Case Summary (BLD) | | | 9/28/2009 | | |
|
|
|
|
Case Summary (BLD) | | | 4/7/2008 | | DONE |
|
|
|
|
Second Notice BLD | 12/22/2005 | 12/22/2005 | 1/4/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/1/2005 | 12/22/2005 | | DONE |
|
|
|
|
BLD-Final | 12/1/2005 | 12/1/2005 | 12/1/2005 | P | PASS |
Mike Jordan
|
|
|
nat; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Permanent Occupancy | | 12/1/2005 | 12/1/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/1/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/1/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10818 issued 12-1-05 to Body Building.Com
|
FIRE-Final Inspection | 11/21/2005 | 11/21/2005 | 11/21/2005 | P | FAIL |
Troy Cobbley
|
|
|
Life safety can be finaled when the fire alarm permit is done.
|
BLD-Other | 11/10/2005 | 11/14/2005 | 11/14/2005 | A | CANC |
Mike Jordan
|
|
|
natt Note: racking; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Notified by permit desk of cancellation.
|
BLD-Conference | 10/4/2005 | 10/4/2005 | 10/4/2005 | P | DEFR |
Jim Sly
|
|
|
ned; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Told Nat that he needs to meet with the Architect on site to review all ADA requirements......Lot of elements not per appr plan. ie. door swings. tactile signs etc.
|
FIRE-Final Inspection | 8/17/2005 | 8/17/2005 | 8/17/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide knox key box per note #9. Provide painting or signage per note #11. Provide exit discharge lighting per note #5. Provide approved door hardware per notes #14 and #15. Repair the fire alarm panel and provide the requirements of note #24. Provide clear path of travel, non locking hardware, through doors with exit signs or meet with plan review to possibley remove exit signs.
|
BLD-Framing/Rough-in | 7/26/2005 | 7/26/2005 | 7/26/2005 | P | PASS |
Mike Jordan
|
|
|
stairs//matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/25/2005 | 7/26/2005 | 7/26/2005 | A | FAIL |
Mike Jordan
|
|
|
stairs//tim; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. City approved plans not on site.
|
Inspection Record Card- Bld | | | 6/30/2005 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 3/9/2005 | | 4/25/2005 | | PASS |
|
|
|
4/25/2005 07:29:18 DRS - activity updated through activity BLDA022 from case BLD05-00574.
|
Routing - PLAN CHECK | 4/22/2005 | | 4/25/2005 | | PASS |
|
|
|
Plans approved by fire code a analyst. Routing to permit desk to issue along with racking permit BLD04-02676 for issuing of permits.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2005 | | PASS |
|
|
|
To permit desk to issue.
|
Permit Ready to Issue | | | 4/25/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/25/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/25/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/25/2005 | | DONE |
|
|
|
Left voice message for Cory that permit is ready & fees///4/25/05 9:45am BAS
|
Issue PAID IN FULL permit | | | 4/25/2005 | | DONE |
|
|
|
|
Routing - FIRE | 4/21/2005 | | 4/22/2005 | | PASS |
|
|
|
resubmittal acceptable. revised comments faxed to architect.
|
Routing - Erosion and Sediment | 4/19/2005 | | 4/20/2005 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Routing - PLAN CHECK | 3/29/2005 | | 4/19/2005 | | PASS |
|
|
|
No further resubmittals required. Provided ESC application and waiver request and modified restroom layout. Need to route to steve Webb for ESC; Louise Waldorf for PW sewer use fee re-analysis and then to fire code analyst for re-review.
|
Plan resubmittals received | | | 4/19/2005 | | DONE |
|
|
|
Received Transmittal,Waiver letter to Steve W. along with an ESC Application, 1 United Water sheet,2 Plan Review Response & 2 Copys of sheets A0.0,A0.1,A1.0,A2.0,A3.0,A4.0,A5.0 Taken to Dan S.
|
Routing - PUBLIC WORKS | 4/19/2005 | | 4/19/2005 | | PASS |
|
|
|
Original plans of restroom expansion modified. Fee's removed based on resubmittals of 4/19/05. Plans routed to ESC.
|
Telephone call | | | 4/12/2005 | | DONE |
|
|
|
I was called by Fred Tucker, rack installer, checking on status of permit plan review. I told him that I sent my plan review comments to the architect on 3/23 and fire sent theirs on 3/29 and we have not received and response. Fred said he would follow up with architect.
|
Routing - FIRE | 3/23/2005 | | 3/29/2005 | | FAIL |
|
|
|
hydrants, fire flow and exit signage issues. Review comments faxed to architect.
|
1st review completed | | | 3/29/2005 | | FAIL |
|
|
|
failed plan check and fire.
|
Plan resubmittals requested | | | 3/23/2005 | | DONE |
|
|
|
E-mailed & faxed copies of plan review report to Cory Nelson, Cole|Poe architects.
|
Routing - PLAN CHECK | 3/10/2005 | | 3/23/2005 | | FAIL |
|
|
|
Copy of plan review conditions needing response e-mailed and faxed to Cory Nelson.
|
Routing - PUBLIC WORKS | 3/9/2005 | | 3/10/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/8/2005 | | |
|
|
|
|
Application received | | | 3/4/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/4/2005 | | DONE |
|
|
|
|
Fee Review-notes | 3/4/2005 | 3/4/2005 | | | |
|
|
|
|