BLD-Final | 6/7/2005 | 6/8/2005 | 6/8/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/7/2005 at 8:29:19 AM. Contact: ###-####.
|
DOC - Permit Finaled | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PASS |
Jim Storey
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/2/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/2/2005 | | |
|
|
|
|
BLD-Final | 5/9/2005 | 5/12/2005 | 5/16/2005 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/9/2005 at 12:22:35 PM. Contact: ###-####. need fire aproval be fore bld insp.
|
Case Summary (BLD) | | | 5/13/2005 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/10/2005 | | 3/17/2005 | | PASS |
|
|
|
3/17/2005 07:52:26 JCM - activity updated through activity BLDA022 from case BLD05-00593.
|
Routing - PLAN CHECK | 3/16/2005 | | 3/17/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/17/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/17/2005 | | DONE |
|
|
|
lft mes with secretary ###-#### that permit and fees are ready to be picked up
|
Issue & PRINT permit | | | 3/17/2005 | | DONE |
|
|
|
|
Routing - FIRE | 3/11/2005 | | 3/16/2005 | | PASS |
|
|
|
Approved with annotated requirement to obtain a Fire Sprinkler and a Fire Alarm permit. No written comments required.
|
1st review completed | | | 3/16/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 3/10/2005 | | 3/11/2005 | | PASS |
|
|
|
Sarah Schafer - Approved. Interior site work in a T-2 zone does not require a formal DR.
|
Routing - PLAN CHECK | 3/11/2005 | | 3/11/2005 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2005 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2005 | | DONE |
|
|
|
Ok to take in plans per Marlene.
|
Application received | | | 3/8/2005 | | |
|
|
|
|