Permit Information
Permit NumberBLD05-00493
StatusFinaled
Name MIKE & TER LANDA
Site Address 342 W PANORAMA PL
Project NameHillside
Customer Number 
ePlanReviewNo
Description
To construct a two bedroom, two and one quarter bathroom 2675 sq. ft. two story single family dwelling (1275 sq. ft. lower level/1360 sq. ft. main level/40 sq. ft. garage level) with a attached 703 sq. ft. two car garage, a 45 sq. ft. deck off the master bedroom and a 502 sq. ft. back deck. Per approved plans, engineering and requirement list. This lot is within a hillside area and is subject to the hillside ordinances. A class "A" roof system and defensible area will be maintained. (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/18/200610/19/200610/19/2006APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 10/18/2006 at 4:49:35 PM. Contact: ###-####.
DOC - Permit Finaled10/19/200610/19/200610/19/2006PPASS
DetailsTony Young
BLD-Grading Inspection10/19/200610/19/200610/19/2006 DONE
Final grading and drainage complete and approved.
BLD-Final10/17/200610/18/200610/18/2006ANR
DetailsTony Young
Phone #: ###-####
BLD-Final10/17/200610/17/200610/18/2006PNR
DetailsTony Young
Scheduled by a contractor via Hello! on 10/17/2006 at 10:20:29 AM. Contact: ###-####.
BLD-Conference10/13/200610/13/200610/13/2006PPASS
DetailsTony Young
stair ?s
BLD-Final10/12/200610/13/200610/13/2006ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/12/2006 at 11:03:21 AM. Contact: ###-####. re sced for pm per contractor
BLD-Conference8/22/20068/23/20068/23/2006APASS
DetailsTony Young
Mike, railing ?s; Phone #: ###-####
disscussed guard and hand rails
BLD-Conference8/21/20068/22/20068/22/2006ACANC
DetailsTony Young
Scheduled by a contractor via Hello! on 8/21/2006 at 12:17:05 PM. Contact: ###-####.
out of time
BLD-Energy code compliance7/24/20067/24/20067/24/2006PPASS
DetailsTom Arcoraci
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in7/7/20067/10/20067/10/2006APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 7/7/2006 at 6:21:03 PM. Contact: ###-####.
ok to insulate pending trades
BLD-Framing/Rough-in7/7/20067/7/20067/7/2006APART
DetailsTony Young
Scheduled by a contractor via Hello! on 7/7/2006 at 7:28:16 AM. Contact: ###-####.
ok to insulate double walls,,
BLD-Framing/Rough-in6/28/20066/28/20066/28/2006PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 6/28/2006 at 10:53:12 AM. Contact: ###-####.
all exterior shear ok
BLD-Foundation5/18/20065/18/20065/18/2006PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 5/18/2006 at 9:29:19 AM. Contact: ###-####.
wip on block retaining wall
BLD-Concrete5/10/20065/10/20065/10/2006APART
DetailsTony Young
Scheduled by a contractor via Hello! on 5/10/2006 at 7:27:01 AM. Contact: ###-####.
bridge slab ok to pour
BLD-Foundation4/6/20064/6/20064/6/2006PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 4/6/2006 at 9:24:54 AM. Contact: ###-####.
BLD-Footing3/24/20063/24/20063/24/2006PPASS
DetailsTony Young
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
bridge ftg
PubWorks Subgrade Approval3/23/20063/23/20063/23/2006 DONE
Footing subgrade for bridge deck has been approved by the geotech
BLD-Foundation3/4/20063/6/20063/6/2006APART
DetailsTony Young
Scheduled by a contractor via Hello! on 3/4/2006 at 5:04:32 PM. Contact: ###-####.
masonary wall on garage fronts,, and garage slab,, wip,, ok
BLD-Framing/Rough-in2/8/20062/8/20062/8/2006PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 2/8/2006 at 10:11:39 AM. Contact: ###-####.
ext. shear ok
BLD-Foundation11/16/200511/16/200511/17/2005PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 11/16/2005 at 9:27:33 AM. Contact: ###-####.
wip
BLD-Foundation11/10/200511/14/200511/14/2005APART
DetailsTony Young
Scheduled by a contractor via Hello! on 11/10/2005 at 9:19:57 PM. Contact: ###-####.
wip on upper walls
BLD-Foundation11/2/200511/3/200511/3/2005APART
DetailsTony Young
Scheduled by a contractor via Hello! on 11/2/2005 at 6:03:36 PM. Contact: ###-####.
lower retaining wall ok,, S 2.3 #7,, reviewed struct. engineer on using #5 bar instead of #6 bar,, ok
BLD-Foundation10/30/200510/31/200510/31/2005PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/30/2005 at 9:16:09 PM. Contact: ###-####. @nd lift at masonry retaining wall. noted incorrect rebar placement at corners and around openings. Correct rebar has been placed at 2nd lift. Preivious lifts have incorrect rebar placement. Need engineer ok on work in place.
BLD-Foundation10/19/200510/19/200510/20/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/19/2005 at 11:16:02 AM. Contact: ###-####.first course of cmu ok to grout
BLD-Foundation10/13/200510/13/200510/13/2005PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/13/2005 at 8:48:14 AM. Contact: ###-####. 2nd lift of fire place bar set almost done wing wall wip .
BLD-Foundation10/12/200510/12/200510/13/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/12/2005 at 10:30:18 AM. Contact: ###-####. first 4ft of fire place and wall in basement ok to grout
BLD-Foundation9/12/20059/12/20059/12/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/12/2005 at 10:37:05 AM. Contact: ###-####. retaining wall and deck colunms ok to pour
BLD-Footing9/1/20059/1/20059/7/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/1/2005 at 10:09:52 AM. Contact: ###-####. retainning walls and column ftg for deck ok to pour
PubWorks Subgrade Approval9/7/20059/7/20059/7/2005 PART
Footing subgrade for two exterior retaiing walls has been approved by the gweotech
BLD-Foundation7/13/20057/14/20057/14/2005APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 7/13/2005 at 8:58:48 PM. Contact: ###-####.
BLD-Footing6/13/20056/14/20056/14/2005APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/13/2005 at 4:06:53 PM. Contact: ###-####.
BLD-Footing6/8/20056/9/20056/8/2005ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/8/2005 at 9:36:05 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jun 8 2005 3:36PM.
PubWorks Subgrade Approval3/8/20053/8/20056/8/2005 DONE
Geotechnical engineer has approved the footing subgrade for the house. 6/8/05


A letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####
Telephone call  5/31/2005 DONE
left mess that permit is ready
Receive PAYMENT IN FULL PRINT  5/31/2005  
Plan Reviewer's activity  5/27/2005 DONE
Builder brought in new plans because of adding 275 sq. ft. to the basement where there once was crawl space. Two hours of my time added.
Override - Activity Holds  5/27/2005  
Inspection Record Card- Bld  5/27/2005 DONE
Print Occupancy Form  5/27/2005 DONE
Override - Activity Holds  5/4/2005  
Issue PAID IN FULL permit  5/4/2005 DONE
Override - Activity Holds  4/7/2005  
Inspection Record Card- Bld  4/7/2005 DONE
Print Occupancy Form  4/7/2005 DONE
Override - Activity Holds  4/7/2005  
Permit Ready to Issue  4/7/2005 DONE
Telephone call  4/7/2005 DONE
tlk to mike ###-#### that permit and fees are ready to be picked up
Plan assigned to (SAM)2/25/20053/29/20054/6/2005 PASS
4/6/2005 13:14:16 SAM - activity updated through activity BLDA022 from case BLD05-00493.
Routing - PLAN CHECK3/31/2005 4/6/2005 PASS
Case Summary (BLD)  4/6/2005  
Routing - Erosion and Sediment4/6/2005 4/6/2005 PASS
ESC resubmittal approved with attached conditions.
PLANS/APPL TAKEN TO FRONT DESK  4/6/2005 DONE
Routing - Erosion and Sediment3/30/2005 3/31/2005 FAIL
ESC does not meet standards set forth in BMC 8-17 plus no mention of ACHD moving storm drain through property. Informed PD
Routing - PLAN CHECK3/11/2005 3/30/2005 FAIL
I called and left messages with the engineer and architect. I need more information from each of them before the plans review will be finished. Routing plans to Erosion.
Routing - Erosion and Sediment3/10/2005 3/11/2005 FAIL
ESC plan failed. No ESC application with plans. Contacted PD.
Routing - FIRE3/11/2005 3/11/2005 PASS
No fire sprinklers required (Boi9se Heights sub 2)
Routing - PLANNING3/9/2005 3/10/2005 PASS
Routing - PUBLIC WORKS3/9/2005 3/9/2005 PASS
Routing - PUBLIC WORKS GRADING2/25/2005 3/8/2005 PASS
Approved as Category 3
Application received  2/25/2005