge lighting at the three exits. Must be listed for outdoor/cold weather. See review note #10. Provide additional text for the occupant load sign, "Dividers closed 66". Redduce storage height per note #13 (24"). Re-install hydraulic closers and provide gaskets on all doors in rated assemblies. Provide fire extinguisher for the new storage room. See note #3. Provide zoning and cfm information on the hvac system.
|
BLD-Final | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | NR |
Mike Jordan
|
|
|
herman; Phone #: ###-#### Note: if possible before 3:00 pm Internet Inspection Request from: Cathy Chiles. life/safety insp required.
|
BLD-Framing/Rough-in | 7/27/2005 | 7/27/2005 | 7/27/2005 | P | PASS |
Jim Sly
|
|
|
michael; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Left note.....May call for Conf insp for all other issues per scope of work.
|
BLD-Footing | 6/28/2005 | 6/30/2005 | 6/30/2005 | A | PASS |
Jim Sly
|
|
|
memmelaar construction; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Foot and wall... OK
|
Issue PAID IN FULL permit | | | 6/8/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 6/2/2005 | | 6/3/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2005 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/3/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/3/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/3/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/3/2005 | | DONE |
|
|
|
called talked to Chris permit is ready, fees, and need RP
|
Plan assigned to (JCB) | 2/10/2005 | | 6/3/2005 | | PASS |
|
|
|
6/3/2005 08:11:38 JCB - activity updated through activity BLDA022 from case BLD05-00261.
|
Routing - Erosion and Sediment | 6/1/2005 | | 6/2/2005 | | PASS |
|
|
|
ESC plan waiver approved with attached conditions.
|
Routing - PLAN CHECK | 3/30/2005 | | 6/1/2005 | | PEND |
|
|
|
When approved by Erosion/Sediment Control permit can be issued. Plans to route to Erosion/Sediment Control for approval.
|
Plan resubmittals received | | | 5/31/2005 | | DONE |
|
|
|
Second copy of resubmittal drawings provided.
|
Plan resubmittals received | | | 5/25/2005 | | |
|
|
|
Received (1) copy of sheet A1-01, A2-01 and A4-01. Routed to Jason B.
|
Telephone call | | | 4/25/2005 | | DONE |
|
|
|
Talked with Chris Anderson of Rudeen & Associates. He said they were going to meet with the owner concerning this project this week and probably resubmit plans with changes.
|
Routing - FIRE | 3/24/2005 | | 3/30/2005 | | PASS |
|
|
|
resubmittal acceptable; revised comments faxed to architect.
|
Routing - PLAN CHECK | 3/9/2005 | | 3/24/2005 | | PEND |
|
|
|
When approved by Erosion/Sediment Control and Fire Dept. permit can be issued. Plans to route to these divisions.
|
Routing - Erosion and Sediment | 3/24/2005 | | 3/24/2005 | | FAIL |
|
|
|
ESC plan waiver request denied. Not allowed per BMC 8-17, informed contact (Chris).
|
Plan resubmittals received | | | 3/23/2005 | | DONE |
|
|
|
Received Transmittal Letter, 1 ESC Application/ Waiver sheet(s) 1 Addendum sheet, 1 Review sheet,& 3 Copys of sheets A1.01,A2.01,A4.01 Taken to Jason B.
|
Telephone call | | | 3/23/2005 | | DONE |
|
|
|
Called Chris Anderson concerning if there are exit signs above the other exit doors from the A-3 meeting room. He said there are not so they will need to be provided. These will be red-lined on the plans. Also clarified with him that all exit signs in the building also have emergency lights.
|
1st review completed | | | 3/9/2005 | | FAIL |
|
|
|
failed plan check, ESC, and fire.
|
Routing - FIRE | 3/4/2005 | | 3/9/2005 | | FAIL |
|
|
|
review comments faxed to architect, same issues as listed on the building review.
|
Routing - Erosion and Sediment | 3/4/2005 | | 3/4/2005 | | FAIL |
|
|
|
Talked with Steve Webb and an Erosion and Sediment Control permit will be required. Applicant to provide completed ESC application and a waiver letter or plan.
|
Plan resubmittals requested | | | 3/4/2005 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 2/14/2005 | | 3/4/2005 | | FAIL |
|
|
|
Plan review report e-mailed and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Routing - PLANNING | 2/11/2005 | | 2/14/2005 | | PASS |
|
|
|
Karen G. CUP04-00139 -Approved.
Sarah S. DRH04-00304 - Approved per DRH04-00304. I will pass the plans on to Karen G. 2/14/05
|
Routing - PUBLIC WORKS | 2/10/2005 | | 2/11/2005 | | PASS |
|
|
|
|
Application received | | | 2/2/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/2/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/2/2005 | | |
|
|
|
|