BLD-Final | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | PASS |
Dave Hannah
|
|
|
ok for issuing L/C
|
FIRE-Final Inspection | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | CANC |
Forrest France
|
|
|
Duplicate inspection, already completed and passed in the AM.
|
FIRE-Final Inspection | 6/14/2005 | 6/15/2005 | 6/15/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
DOC - Permit Finaled | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/9/2005 | 6/9/2005 | 6/9/2005 | P | FAIL |
Forrest France
|
|
|
Need current annual inspection on fire sprinkler system, provide sign at shaftway, fire ext. and its location sign must correspond.
|
BLD-Final | 6/8/2005 | 6/9/2005 | 6/9/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/8/2005 at 9:22:59 AM. Contact: ###-####. evrey thing ok but needs sprk and L/F Finals
|
Issue PAID IN FULL permit | | | 4/15/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/14/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/14/2005 | | DONE |
|
|
|
tlk to bill schenner ###-#### that permit and fees are ready to be picked up
|
Routing - FIRE | 4/11/2005 | | 4/13/2005 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 4/13/2005 | | 4/13/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2005 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 3/15/2005 | | 4/13/2005 | | PASS |
|
|
|
4/13/2005 13:25:21 JCB - activity updated through activity BLDA022 from case BLD05-00597.
|
Routing - PLAN CHECK | 3/25/2005 | | 4/11/2005 | | PEND |
|
|
|
Received resubmittals required by Fire Dept. Plans to route to Fire Dept. for review of resubmittals. When approved by Fire Dept. permit can be issued.
|
Plan resubmittals received | | | 4/8/2005 | | DONE |
|
|
|
Received 1 Fire Code Review, 3 Hydraulic calcs, 2 Small Copys if sheet 1 of 1 , & 3 Copys of sheet FP1.0 Taken to Jason B.
|
Routing - FIRE | 3/23/2005 | | 3/25/2005 | | FAIL |
Bill Alexander
|
|
|
Fire protection calculations do not meet requirements of NFPA 13, Chapter 14.
a. ROOF design is being verified for: .20/1500-ft/2 and head spacing of 98-ft/2 spacing. This will require more than 9 sprinklers operating for the most demanding/remote area of operation? Provide clarification, corrections and resubmit.
b. Average spacing of sprinklers for 9 heads operating would be average 166+ ft/2, which exceeds the maximum allowance of 130-ft/2 for standard spray sprinklers? Provide clarification, corrections and resubmit.
c. No dimensioned or scalable section view of the structure provided for verification of commodity height and ceiling/roof clearance. Fire Sprinkler Cover Sheet addresses a ceiling height of 13'-5". Storage height is reported to be 12'-4". This would be a clearance of 1'-1" (13") and does not meet the clearance for standard spray sprinklers (deflector to top of storage) of 18"? Provide clarification, corrections and resubmit.
|
1st review completed | | | 3/25/2005 | | FAIL |
Bill Alexander
|
|
|
Failed in Fire.
|
Routing - PLAN CHECK | 3/15/2005 | | 3/23/2005 | | PEND |
|
|
|
When approved by Fire Department, permit can be issued. Plans to route to Fire Department for review.
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2005 | | |
|
|
|
Had Bill A. from Fire- look at plans before submittal.
|
Application received | | | 3/8/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/8/2005 | | DONE |
|
|
|
|