Third Notice BLD | 12/7/2005 | 12/7/2005 | 12/29/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice | | 7/13/2005 | 12/7/2005 | | DONE |
|
|
|
|
First Notice | | 5/24/2005 | 7/13/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/24/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10594 issued 5-24-05 to HA Andersen Co.
|
FIRE-Final Inspection | 5/19/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Permanent Occupancy | | 5/23/2005 | 5/23/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/18/2005 | 5/18/2005 | 5/18/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguisher and test access controled egress doors.
|
BLD-Final | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/17/2005 at 9:58:06 AM. Contact: ###-####. OK for perm Occ. :) 5/17/2005 4:17:19 PM
|
BLD-Wall cover | 5/13/2005 | 5/13/2005 | 5/13/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/13/2005 at 6:52:10 AM. Contact: ###-####. Right address is 6200...... 5/13/2005 3:16:18 PM
|
BLD-Framing/Rough-in | 4/19/2005 | 4/20/2005 | 4/20/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/19/2005 at 12:29:24 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 4/11/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/7/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/7/2005 | | DONE |
|
|
|
tlk to wes steele ###-#### that permit and fees are ready to be picked up
|
Routing - PLAN CHECK | 3/16/2005 | | 4/6/2005 | | PASS |
|
|
|
Received complete new plan submittals of all sheets plus new "M" mechanical sheet. Reviewed resubmittals against plan review comments. Preparing to send to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2005 | | PASS |
|
|
|
To permit desk to issue.
|
Plan assigned to (DRS) | 2/16/2005 | | 4/6/2005 | | PASS |
|
|
|
4/6/2005 15:56:11 DRS - activity updated through activity BLDA022 from case BLD05-00333.
|
Plan resubmittals received | | | 4/5/2005 | | DONE |
|
|
|
Received Transmittal ,1 support sheet,& 2 Copys of sheets A0,A2.1,A3.1,A8.1,M-1,EN-1,E1.0 Taken to Dan S.
|
1st review completed | | | 3/16/2005 | | FAIL |
|
|
|
failed plan check
|
Routing - FIRE | 3/11/2005 | | 3/16/2005 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 3/11/2005 | | FAIL |
|
|
|
Copy of plan review items requiring correction e-mailed and faxed to Wes Steele.
|
Routing - PLAN CHECK | 2/17/2005 | | 3/11/2005 | | FAIL |
|
|
|
Resubmittals required. Copy of required corrections e-mailed and faxed to Wes Steele, Habitec.
|
Routing - PUBLIC WORKS | 2/16/2005 | | 2/17/2005 | | PASS |
|
|
|
|
Application received | | | 2/14/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2005 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/14/2005 | | |
|
|
|
|
Fee Review-notes | 2/14/2005 | 2/14/2005 | | | |
|
|
|
|