Permit Information
Permit NumberBLD05-00600
StatusFinaled
Name CHRIS LARAWAY
Site Address 10116 W OVERLAND RD
Project NameWILLIAMSBURG OFFICE #2
Customer Number 
ePlanReviewNo
Description
(TRIAD LEASING AND FINANCIAL)(WILLIAMSBURG OFFICE BLDG #2) To construct a 3,000 sq. ft. office tenant in a new vacant shell building which will occupy the entire building per approved plans. Work to include new interior walls, new interior doors and windows, interior finish, two new accessible restrooms, mechanical work, plumbing work, and electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: The shell building permit done under BLD00-03010 is to be finaled in conjunction with this tenant permit. NOTE: This building is not sprinklered. JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  1/11/2006 DONE
Third Notice BLD12/6/200512/6/200512/16/2005 DONE
Second Notice has not been responded to.
Second Notice BLD10/10/200510/10/200512/6/2005 DONE
First Notice has not been responded to.
First Notice 9/14/200510/10/2005 DONE
Permanent occupancy UNPAID FEE  8/22/2005 DONE
Perm. Occ. Cert. # 10697 issued 8-22-05 to Triad Leasing and Financial.
BLD-Final8/5/20058/8/20058/8/2005APASS
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
OK for Perm Occ. ():
Permanent Occupancy 8/8/20058/8/2005 DONE
Details
BLD-Final6/23/20056/23/20056/23/2005PNR
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Barbara Moore All corrections completed. Just need Electrical to sign off for Perm Occ.......then Structural Perm Occ. OK
FIRE-Final Inspection6/16/20056/16/20056/16/2005PPASS
DetailsTroy Cobbley
Fire life safety finaled
FIRE-Final Inspection6/14/20056/15/20056/15/2005AFAIL
DetailsTroy Cobbley
The correct remote annunciators have been installed and they operate correctly but when the duct detectors goes into alarm they do not shut down the hvac units.
BLD-Final6/13/20056/13/20056/13/2005PPART
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa OK for Temp.... Need Fire and Electr final C/N Fill in holes at furnace room (1hr) walls
FIRE-Final Inspection6/10/20056/10/20056/10/2005PPART
DetailsTroy Cobbley
Temporary occupancy was given with sam rogers permission until the correct annunciator have been installed for the duct smoke detectors and tested.
BLD-Final6/8/20056/9/20056/9/2005PNR
DetailsDave Hannah
matt; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Need Plumb and fire sign off.... Electr now signed Temp. Mech pass.
FIRE-Final Inspection6/8/20056/9/20056/9/2005AFAIL
DetailsTroy Cobbley
No approved plans on site for inspection, no fire extinguisher, door hardware not correct, possiblity of needing duct smoke detectors.
(F) Reprint permit  6/7/2005  
Case Summary (BLD)  6/7/2005 DONE
BLD-Energy code compliance5/12/20055/13/20055/13/2005APASS
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
BLD-Framing/Rough-in5/11/20055/11/20055/11/2005PPASS
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Issue PAID IN FULL permit  4/18/2005  
Routing - PLAN CHECK3/30/2005 3/31/2005 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  3/31/2005 PASS
Permit Ready to Issue  3/31/2005  
Inspection Record Card- Bld  3/31/2005 DONE
Print Occupancy Form  3/31/2005  
Telephone call  3/31/2005 DONE
talked to chris laraway at ###-#### is ready
Plan assigned to (JCB)3/14/2005 3/31/2005 PASS
3/31/2005 10:53:09 JCB - activity updated through activity BLDA022 from case BLD05-00600.
Routing - FIRE3/25/2005 3/30/2005 PASS
1st review completed  3/30/2005 FAIL
failed plan check.
Plan resubmittals requested  3/25/2005 DONE
Plan resubmittals and written response required for further review.
Routing - PLAN CHECK3/16/2005 3/25/2005 FAIL
Plan review e-mailed and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
Routing - PUBLIC WORKS3/14/2005 3/16/2005 PASS
Plans ACCEPTED BY PLAN TECH  3/9/2005  
Ok per Chris Laraway to cross out 2000 code on cover sheet and put 2003 . we had gone over that when plans were submitted and he left with out doing it. ///DLD
Application received  3/8/2005  
Recd Pcfee & Taken To Pln CK  3/8/2005 DONE