Third Notice BLD | 12/6/2005 | 12/6/2005 | 1/10/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/14/2005 | 9/14/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/11/2005 | 9/14/2005 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 8/3/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10675 issued 8-3-05 to Taco Del Mar.
|
Permanent Occupancy | | 7/19/2005 | 7/19/2005 | | DONE |
|
|
|
|
Temporary occupancy | | | 7/19/2005 | | DONE |
|
|
|
Temp. Occ. Cert. #5254 issued 7-19-05 to Taco Del Mar.
|
FIRE-Final Inspection | 7/18/2005 | 7/18/2005 | 7/18/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
FIRE-Final Inspection | 7/15/2005 | 7/18/2005 | 7/18/2005 | A | FAIL |
Forrest France
|
|
|
Provide building address, install fire ext. within a normal path of travel, verify function of emergency discharge lighting.
|
BLD-Final | 7/15/2005 | 7/18/2005 | 7/18/2005 | A | PART |
Jim Storey
|
|
|
sunny; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa final ok pending all others/ no occ card was printed upon permit isuance.
|
BLD-Framing/Rough-in | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | PASS |
Jim Storey
|
|
|
ceiling grid///sunny; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 6/2/2005 | 6/3/2005 | 6/3/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/2/2005 at 10:26:53 AM. Contact: ###-####.
|
Case Summary (BLD) | | | 5/13/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/2/2005 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 4/5/2005 | | 4/28/2005 | | PASS |
|
|
|
4/28/2005 09:43:28 RMH - activity updated through activity BLDA022 from case BLD05-00687.
|
Case Summary (BLD) | | | 4/28/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2005 | | |
|
|
|
|
Telephone call | | | 4/28/2005 | | DONE |
|
|
|
tlk to todd ###-#### that permit and fees are ready to be picked
|
Routing - FIRE | 4/21/2005 | | 4/25/2005 | | PASS |
|
|
|
|
1st review completed | | | 4/25/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/19/2005 | | 4/21/2005 | | |
|
|
|
|
Routing - PLUMBING | 4/11/2005 | | 4/19/2005 | | PASS |
|
|
|
additional cross connection protection may be required
|
Routing - PLANNING | 4/7/2005 | | 4/11/2005 | | PASS |
|
|
|
Approved per DRH03-00208 MOD #1/MOD#2. Note parking was increased for potential restaurant uses per CVA04-40
|
Routing - PUBLIC WORKS | 4/5/2005 | | 4/7/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/5/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/5/2005 | | DONE |
|
|
|
Resubmittal of signed llighting compliance sheets received. Began routing.
|
Plan resubmittals received | | | 4/1/2005 | | DONE |
|
|
|
Complete new sets of plans received with architects stamp and signature. Lighting compliance sheets not signed. Held at front desk awaiting lighting compliance resubmittals
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/2005 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 3/17/2005 | | FAIL |
|
|
|
PLANS CANNOT BE ROUTED DUE TO THE FOLLOWING: (1) NOT STAMPED AND SIGNED BY IDAHO LICENSED ARCHITECT, (2) PLANS CANNOT SAY "NOT FOR CONSTRUCTION". Resubmittals are required prior to routing. (MSouthard)
|
Fee Review-notes | 3/16/2005 | 3/16/2005 | 3/16/2005 | | DONE |
|
|
|
|
Application received | | | 3/16/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/16/2005 | | DONE |
|
|
|
|