Third Notice BLD | 12/28/2005 | 12/28/2005 | 3/15/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 12/5/2005 | 12/5/2005 | 12/28/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 11/15/2005 | 11/15/2005 | 12/5/2005 | | DONE |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 11/15/2005 | 11/15/2005 | 11/15/2005 | P | PASS |
Tom Arcoraci
|
|
|
pete Note: structual inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Final | 11/15/2005 | 11/15/2005 | 11/15/2005 | P | PASS |
Tom Arcoraci
|
|
|
pete Note: structual inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 11/15/2005 | 11/15/2005 | 11/15/2005 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 9/27/2005 | 9/27/2005 | 9/27/2005 | | NR |
Tom Arcoraci
|
|
|
|
FIRE-Conference | 7/28/2005 | 7/28/2005 | 7/28/2005 | P | PASS |
Troy Cobbley
|
|
|
Inspection was for viewing some of the treated wood. It appears to be treated per the example presented.
|
FIRE-Conference | 7/20/2005 | 7/21/2005 | 7/21/2005 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for flame retardant that is to be applied to the concealed combustibles above the canopy ceilings. I could not tell if the retardant had been applied or not. Contractor will apply some to a small piece for closer inspection
|
BLD-Framing/Rough-in | 5/26/2005 | 5/27/2005 | 5/27/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/26/2005 at 8:02:15 AM. Contact: ###-####. Ceiling grid OK.
|
BLD-Other | 5/6/2005 | 5/6/2005 | 5/6/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/6/2005 at 8:34:03 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/13/2005 | 4/14/2005 | 4/14/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/13/2005 at 2:04:22 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 4/4/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/31/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/31/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/31/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/16/2005 | | 3/30/2005 | | PASS |
|
|
|
3/30/2005 13:17:06 CJW - activity updated through activity BLDA022 from case BLD05-00660.
|
Routing - FIRE | 3/23/2005 | | 3/30/2005 | | PASS |
|
|
|
approved subject to obtaining a Fire Alarm Permit and approved plans for the fire alarm work prior to installation Called architect and advised him he can submit a FA permit immediately.
|
1st review completed | | | 3/30/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/30/2005 | | 3/30/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/16/2005 | | 3/23/2005 | | PASS |
|
|
|
The IBC plan review was started March 22, 2005 and was finished the next day. The drawings were approved. No plan corrections were noted.
|
Pending Assignment by MYS | 3/14/2005 | | 3/16/2005 | | DONE |
|
|
|
3/16/2005 13:14:15 MYS - activity updated through activity BLDA172 from case BLD05-00660.
|
Plans ACCEPTED BY PLAN TECH | | | 3/16/2005 | | DONE |
|
|
|
Ok to take in on the 2000 code per Bruce C. & Carl W.
|
Application received | | | 3/14/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2005 | | |
|
|
|
|
Fee Review-notes | 3/14/2005 | 3/14/2005 | | | |
|
|
|
|