Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD05-00626
StatusFinaled
Name SHAWMUT DESIGN AND CONSTRUCTION
Site Address 391 S 8TH ST
Project NameBODO BLDG #4
Customer Number 
ePlanReviewNo
Description
(P. F. CHANG'S CHINA BISTRO - BOBO BLDG 4) This building is fire sprinklered for building area increase and for fire area. To construct a 7,500 square foot restaurant tenant space (3,315 square feet for interior dining, 1,015 square feet for covered exterior dining, 2,720 square feet for the kitchen, 450 square feet for the restrooms) within a new 2 story building. Work is to include 2 restrooms accessible to the disabled, interior nonbearing walls, suspended ceilings, 4 grease hoods, millwork, and interior finishes. All work shall comply with the approved drawings, the plan review report, and all applicable codes. The fire sprinkler system shall comply with 2002 NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD6/14/20066/14/200611/7/2007 DONE
Second Notice has not been responded to.
(F) Reprint permit  10/29/2007  
Telephone call  10/23/2007 DONE
lft vm with shaw at ###-#### regarding the final value cofv - called 7/24 last time. Hope to hear from 11:15 am
Telephone call  7/24/2007 DONE
lft vm with shaw at ###-#### 7372 regarding the final values 11:20 am
Telephone call  4/11/2007 DONE
call to Shaw at Shaw Mnt Design and const. left msg to send in cert of fv
Second Notice BLD5/25/20065/25/20066/14/2006 DONE
First Notice has not been responded to.
First Notice 5/15/20065/25/2006 DONE
Permanent occupancy  5/15/2006 DONE
Perm. Occ. Cert. # 11024 issued 5-15-06 to P. F. Chang's China Bistro.
BLD-Final5/8/20065/9/20065/9/2006PPASS
DetailsDave Hannah
Jim Flemming, ###-#### ok for perm occ
FIRE-Final Inspection5/8/20065/9/20065/9/2006APASS
DetailsForrest France
The project related fire alarm and sprinkler permits have been finaled, fire life safety is satisfactory for final.
BLD-Other2/9/20062/9/20062/9/2006 DONE
Temp. Occ. Cert. # 5294 extended addl. 90 days per Jenifer. New expiration date 4-27-06.
(F) Reprint permit  11/2/2005 DONE
FIRE-Final Inspection10/27/200510/28/200510/28/2005APART
DetailsForrest France
Temporary occupancy approval granted with Dave Hanneman's permission pending duct detector testing and approval.
FIRE-Final Inspection10/26/200510/27/200510/27/2005AFAIL
DetailsForrest France
Three items on correction notice remain, including the visual indicators on the main entry/exit doors, one missing exit sign and one missing emergency light at outdoor seating area.
Override - Parcel Holds1/1/19001/1/190010/27/2005  
Override - Parcel Holds  10/27/2005  
Temporary occupancy  10/27/2005 DONE
Temp. Occ. Cert. # 5294 issued 10-27-05 to P.F. Chang's China Bistro in the BODO Bldg. #4.
BLD-Final10/24/200510/25/200510/26/2005ANR
DetailsDave Hannah
jim ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs other trades to sign off
FIRE-Final Inspection10/25/200510/25/200510/25/2005PFAIL
DetailsForrest France
Provide three fire extinguishers as discussed, provide tenant address, provide max occupant load signs, provide emergency lighting and exit signs as indicated on approved plans sheet E3.0, emergency lights in two locations are non-functional, provide visual indicator and signage above the main entry/exit doors, storage must be maintained min. 18" below sprinkler deflectors, need fire sprinkler and alarm permits finaled prior to life safety approval.
Print Occupancy Form  10/18/2005 DONE
BLD-Final10/10/200510/11/200510/12/2005PFAIL
DetailsDave Hannah
jim fleming- ###-#### cell not ready discussion about what will be needed to get a T.O.
BLD-Framing/Rough-in9/19/20059/20/20059/21/2005APART
DetailsDave Hannah
above ceiling framing inspection//tim flemming; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ceiling grid west side ok after other trades sign off
BLD-Framing/Rough-in8/25/20058/26/20058/26/2005PPART
DetailsDave Hannah
ceiling framing///jim flemming; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover restrooms and front lobby
BLD-Framing/Rough-in8/17/20058/18/20058/18/2005PPASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles walls soffits ext wall insulation all ok
Plan Reviewer's activity  7/13/2005 PASS
Revised drawings approved after 2nd review. Left message that the drawings were ready to be picked up. No additional fees.
Plan resubmittals received  7/6/2005  
Received (3) copies of sheet S2.2 and S2.3. Routed to Carl W.
Plan resubmittals received  6/24/2005 DONE
Received 7 Transmittals,7 Structural Calcs, & 7 Copys of sheets S2.1,S2.2,S2.3 Taken to Carl W.
Issue PAID IN FULL permit  6/14/2005 DONE
Routing - FIRE6/8/2005 6/9/2005 PASS
Approved subject to review conditions regarding resubmitted information. review comments faxed to architect.
Routing - PLAN CHECK6/9/2005 6/9/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/9/2005 DONE
Permit Ready to Issue  6/9/2005  
Inspection Record Card- Bld  6/9/2005 DONE
Print Occupancy Form  6/9/2005  
Telephone call  6/9/2005 DONE
talked to scott duffner at ###-#### permit is ready and jim flemming ###-#### is ready
Plan assigned to (CJW)3/14/2005 6/9/2005 PASS
6/9/2005 08:42:49 CJW - activity updated through activity BLDA022 from case BLD05-00626.
Plan resubmittals received  6/8/2005 DONE
Received 2 Transmittals,1 Fire Code Review, & 3 Copys of sheets A2.2,FA-1,SE-1 Taken to Carl W.
Meeting  6/8/2005  
Please note that no certificate of occupancy shall be issued for this TI until the design of the exterior wall sconces are approved by the DR staff.
Routing - PLAN CHECK6/7/2005 6/8/2005 DONE
Sent back to fire.
Routing - PLAN CHECK5/24/2005 6/7/2005 PASS
(5-25-05) Drawings approved after resubmittal review. Drawings on hold until called for by Planning or Fire.

(6-7-05) Sent back to Planning.
Routing - PLANNING6/7/2005 6/7/2005 PASS
Approved per DRH05-00071. C of O shall not be issued until DR has signed off on exterior wall sconces. I have placed a tag on the parcel with this information.
Routing - FIRE5/19/2005 5/24/2005 FAIL
Sever items were not responded to. Revised comments faxed to architect.
Routing - PLANNING5/10/2005 5/19/2005  
Pulled back to finish IBC plan review of revised drawings.
Routing - PLAN CHECK5/19/2005 5/19/2005 FAIL
Finished IBC plan review of revised drawings. Two items were not resolved. Emailed Architect.
Routing - PLAN CHECK4/5/2005 5/10/2005  
Resubmittal review not complete. Drawings sent back to Planning to keep this project moving while the IBC Plans Examiner is on vacation.
Permanent Occupancy 5/9/20055/9/2005 DONE
Details
Plan resubmittals received  5/6/2005 DONE
1 copy of plan review report, 1 copy of building dept plan corrections, 1 copy of plumbing plan review, 1 copy of fire code review, 1 copy of fire plan corrections, 1 copy of owner changes/plan check comments, 2 copies of sheets A0.0, A0.1, A0.2, A0.3, A0.5, A0.6, A1.1b, A2.1, A2.2, A2.3, A2.4, A2.5, A3.1, A3.2, A3.2a, A3.3, A5.1, A5.2, A5.3, A8.2, A8.3, A9.1, A9.2, A9.3, A9.4, A9.5, A9.6, A9.7, A9.8, FS4.0, M1.1, M2.1, M2.2, M2.3, M3.3, M4.1, P-1, P-2, P-3, E1.0, E2.0, E3.0, E3.1, E4.0, E4.1, E5.0, E6.0, E7.0, E7.1, E8.0, E8.1, SS-1, SS-2,
Routing - FIRE3/31/2005 4/5/2005 FAIL
improper sprinkler and fire alarm systems shown, no PFE's . Faxed review to architect.
1st review completed  4/5/2005 FAIL
failed plan check and fire.
Routing - PLAN CHECK3/21/2005 3/31/2005 FAIL
The IBC plan review was started on March 25, 2005 and was finished on March 31, 2005. Resubmitted drawings were required. See the plan review report.
Routing - PLANNING3/17/2005 3/21/2005 FAIL
Modification currently being processed by Sarah Schafer (DRH05-71). Sarah will call for Building plans upon completion of review.
Routing - PLUMBING3/15/2005 3/17/2005 PASS
note C page P-2 indirect waste required for all food perp and dish washing sinks and equipment, idaho state code. additional cross connection protection may be required, upstream of the filtered water connection, various equipment, etc. provide odor control per public works pretreatment.
Routing - PUBLIC WORKS3/14/2005 3/15/2005 PASS
Plans ACCEPTED BY PLAN TECH  3/11/2005  
Application received  3/9/2005  
Recd Pcfee & Taken To Pln CK  3/9/2005  
Fee Review-notes3/9/20053/9/2005