Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD05-00430
StatusFinaled
Name DOUG STOREY
Site Address 5300 W BETHEL ST
Project NameTEMPCO WAREHOUSE
Customer Number 
ePlanReviewNo
Description
(NO TENANT-SUITE A-WEST SIDE OF BLDG) To remodel a 3,938 sq.ft. area of existing warehouse for a future tenant space with office, restroom and additional structural upgrades per approved plans. This building is not fire sprinklered. NO OCCUPANCY ALLOWED UNDER THIS PERMIT. A separate permit will be required prior to occupancy. RMH Demo work performed under BLD05-00570.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD9/20/20059/20/200512/6/2005 DONE
First Notice has not been responded to.
First Notice 7/22/20059/20/2005 DONE
DOC - Permit Finaled7/22/20057/22/20057/22/2005PPASS
DetailsTom Arcoraci
BLD-Final7/19/20057/19/20057/19/2005PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/19/2005 at 8:56:27 AM. Contact: ###-####. needs landing gaurd rail
FIRE-Final Inspection7/19/20057/19/20057/19/2005PPASS
DetailsTroy Cobbley
Fire life safety finaled
BLD-Other6/29/20056/29/20056/29/2005PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 6/29/2005 at 10:11:01 AM. Contact: ###-####. grid ok
BLD-Framing/Rough-in6/7/20056/7/20056/7/2005PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/7/2005 at 8:37:48 AM. Contact: ###-####. ok pending mech sign off.
BLD-Footing5/10/20055/11/20055/11/2005APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/10/2005 at 5:21:53 PM. Contact: ###-####. eng to verify 3500 or 2500 concrete
Permit Ready to Issue  3/30/2005  
Inspection Record Card- Bld  3/30/2005 DONE
Issue PAID IN FULL permit  3/30/2005 DONE
Case Summary (BLD)  3/29/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/29/2005 DONE
Case Summary (BLD)  3/29/2005  
Plan assigned to (R_H)3/4/2005 3/29/2005 PASS
3/29/2005 08:01:45 RMH - activity updated through activity BLDA022 from case BLD05-00430.
Routing - PLAN CHECK3/18/2005 3/23/2005  
No action at this time. After resubmittals received plans were sent to ESC with a new permit and request for waiver letter.
Routing - Erosion and Sediment3/23/2005 3/23/2005 PASS
Waiver request approved with attached conditions.
1st review completed  3/18/2005 FAIL
failed plan check.
Routing - FIRE3/11/2005 3/18/2005 PASS
Plan resubmittals received  3/15/2005 DONE
Received Transmittal Letter,1 ESC Application,3 Structural Calcs,& 4 Copys of sheet A-0 Taken to Ron H.
Routing - PLAN CHECK3/7/2005 3/11/2005 FAIL
Faxed requirements to architect on 3/10/05, routed plans to fire on 3/11/05
Routing - PUBLIC WORKS3/4/2005 3/7/2005 PASS
Plans ACCEPTED BY PLAN TECH  3/4/2005 DONE
Routing - PLANNING3/4/2005 3/4/2005 PASS
No zoning certificate required.
Application received  2/22/2005  
Recd Pcfee & Taken To Pln CK  2/22/2005  
Third Notice BLD12/6/200512/6/2005   
Second Notice has not been responded to.
Routing - PLAN CHECK3/23/2005