BLD-Final | 3/3/2006 | 3/3/2006 | 3/3/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/3/2006 at 7:53:21 AM. Contact: ###-####.
|
DOC - Permit Finaled | 3/3/2006 | 3/3/2006 | 3/3/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 2/22/2006 | 2/23/2006 | 2/24/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/22/2006 at 3:20:31 PM. Contact: ###-####. needs handrail on stairs into kitchen and close risers finish handrail and gaurdrail on stair off back pourch
|
BLD-Grading Inspection | 2/16/2006 | 2/16/2006 | 2/16/2006 | | BOND |
|
|
|
Rough grading is complete however fine grading and restoration of the disturbed hillside must still be done. For this a $250.00 bond is required. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Wall cover | 11/15/2005 | 11/16/2005 | 11/16/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/15/2005 at 2:59:48 PM. Contact: ###-####. insulation ok ok to cover
|
BLD-Framing/Rough-in | 11/11/2005 | 11/14/2005 | 11/14/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/11/2005 at 1:31:04 PM. Contact: ###-####. ok to insulate back side shear also ok to cover
|
BLD-Framing/Rough-in | 11/8/2005 | 11/9/2005 | 11/9/2005 | P | PART |
Dave Hannah
|
|
|
shear wall inspection//bob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover front and sides but need engineer to review hold downs on back of house wrong size installed and fl/fl strapes need to finaish nailing
|
BLD-Framing/Rough-in | 10/28/2005 | 10/31/2005 | 10/31/2005 | A | FAIL |
Dave Hannah
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa c/n on site do not insulate
|
BLD-Foundation | 9/1/2005 | 9/2/2005 | 9/2/2005 | A | PART |
Dave Hannah
|
|
|
dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore remainder of garage wall
|
BLD-Footing | 8/30/2005 | 8/31/2005 | 9/1/2005 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/30/2005 at 4:47:28 PM. Contact: ###-####.
|
BLD-Foundation | 8/31/2005 | 8/31/2005 | 9/1/2005 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/31/2005 at 7:54:28 AM. Contact: ###-####.
|
BLD-Foundation | 7/28/2005 | 7/29/2005 | 7/29/2005 | A | PASS |
Jim Storey
|
|
|
dustin; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 7/28/2005 | | |
|
|
|
|
BLD-Concrete | 7/22/2005 | 7/25/2005 | 7/25/2005 | A | PASS |
Mike Jordan
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 7/22/2005 | 7/25/2005 | 7/25/2005 | A | PASS |
Mike Jordan
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 7/20/2005 | 7/22/2005 | 7/22/2005 | A | NR |
Tony Young
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles will recall for monday am
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 7/22/2005 | | |
|
|
|
it is for the lower level cmc
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 7/22/2005 | | |
|
|
|
due to lower level ok by terry
|
PubWorks Subgrade Approval | 7/20/2005 | 7/20/2005 | 7/20/2005 | | DONE |
|
|
|
Footings for lower level have been approved. For the upper level footings a letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####.
|
PubWorks Subgrade Approval | 3/9/2005 | 3/9/2005 | 7/20/2005 | | DONE |
|
|
|
Footing subgrade for the north wall of the garage is approved by the geotechnical engineer. 7/20/05
A letter from the applicants geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 7/20/2005 | | |
|
|
|
cleared with terry
|
BLD-Footing | 7/12/2005 | 7/12/2005 | 7/12/2005 | P | PASS |
Mike Jordan
|
|
|
stem wall and footing ok to do per Dave Hannah. All rebar in place as per approved plans. Lower portion only as per Terry Records.
|
Override - Activity Holds | | | 7/12/2005 | | |
|
|
|
|
BLD-Footing | 6/29/2005 | 6/30/2005 | 6/30/2005 | A | PART |
Dave Hannah
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to pour first area
|
PubWorks Subgrade Approval | 6/29/2005 | 6/29/2005 | 6/29/2005 | | DONE |
|
|
|
Footing subgrade for lower footings approved by the geotechnical engineer
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 6/29/2005 | | |
|
|
|
per Terry ok to do lower footing and wall inspections , then he will get another letter and take off hold for 2nd footing
|
Telephone call | | | 6/29/2005 | | DONE |
|
|
|
per Terry this place is done in two levels. Can get first footing and wall inspection before hold is taken off. Second footing only when Terry gets 2nd ok and takes off hold.
|
Override - Activity Holds | | | 6/29/2005 | | |
|
|
|
|
Override - Activity Holds | | | 5/31/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/31/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 5/11/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/11/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/11/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 5/11/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 5/11/2005 | | |
|
|
|
|
Plan assigned to (SAM) | 2/7/2005 | 5/6/2005 | 5/10/2005 | | PASS |
|
|
|
5/10/2005 15:37:27 SAM - activity updated through activity BLDA022 from case BLD05-00286.
|
Case Summary (BLD) | | | 5/10/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/22/2005 | | 5/10/2005 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/5/2005 | | DONE |
|
|
|
Grading permit MIS05-00057 and ESC05-00170 issued on 5/5/05.
|
Routing - Erosion and Sediment | 4/22/2005 | | 4/22/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 4/22/2005 | | 4/22/2005 | | PASS |
|
|
|
No fire sprinklers required (Morningside sub #1)
|
Routing - PLANNING | 4/21/2005 | | 4/22/2005 | | PASS |
|
|
|
Encroaching roof eaves have been corrected per redlines on building plans. Ok per CFH05-00007.kg
|
Routing - PUBLIC WORKS GRADING | 4/21/2005 | | 4/21/2005 | | PASS |
|
|
|
Approved as Category 1
|
Routing - PLANNING | 3/9/2005 | | 4/7/2005 | | FAIL |
|
|
|
Failed due to overhang that encroaches into setback.
|
Routing - PUBLIC WORKS | 3/9/2005 | | 3/9/2005 | | PASS |
|
|
|
|
Application received | | | 2/7/2005 | | |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 2/7/2005 | | 2/7/2005 | | FAIL |
|
|
|
Needs Hillside Development Application
|