Third Notice BLD | 12/6/2005 | 12/6/2005 | 12/29/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 12/29/2005 | | DONE |
|
|
|
Left message for Douglas Henken regarding there being no MEC permit///12/29/05 @4:10pm BAS
|
Second Notice BLD | 9/29/2005 | 9/29/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 9/14/2005 | 9/14/2005 | 9/29/2005 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Jim Storey
|
|
|
###-####- the guy
|
DOC - Permit Finaled | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 8/9/2005 | 8/10/2005 | 8/10/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 3:35:31 PM. Contact: ###-####.wall framing ok
|
Issue PAID IN FULL permit | | | 6/28/2005 | | |
|
|
|
|
(F) Reprint permit | | | 6/28/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/13/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/13/2005 | | DONE |
|
|
|
tlk to kyle ###-#### that permit and fees are ready to be picked up
|
Routing - FIRE | 6/3/2005 | | 6/10/2005 | | PASS |
|
|
|
resubmittal acceptable. Revised review faxed to architect.
|
Routing - PLAN CHECK | 6/10/2005 | | 6/10/2005 | | PASS |
|
|
|
Approved to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2005 | | PASS |
|
|
|
To permit desk to process for permit.
|
Plan assigned to (DRS) | 3/4/2005 | | 6/10/2005 | | PASS |
|
|
|
6/10/2005 09:01:33 DRS - activity updated through activity BLDA022 from case BLD05-00482.
|
Routing - PLAN CHECK | 3/24/2005 | | 6/3/2005 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst for re-review.
|
Plan resubmittals received | | | 6/2/2005 | | |
|
|
|
Received (3) copies of sheet A-1, A-2, E-1 and M-1. Routed to Dan S.
|
Telephone call | | | 5/3/2005 | | DONE |
|
|
|
Called Kyle Freutel to see how things were progressing on resubmittals. He has not received strage quantity & container size from owner and letter stating they know and will stay within their allowable quantities for hazardous materials - oxidizer. Said he would call them again.
|
Telephone call | | | 4/13/2005 | | DONE |
|
|
|
Called and talked with Kyle. New drawings for submittal are ready but do not have letter from owner stating his awareness of special requirements for quantity storage & handling of oxidizer (oxygen). Will call owner to see if he can expidite letter.
|
Plan resubmittals requested | | | 3/25/2005 | | DONE |
|
|
|
Faxed Kyle Freutel concerning questions on total quantities of oxidizing gas to be used and stored in existing facility and the landing or step down at the new door from the oxygen storage room. I had talked to Kyle by phone concerning these items on 3/15 & 3/16/05 and he was to follow up with response, clarifications and corrections. This has not occured to date so I am sending this follow up fax.
|
Routing - FIRE | 3/17/2005 | | 3/24/2005 | | FAIL |
|
|
|
improper vent locations and sprinkler specifications, lack of quantity indicated. Review faxed to architect.
|
1st review completed | | | 3/24/2005 | | FAIL |
|
|
|
failed plan check and fire.
|
Routing - PLAN CHECK | 3/4/2005 | | 3/17/2005 | | PEND |
|
|
|
Clarifications coming from architect concerning cylinder size and number and step down at new door. routing to fire code analyst for review.
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2005 | | |
|
|
|
|
Application received | | | 2/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/25/2005 | | |
|
|
|
|
Fee Review-notes | 2/25/2005 | 2/25/2005 | | | |
|
|
|
|