Third Notice BLD | 12/6/2005 | 12/6/2005 | 1/11/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/15/2005 | 9/15/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/30/2005 | 9/15/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/11/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10662 issued 7-11-05 to Shakers Saloon & Grill.
|
BLD-Final | 6/29/2005 | 6/29/2005 | 6/30/2005 | P | PASS |
Dave Hannah
|
|
|
###-#### - joe ok for perm occ
|
Permanent Occupancy | | 6/30/2005 | 6/30/2005 | | DONE |
|
|
|
|
BLD-Final | 6/9/2005 | 6/9/2005 | 6/10/2005 | P | NR |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Final Inspection | 4/4/2005 | 4/5/2005 | 4/5/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. Notified Joe that the manual bolts at the main exterior exit need to be removed
|
FIRE-Final Inspection | 4/4/2005 | 4/4/2005 | 4/4/2005 | P | FAIL |
Troy Cobbley
|
|
|
joe ; Phone #: ###-#### Electrical shunt did not reset.
|
BLD-Final | 4/4/2005 | 4/4/2005 | 4/4/2005 | P | CANC |
Dave Hannah
|
|
|
joe ###-#### pending fire fn
|
BLD-Final | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | CANC |
Dave Hannah
|
|
|
joe ###-#### pending fire fn
|
FIRE-Final Inspection | 3/31/2005 | 4/1/2005 | 4/1/2005 | A | PART |
Forrest France
|
|
|
Temp given per Renn Ross per shunt replacement, add emergency light, repair emergency exit light.
|
BLD-Final | 4/1/2005 | 4/1/2005 | 4/1/2005 | P | PART |
Dave Hannah
|
|
|
ok for temp occ needs allother trades to sign final and install hand rails on stairs at back 4/1/2005 3:22:54 PM
|
Temporary occupancy | | | 4/1/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5224 issued 4-1-05 to Shakers Saloon & Grill.
|
BLD-Framing/Rough-in | 3/24/2005 | 3/25/2005 | 3/25/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/24/2005 at 2:31:48 PM. wall behind 1hr hood 3/25/2005 11:40:02 AM
|
BLD-Framing/Rough-in | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | PART |
Dave Hannah
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Moore steel stud wall back of hood ok to cover 3/25/2005 3:45:23 PM
|
Issue PAID IN FULL permit | | | 3/24/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/21/2005 | | 3/23/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2005 | | DONE |
|
|
|
Plans taken to the permit desk for Ron Hill by M. Southard
|
Permit Ready to Issue | | | 3/23/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/23/2005 | | |
|
|
|
|
Print Occupancy Form | | | 3/23/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2005 | | |
|
|
|
talked to joseph knoblrih at ###-#### is ready
|
Plan assigned to (R_H) | 3/3/2005 | | 3/23/2005 | | PASS |
|
|
|
3/23/2005 11:57:50 MYS - activity updated through activity BLDA022 from case BLD05-00480.
|
Routing - FIRE | 3/14/2005 | | 3/21/2005 | | PASS |
|
|
|
review faxed to architect.
|
1st review completed | | | 3/21/2005 | | FAIL |
|
|
|
failed plumbing
|
Routing - PLAN CHECK | 3/11/2005 | | 3/14/2005 | | PEND |
|
|
|
No corrections required by the building department review, Routed plan to the fire department on 3/14/05, Permit pending fire departments review.
|
Plan resubmittals received | | | 3/11/2005 | | DONE |
|
|
|
Received 2 Copys of sheet A-1 Taken to Ron H.
|
Routing - PLUMBING | 3/8/2005 | | 3/11/2005 | | PASS |
|
|
|
per resubmitted plans and 2003 upc
|
Routing - PLUMBING | 3/4/2005 | | 3/8/2005 | | FAIL |
|
|
|
move floor sink up to finish floor and out of traffic way.
|
Routing - PUBLIC WORKS | 3/3/2005 | | 3/4/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2005 | | DONE |
|
|
|
Ok to take in- checked with Ron Hill to see if Architect was needed.
|
Application received | | | 2/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/25/2005 | | DONE |
|
|
|
|