Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD05-00592
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project Name 
Customer Number8119
ePlanReviewNo
Description
Micron Building #26 - Complete QC/FA Inspection Labs in Area "C" - (#26-20058119) * To remove all of the interior partitions and doors creating all of the offices that surround the Process Development #203A with the exception of Offices #203G, #203H and #203I at the south east corner. The removal of these offices creates a large, 6000 square foot, open area at Process Development #203A. To install new interior partitions and one new interior door as well as two new 8080 entry doors from Corridor #200C. The new partitions will create a new 375 sq. ft. C-SAM #203B area, a new 2230 sq. ft. QC/FA LAB #203A, a new 1325 sq. ft. INSPECTION LAB #203C and a new 1800 sq. ft. BULLPEN #203D. This permit also includes mechanical, electrical, suspended ceiling, flooring, fire alarms and fire sprinklers modifications associated with this remodel. This work is being done at the southeast corner of the second floor of Building #26 between grid lines #J&#M and #!12. All of the rated corridors, first and second floors, must be maintained because of long travel distances. All construction per the approved plans on file. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/31/20056/1/20056/1/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/31/2005 at 8:08:46 AM. Contact: ###-####.l/c isued on site
DOC - Permit Finaled6/1/20056/1/20056/1/2005PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/31/2005 at 8:08:46 AM. Contact: ###-####.
FIRE-Final Inspection5/27/20055/27/20055/27/2005PPASS
DetailsTroy Cobbley
life safety finaled
BLD-Conference4/25/20054/26/20054/26/2005PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/25/2005 at 2:33:50 PM. Contact: ###-####.office area ok for temp occ pending lab final wip.
FIRE-Final Inspection4/25/20054/25/20054/25/2005PPART
DetailsTroy Cobbley
Office area is ok to occupy
BLD-Conference4/12/20054/13/20054/13/2005PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/12/2005 at 10:59:20 AM. Contact: ###-####.
BLD-Conference3/31/20054/1/20054/4/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/30/2005 at 9:12:37 AM. Contact: ###-####.
BLD-Conference3/30/20053/31/20053/31/2005ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/30/2005 at 9:12:37 AM. Contact: ###-####.
Inspection Record Card- Bld  3/17/2005 DONE
Telephone call  3/17/2005 DONE
email paul and Max that permit and fees are ready to be picked up
Issue & PRINT to be Invoiced  3/17/2005  
Plan assigned to (JCM)3/8/20053/8/20053/16/2005 PASS
3/16/2005 14:07:19 JCM - activity updated through activity BLDA022 from case BLD05-00592.
Routing - PLAN CHECK3/15/2005 3/16/2005 PASS
Plan resubmittals received  3/16/2005  
Received a floor plan for the second floor identifying travel distances and revised plans indicating that the corridors would be maintained fire-resistive. JCM
PLANS/APPL TAKEN TO FRONT DESK  3/16/2005 DONE
Inspector's copy Bld permit  3/16/2005 DONE
Inspection Record Card- Bld  3/16/2005  
Permit Ready to Issue  3/16/2005 DONE
Routing - FIRE3/10/2005 3/15/2005 PASS
approved subject to insepction. AS and FA permits are required.
1st review completed  3/15/2005 FAIL
failed plan check.
Plan resubmittals requested  3/10/2005 DONE
E-mailed the architect requesting additional information on the travel distances to determine if the corridors would be required to be maintained fire-resistive. JCM
Routing - PLAN CHECK3/9/2005 3/10/2005 FAIL
Plans ACCEPTED BY PLAN TECH  3/8/2005  
Application received  3/7/2005  
Fee Review-notes3/7/20053/7/2005