Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-00291
StatusFinaled
Name ATWATER CONSTRUCTION
Site Address 1307 S ORCHARD ST
Project NameHOU SPA
Customer Number 
ePlanReviewNo
Description
(HOU SPA) Remodel for a new spa and massage tenant in an existing 2,020 sq. ft. building per approved plans and CZC05-00038. The parking lot will be restriped. Work to include complete interior demolition work, new interior walls and doors, new main exterior entrance/exit door, two new accessible restrooms, two new shower rooms, a new steam room, interior finish, mechanical work, plumbing work, and electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is not fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/6/200512/6/20052/7/2006 DONE
Second Notice has not been responded to.
Second Notice BLD9/14/20059/14/200512/6/2005 DONE
First Notice has not been responded to.
First Notice 8/29/20059/14/2005 DONE
Permanent occupancy  8/29/2005 DONE
Perm. Occ. Cert. # 10703 issued 8-29-05 to the Hou Spa.
BLD-Final8/16/20058/17/20058/17/2005APASS
DetailsTom Arcoraci
###-#### - aaron Note: please call 1/2 hr prior to inspection ok for perm occ
Permanent Occupancy 8/17/20058/17/2005 DONE
Details
FIRE-Final Inspection6/20/20056/21/20056/21/2005APASS
DetailsForrest France
Fire life safety finaled.
BLD-Final6/17/20056/20/20056/20/2005ANR
DetailsJim Sly
aaron; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Need Fire Perm occ.
BLD-Final6/1/20056/2/20056/3/2005PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/1/2005 at 3:55:26 PM. Contact: ###-####. Note: late as possible for inspection
BLD-Other6/3/20056/3/20056/3/2005 PASS
Code Enforcement issues are final per Dena
BLD-Final6/3/20056/3/20056/3/2005PPART
DetailsDave Hannah
ok for temp occ
FIRE-Final Inspection6/1/20056/2/20056/2/2005PPART
DetailsTroy Cobbley
A temporary occupancy was given until the north exterior door has approved hardware installed. Per contractor hardware to be installed monday.
BLD-Final5/31/20055/31/20055/31/2005PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 5/31/2005 at 8:21:39 AM. Contact: ###-####.
FIRE-Final Inspection5/31/20055/31/20055/31/2005PFAIL
DetailsTroy Cobbley
provide address, provide fire extinguisher, provide approved door hardware for all doors, this includes removing the dead bolt from the rear door, removing keyed hardware from the side door and move indicator to the interior side on the main door.
BLD-Other5/19/20055/19/20055/19/2005PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/19/2005 at 8:20:20 AM. Contact: ###-####.
BLD-Other5/18/20055/18/20055/18/2005PNH
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/18/2005 at 8:27:26 AM. Contact: ###-####.
BLD-Framing/Rough-in4/14/20054/14/20054/14/2005PPASS
DetailsTom Arcoraci
please call prior to inspection so he can meet ya there////arron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Permit Ready to Issue  3/23/2005  
Inspection Record Card- Bld  3/23/2005  
Print Occupancy Form  3/23/2005 DONE
Telephone call  3/23/2005 DONE
talked to preston baker at ###-#### is ready
Issue PAID IN FULL permit  3/23/2005 DONE
Routing - PLANNING3/21/2005 3/22/2005 PASS
Sarah. Approved per CZC05-00038.
Routing - PLAN CHECK3/22/2005 3/22/2005 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  3/22/2005 PASS
Plan assigned to (JCB)2/11/2005 3/22/2005 PASS
3/22/2005 11:45:47 JCB - activity updated through activity BLDA022 from case BLD05-00291.
Routing - PLAN CHECK3/11/2005 3/21/2005 PEND
Permit approval dependent on approval by Planning. Plans to route to Sarah Schafer in Planning.
Plan resubmittals received  3/21/2005 DONE
Small addendum sheets received for steam room construction details.
Routing - FIRE3/8/2005 3/11/2005 PASS
1st review completed  3/11/2005 FAIL
failed planning and plan check
Telephone call  3/8/2005  
Called architect Gerald Teal to request some information on the construction of the new steam room. He said he would look into it and fax over some additional information.
Routing - PLAN CHECK2/16/2005 3/8/2005 FAIL
Called architect Gerald Teal to request some information on the construction of the new steam room. He said he would look into it and fax over some additional information. Plans to route to Fire Dept. for review. Planning approval still also required.
Routing - PUBLIC WORKS2/11/2005 2/16/2005 PASS
Architect needs to contact Bench Sewer District for fees.
Routing - PLANNING2/16/2005 2/16/2005 FAIL
Sarah Schafer (no zoning info provided)

Needs a zoning certificate because of the re-stripping of the parking lot and the tenant change. I have left a message for Gerry Teal.
Recd Pcfee & Taken To Pln CK  2/8/2005  
Plans ACCEPTED BY PLAN TECH  2/8/2005  
Application received  2/7/2005