Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-00316
StatusFinaled
Name ALBERTSONS INC CDC
Site Address 730 S AMERICANA BLVD
Project NameSHORELINE TECH CENTER
Customer Number 
ePlanReviewNo
Description
(ALBERTSONS CDC-PHASE 3)(SHORELINE TECH CENTER-WEST SIDE) Remodel for a new office tenant in an existing 10,830 sq. ft. space in an existing 22,097 sq. ft. building per approved plans. Work to include some new interior walls and doors, interior finish, fire sprinkler work, mechanical work, and electrical work. A Certificate of Occupancy is to be issued when completed and approved. The West wall of this building is an existing 4-hour rated fire wall with a Type III-B building on the other side of the wall at the address of 1500 W. Shoreline Drive which is also occupied by "Albertson's". This building is located in the flood plain. NOTE: This building is fully fire sprinklered for area increase. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/10/20058/10/20058/10/2005PPASS
DetailsDave Hannah
ok for perm occ
FIRE-Final Inspection7/18/20057/18/20057/18/2005PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final7/15/20057/15/20057/15/2005PPART
DetailsDave Hannah
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp
FIRE-Final Inspection7/15/20057/15/20057/15/2005PFAIL
DetailsForrest France
Provide correct building address, supply fire extinguishers, repair emergency light and exit signs, provide approved door hardware at east corridor exit.
BLD-Framing/Rough-in6/23/20056/23/20056/24/2005PPASS
DetailsDave Hannah
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Issue PAID IN FULL permit  3/31/2005  
Routing - PLAN CHECK2/25/2005 2/28/2005 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  2/28/2005 PASS
Permit Ready to Issue  2/28/2005 DONE
Inspection Record Card- Bld  2/28/2005 DONE
Print Occupancy Form  2/28/2005 DONE
Telephone call  2/28/2005 DONE
left mess with david rudeen at ###-#### is ready
Plan assigned to (JCB)2/11/2005 2/28/2005 PASS
2/28/2005 08:32:29 JCB - activity updated through activity BLDA022 from case BLD05-00316.
Routing - FIRE2/23/2005 2/25/2005 PASS
review faxed to archtiect to advise of requirement for fire alarm permit.
1st review completed  2/25/2005  
Plan resubmittals received  2/23/2005 DONE
Received Transmittal Letter, & 3 Copys of sheet A2.00 Taken to Jason B.
Routing - PLAN CHECK2/11/2005 2/23/2005 PEND
When approved by Fire Dept. permit can be issued. Plans to route to Fire Dept. for review.
Meeting  2/22/2005  
Met with architect representative, Byron, to go over a few minor issues. He said he would look into them and get back to me today.
Telephone call  2/22/2005  
Byron called and said he field verified and addressed some of the items and he will provide a resubmittal sheet (3 copies) to clarify within the next day.
Plans ACCEPTED BY PLAN TECH  2/11/2005 DONE
Ok no lighting comp per Jason B.
Application received  2/10/2005  
Recd Pcfee & Taken To Pln CK  2/10/2005