Third Notice BLD | 5/25/2007 | 5/25/2007 | 6/21/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/24/2007 | 5/9/2007 | | DONE |
|
|
|
|
Override - Condition Holds | | | 4/24/2007 | | |
|
|
|
|
Override - Condition Holds | | | 4/24/2007 | | |
|
|
|
|
Permanent occupancy | | | 4/4/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11513 issued 4-24-07 to Ellen's Ferry Apartments.
|
Permanent Occupancy | | 4/3/2007 | 4/3/2007 | | DONE |
|
|
|
|
BLD-Final | 4/2/2007 | 4/2/2007 | 4/2/2007 | P | PASS |
Tom Arcoraci
|
|
|
###-#### - jeff
|
Code Occupancy Approval | 4/2/2007 | 4/2/2007 | 4/2/2007 | P | PASS |
Michael Garner
|
|
|
site inspection complete - I found that the complex meets the conditions set forth by the approved plans and permits - pass
|
Override - Condition Holds | | | 4/2/2007 | | |
|
|
|
|
Override - Condition Holds | | | 4/2/2007 | | |
|
|
|
|
BLD-Conference | 3/21/2007 | 3/21/2007 | 3/21/2007 | P | PASS |
Tony Young
|
|
|
###-#### - jeff stair issues resolved now
|
Override - Condition Holds | | | 3/21/2007 | | |
|
|
|
|
Override - Condition Holds | | | 3/21/2007 | | |
|
|
|
|
FIRE-Final Inspection | 3/19/2007 | 3/19/2007 | 3/19/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 3/14/2007 | 3/15/2007 | 3/15/2007 | P | NR |
Tony Young
|
|
|
###-#### conf walk through only,, need trades, zoning sign offs,, stair issues
|
FIRE-Final Inspection | 3/14/2007 | 3/15/2007 | 3/15/2007 | A | FAIL |
Troy Cobbley
|
|
|
Smoke alarms need to be relocated to atleast 3' away from the bathroom doors. All other items are ok.
|
FIRE-Final Inspection | 3/14/2007 | 3/14/2007 | 3/15/2007 | P | FAIL |
Troy Cobbley
|
|
|
Smoke alarms need to be relocated to atleast 3' away from the bathroom doors. All other items are ok.
|
Override - Condition Holds | | | 3/14/2007 | | |
|
|
|
|
Override - Condition Holds | | | 3/14/2007 | | |
|
|
|
|
Print Occupancy Form | | | 3/14/2007 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/30/2007 | 1/30/2007 | 2/2/2007 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/28/2006 | 11/28/2006 | 12/1/2006 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 9/25/2006 | 9/26/2006 | 9/26/2006 | A | PASS |
Tony Young
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 9/25/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/20/2006 | 9/21/2006 | 9/21/2006 | A | PASS |
Tony Young
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 9/20/2006 | | |
|
|
|
|
Plan resubmittals received | | | 8/8/2006 | | |
|
|
|
Received transmittal sheet, 1pg. letter from Gerald Teal, 1pg. fax transmittal from Kartchner Engineering, 6 copies of pg. A2-2, three copies of the following pages: A4-1, A4-2, A4-3, A7-1, A7-3; taken to Mike Phillips, ok to accept as resubmittals
|
BLD-Framing/Rough-in | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | PART |
Tony Young
|
|
|
shear insp//brian; Phone #: ###-#### Internet Inspection Request from: Letitia Gallop exterior shear ok
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 7/20/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 7/7/2006 | 7/7/2006 | 7/7/2006 | P | NR |
Tony Young
|
|
|
scott - outside sheer; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Framing/Rough-in | 6/30/2006 | 6/30/2006 | 6/30/2006 | P | CANC |
Tony Young
|
|
|
justin - fire wall insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Conference | 6/23/2006 | 6/23/2006 | 6/23/2006 | P | PART |
Tony Young
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley 2nd floor fire walls
|
BLD-Other | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/15/2006 at 10:56:23 AM. Contact: ###-####. lower f/walls ok
|
BLD-Conference | 6/13/2006 | 6/14/2006 | 6/14/2006 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/13/2006 at 2:06:36 PM. Contact: ###-####.
|
BLD-Aging Inspection | 3/29/2006 | 3/29/2006 | 3/29/2006 | | PASS |
Tony Young
|
|
|
will start soon
|
BLD-Footing | 8/1/2005 | 8/2/2005 | 8/2/2005 | P | CANC |
Tony Young
|
|
|
ed; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa called in wrong permit
|
BLD-Footing | 7/13/2005 | 7/14/2005 | 7/14/2005 | A | PART |
Mike Jordan
|
|
|
ed; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Issue PAID IN FULL permit | | | 7/11/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/28/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/28/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/28/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/28/2005 | | DONE |
|
|
|
left mess for justin at ###-#### permit is ready
|
Plan assigned to (M_P) | 2/24/2005 | 2/24/2005 | 6/24/2005 | | PASS |
|
|
|
6/24/2005 15:10:26 M_P - activity updated through activity BLDA022 from case BLD05-00454.
|
Routing - PLAN CHECK | 6/23/2005 | | 6/24/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/24/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/24/2005 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 6/23/2005 | | 6/23/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 5/24/2005 | | 6/23/2005 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan resubmittals received | | | 6/16/2005 | | |
|
|
|
Received (3) copies of sheet C1.5 and C1.6. Routed to Mike P.
|
Plan resubmittals received | | | 6/14/2005 | | |
|
|
|
Received (3) copies of sheet A0-1, A1-1, A2-0, A4-1, A4-2, A4-3, A6-1, A7-1, A7-2, A7-3, and M-1. Received (6) copies of sheet A2-1, A2-2, A2-3, A2-4, A2-5, A3-1, A3-2, E-1, E-2 and (2) copies of structural calcs. Routed to Mike P.
|
Routing - PLANNING | 5/18/2005 | | 5/24/2005 | | PASS |
|
|
|
Approved per DRH05-00073 and CUP05-00004 per SMS and AW.
|
1st review completed | | | 5/18/2005 | | FAIL |
|
|
|
failed Planning, ESC and plan check.
|
Routing - FIRE | 5/9/2005 | | 5/18/2005 | | PASS |
|
|
|
Approved with conditions; review faxed to aarchitect.
|
Routing - PLAN CHECK | 5/3/2005 | | 5/9/2005 | | FAIL |
|
|
|
Removed from hold on 5/3/05 MJP
Plan review completed sent correction report t architect requesting additional information be submitted for futher review prior to issuing permit.
|
Routing - PLANNING | 3/8/2005 | | 3/9/2005 | | FAIL |
|
|
|
Sara S. DRH02-00034
Mark P. CUP02-00027
Both the CUP and the DR have expired. The applicant will have to resubmitted new applications for both. I am trying to contact the architect, Jerry Teal.
|
Routing - PLAN CHECK | 3/9/2005 | | 3/9/2005 | | HOLD |
|
|
|
Placed on hold per Jerry Teal until further notice.
|
Routing - PLUMBING | 3/4/2005 | | 3/8/2005 | | PASS |
|
|
|
see bld05-00453 for review comments
|
Routing - Erosion and Sediment | 3/3/2005 | | 3/4/2005 | | FAIL |
|
|
|
ESC not per requirements in BMC 8-17.
|
Routing - PUBLIC WORKS | 2/28/2005 | | 3/3/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 2/24/2005 | | 2/28/2005 | | PASS |
|
|
|
One-time division of legal parcel.
|
Plans ACCEPTED BY PLAN TECH | | | 2/24/2005 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 2/24/2005 | | |
|
|
|
|
(F) Reprint permit | | | 2/24/2005 | | DONE |
|
|
|
|
Application received | | | 2/23/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/23/2005 | | DONE |
|
|
|
|