BLD-Final | 11/8/2005 | 11/9/2005 | 11/10/2005 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/8/2005 | 11/9/2005 | 11/9/2005 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/8/2005 at 1:37:01 PM. Contact: ###-####.
|
BLD-Final | 11/8/2005 | 11/8/2005 | 11/8/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/8/2005 at 7:35:23 AM. Contact: ###-####.
|
BLD-Energy code compliance | 8/1/2005 | 8/2/2005 | 8/2/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/1/2005 at 3:38:57 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/19/2005 | 7/20/2005 | 7/20/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/19/2005 at 12:16:45 PM. Contact: ###-####.
|
BLD-Footing | 3/31/2005 | 4/1/2005 | 4/1/2005 | A | PART |
Jim Sly
|
|
|
josh; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Bsmnt only. 4/1/2005 10:57:02 AM
|
Issue PAID IN FULL permit | | | 3/22/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/24/2005 | | 3/18/2005 | | PASS |
|
|
|
The applicant faxed an 8 1/2 x 11 reduction of the basement wall detail he would like to use. (This came with a revised site plan I requested). I stapled it to the front of one set of Rescheck sheets. CER
|
Plan assigned to (SAM) | 3/16/2005 | | 3/18/2005 | | PASS |
|
|
|
3/18/2005 14:02:50 SAM - activity updated through activity BLDA022 from case BLD05-00449.
|
Case Summary (BLD) | | | 3/18/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/18/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/18/2005 | | |
|
|
|
|
Telephone call | | | 3/18/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan Reviewer's activity | | | 3/17/2005 | | DONE |
|
|
|
3/16/05 I called and left a message for Craig to call me. I need a new REScheck and have many other questions on plans. Plans are on hold till I get this information.
|
Routing - PLANNING | 2/23/2005 | | 2/24/2005 | | PASS |
|
|
|
Driveway must be paved to match common driveway which is located outside the property line.
|
Routing - PUBLIC WORKS | 2/24/2005 | | 2/24/2005 | | PASS |
|
|
|
|
Application received | | | 2/23/2005 | | |
|
|
|
|