Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-00635
StatusFinaled
Name ST ALPHONSUS REGIONAL MEDICAL CNTR
Site Address 1055 N CURTIS RD
Project NameSt Al's Central Tower Addition
Customer Number 
ePlanReviewNo
Description
(ST ALPHONSUS CENTRAL TOWER)(1ST FLOOR PHARMACY) To finish approximately 14,260 sq. ft. of the first floor and the exit system that serves this area for use as a Pharmacy Unit with associated support services. Exits will be to the north into the existing north tower exit system and to the east to a set of double doors leading directly to the exterior. Work will include construction of interior non-bearing, non-combustible, fire-resistive walls to create the pharmacy and associated support areas; to install the electrical, mechanical, plumbing, fire supression and alarm systems to meet tenant needs and comply with minimum adopted codes and ordinances; to install a suspended ceiling grid system and supported fixture's; interior millwork and finishes; all per the approved plans to include all red-lined notes and attached plan review comments / conditions of all reviewing agencies. (drs)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD9/22/20089/22/20083/10/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 6/11/20088/11/2008 DONE
Permanent Occupancy  6/11/2008 DONE
DetailsCathy Weisshaupt
FIRE-Final Inspection6/6/20086/9/20086/10/2008APASS
DetailsTroy Cobbley
Fire life safety passed.
BLD-Conference6/5/20086/5/20086/5/2008PPASS
DetailsTom Arcoraci
BLD-Aging Inspection5/13/20085/13/20085/13/2008 PART
DetailsTom Arcoraci
BLD-Aging Inspection2/20/20082/20/20082/21/2008 PASS
DetailsTom Arcoraci
BLD-Aging Inspection12/17/200712/17/200712/17/2007 PASS
DetailsTom Arcoraci
Case Summary (BLD)  12/6/2007  
FIRE-Final Inspection10/16/200710/17/200710/17/2007AFAIL
DetailsTroy Cobbley
The exit signs and emergency lights located on the roof and at the ground level exits are in question due to motion detectors and photo sensors being installed to control them. Per the electrical engineer NFPA 101 allows the use of motion detectors. I deferred him to Sam Rogers for the final decision for acceptance. The fire alarm system needs to be satifactory for Mike Timmerman prior to phase 1 sign off as well.
FIRE-Final Inspection10/15/200710/15/200710/16/2007PFAIL
DetailsTroy Cobbley
The exterior emergency lighting needs finished, the fire alarm permit satified and the sprinklers in the new canopy addressed.
BLD-Aging Inspection9/17/20079/17/20079/17/2007 PASS
DetailsTom Arcoraci
BLD-Aging Inspection7/18/20077/18/20077/18/2007 PASS
DetailsTom Arcoraci
BLD-Aging Inspection5/2/20075/2/20075/2/2007 PASS
DetailsTom Arcoraci
BLD-Aging Inspection3/2/20073/2/20073/5/2007 PASS
DetailsTom Arcoraci
BLD-Final12/15/200612/15/200612/15/2006PPART
DetailsTom Arcoraci
Jim; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok for temp occ
FIRE-Final Inspection12/14/200612/14/200612/15/2006PPART
DetailsTroy Cobbley
A temporary occupancy was given until the fire alarm permit has been finaled, the grading permit is finaled and the temporary exit discharge light located at the east exit has been replaced with the permanent fixture.
Temporary occupancy  12/15/2006 DONE
Temp. Occ. Cert. # 5489n issued 12-15-06 to St. Al's Pharmacy.
FIRE-Final Inspection12/11/200612/11/200612/12/2006PFAIL
DetailsTroy Cobbley
I need verification that a permit has been pulled for the fuel system as per the review comments. I need verification that the grading permit has been completed as per the review comments. Emergency lights need to be installed in the small room as discussed. Exit discharge lighting needs to be provided at the new east exit as per the review comments. The fire alarm permit needs to be finaled.
FIRE-Final Inspection12/7/200612/8/200612/8/2006ACANC
DetailsTroy Cobbley
ruth; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Aging Inspection10/30/200610/30/200610/30/2006 PASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/30/2006 at 7:43:30 AM. Contact: ###-####.
BLD-Conference8/28/20068/28/20068/29/2006PCANC
DetailsTom Arcoraci
BLD-Aging Inspection7/14/20067/14/20067/19/2006 PASS
DetailsTom Arcoraci
BLD-Aging Inspection3/3/20063/3/20063/6/2006 PASS
DetailsTom Arcoraci
BLD-Aging Inspection12/30/200512/30/200512/30/2005 PASS
DetailsTom Arcoraci
Issue PAID IN FULL permit  9/30/2005 DONE
Plan assigned to (DRS)3/15/2005 9/20/2005 PASS
9/20/2005 13:05:26 DRS - activity updated through activity BLDA022 from case BLD05-00635.
Routing - PLAN CHECK9/10/2005 9/20/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/20/2005 PASS
Permit Ready to Issue  9/20/2005 DONE
Inspection Record Card- Bld  9/20/2005 DONE
Print Occupancy Form  9/20/2005 DONE
Telephone call  9/20/2005 DONE
Spoke with Jeff and told him permit is ready & fees///9/20/05 3:55pm BAS
Routing - FIRE8/26/2005 9/10/2005 PASS
resubmittal acceptable. revised review comments faxed to architect.
Routing - PLAN CHECK8/24/2005 8/26/2005 PEND
Routing to fire code analyst for re-review.Sam Rogers received clarification from architect.
Routing - PLAN CHECK6/2/2005 8/22/2005 PEND
Routing to plumbing for review.
Telephone call  8/22/2005 DONE
Talked with Jeff Cramer of HDR Architects concerning getting response back for fire code review for this specific project. Need this information before fire can review.
1st review completed  6/2/2005 FAIL
failed plan check and fire.
Routing - FIRE5/24/2005 6/2/2005 FAIL
IFC review comments faxed to architect.
Plan resubmittals requested  5/24/2005 DONE
Copies of items needing corrected sent to Jeff Cramer, HDR.
Routing - PLAN CHECK4/4/2005 5/24/2005 FAIL
Resubmittals required. Copy of items needing addressed sent to Jeff Cramer, HDR. Routing plans to fire code analyst for review.
Routing - PLUMBING3/21/2005 4/4/2005 PASS
per plans and 2003 upc
Routing - PUBLIC WORKS3/15/2005 3/21/2005 PASS
Plans ACCEPTED BY PLAN TECH  3/15/2005 DONE
Need the 2003 Lighting/mechanical / envelope Comp.
Plans are in 3 sections. Routing began to PW with both of the 1st section and 1 set of mechanical. Balance of sections are in Dan Stuart's cubicle.
Application received  3/10/2005  
Recd Pcfee & Taken To Pln CK  3/10/2005  
BLD-Conference5/22/20085/22/2008 P 
DetailsTom Arcoraci
Fee Review-notes3/10/20053/10/2005