Case Summary (BLD) | | | 11/7/2012 | | DONE |
|
|
|
|
BLD-Final | 7/14/2005 | 7/15/2005 | 7/15/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/14/2005 at 4:31:19 PM. Contact: ###-####. ok for temp
|
FIRE-Final Inspection | 7/14/2005 | 7/15/2005 | 7/15/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety is satisfactory.
|
FIRE-Final Inspection | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | CANC |
Forrest France
|
|
|
Contact: ###-####. Cancel per Paul, items on correction notice are not completed.
|
FIRE-Final Inspection | 7/12/2005 | 7/13/2005 | 7/13/2005 | P | FAIL |
Forrest France
|
|
|
Remove thumbturn and supply approved door hardware at both main entry/exit doors, provide fire ext. with current annual inspection tag installed with handle no higher than 48" AFF, provide suite address at main entrance.
|
BLD-Final | 7/12/2005 | 7/14/2005 | 7/13/2005 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/12/2005 at 11:50:13 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 13 2005 2:15PM.
|
FIRE-Final Inspection | 7/12/2005 | 7/13/2005 | 7/12/2005 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/12/2005 at 11:47:29 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 12 2005 11:52AM.
|
BLD-Final | 7/8/2005 | 7/11/2005 | 7/11/2005 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/8/2005 at 12:48:49 PM. Contact: ###-####. needs other trades sign offs
|
BLD-Framing/Rough-in | 5/27/2005 | 5/27/2005 | 5/27/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/27/2005 at 9:47:34 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/25/2005 | 5/25/2005 | 5/25/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 9:13:59 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 4/5/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/31/2005 | | |
|
|
|
|
Print Occupancy Form | | | 3/31/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 3/31/2005 | | |
|
|
|
|
Telephone call | | | 3/31/2005 | | DONE |
|
|
|
left mess for paul macdonald at ###-#### is ready
|
1st review completed | | | 3/30/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/30/2005 | | 3/30/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2005 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 3/4/2005 | | 3/30/2005 | | PASS |
|
|
|
3/30/2005 13:37:06 JCB - activity updated through activity BLDA022 from case BLD05-00481.
|
Routing - FIRE | 3/23/2005 | | 3/30/2005 | | PASS |
|
|
|
no comments required-passed subject to satisfactory inspection by PDS/Fire.
|
Telephone call | | | 3/23/2005 | | DONE |
|
|
|
Talked with Paul MacDonald concerning a few minor issues that will be red-lined on plans.
|
Routing - PLAN CHECK | 3/4/2005 | | 3/23/2005 | | PASS |
|
|
|
When approved by Fire Department permit can be issued. Plans to route to Fire Department for review.
|
Routing - PUBLIC WORKS | 3/4/2005 | | 3/4/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2005 | | |
|
|
|
|
Application received | | | 2/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/25/2005 | | |
|
|
|
|
Fee Review-notes | 2/25/2005 | 2/25/2005 | | | |
|
|
|
|