BLD-Final | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Dave Hannah
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Dave Hannah
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Energy code compliance | 4/19/2005 | 4/19/2005 | 4/19/2005 | P | FAIL |
Jim Sly
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Complete Corr notice. 4/19/2005 2:05:49 PM
|
BLD-Energy code compliance | 4/19/2005 | 4/19/2005 | 4/19/2005 | P | PASS |
Jim Storey
|
|
|
c/n made ok insulation ok
|
BLD-Framing/Rough-in | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/18/2005 at 6:11:48 AM. load calk./top chord sheathed.ok to insulate.
|
BLD-Foundation | 3/30/2005 | 3/30/2005 | 3/30/2005 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/30/2005 at 5:53:37 AM. Contact: ###-####.
|
BLD-Foundation | 3/30/2005 | 3/30/2005 | 3/30/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/30/2005 at 5:53:37 AM. Contact: ###-####.
|
BLD-Footing | 3/29/2005 | 3/29/2005 | 3/29/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/29/2005 at 7:44:35 AM. Contact: ###-####. 3/29/2005 2:45:08 PM
|
Issue PAID IN FULL permit | | | 3/23/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 3/17/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/16/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 3/16/2005 | | |
|
|
|
|
Telephone call | | | 3/16/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (SAM) | 2/18/2005 | 2/18/2005 | 3/15/2005 | | PASS |
|
|
|
3/15/2005 16:33:15 PEP - activity updated through activity BLDA022 from case BLD05-00408.
|
Plan assigned to (PEP) | 3/15/2005 | | 3/15/2005 | | PASS |
|
|
|
3/15/2005 16:33:15 PEP - activity updated through activity BLDA022 from case BLD05-00408.
|
Case Summary (BLD) | | | 3/15/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 3/15/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 3/15/2005 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/15/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/15/2005 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/23/2005 | | 2/23/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 2/23/2005 | | 2/23/2005 | | PASS |
|
|
|
Okay per revised drawings.
|
Application received | | | 2/18/2005 | | |
|
|
|
|
Routing - PLANNING | 2/18/2005 | | 2/18/2005 | | FAIL |
|
|
|
Garage needs to be set back 20' from common drive. Spoke w/ applicant and requested a revised site plan.
|
Routing - PLAN CHECK | 2/23/2005 | | | | |
|
|
|
|