Permit Information
Permit NumberBLD05-00775
StatusFinaled
Name STEED CONSTRUCTION
Site Address 1445 W COMMERCE AVE
Project NameHAYDEN BEVERAGE
Customer Number 
ePlanReviewNo
Description
(HAYDEN BEVERAGE-ADDITION) To construct a one story Type VB 47,307 sq.ft. warehouse/office addition to existing 82,120 sq.ft. unlimited area warehouse/office. Other work inlcudes interior remodeling in the existing warhouse and office areas, all site improvements, paving and landscaping per approved plans and DRH05-00025. Fire sprinklers are used for the unlimited area. This building must maintain 60 foot open yards on all sides. High piled storage requirements are in accordance with the International Fire Code. Separate plans, engineering and permits are required for storage racks over 8 feet in height.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  2/8/2018 DONE
Print Occupancy Form  2/7/2018 DONE
Third Notice BLD10/1/200710/1/200710/12/2007 DONE
Second Notice has not been responded to.
Fee Review-notes3/24/20053/24/200510/12/2007 DONE
Second Notice BLD9/13/20079/13/200710/1/2007 DONE
First Notice has not been responded to.
First Notice7/31/20077/31/20079/13/2007 DONE
DetailsJim Storey
BLD-Aging Inspection7/25/20077/25/20077/31/2007 PASS
DetailsJim Storey
DOC - Permit Finaled7/31/20077/31/20077/31/2007PPASS
DetailsJim Storey
BLD-Final4/4/20074/4/20074/4/2007PPASS
DetailsJim Storey
odie; Phone #: ###-#### Internet Inspection Request from: Victoria Beall final ok si achrived.
Code Occupancy Approval4/4/20074/4/20074/4/2007APASS
DetailsDena Gambrel
4-4-07 Final Occupancy sign off. Landscape is in.
Code Occupancy Approval4/4/20074/4/20074/4/2007ACANC
DetailsDena Gambrel
FIRE-Final Inspection3/8/20073/8/20073/8/2007PPASS
DetailsForrest France
Final fire life safety walk through passed inspection, some issues corrected while on site, previous c/n items are complete.
BLD-Aging Inspection3/6/20073/6/20073/6/2007 DEFR
DetailsJim Storey
to plm and fire bond cod still in place but cod permit finaled
BLD-Framing/Rough-in1/2/20071/3/20071/3/2007APASS
DetailsJim Storey
phase 3; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
Code Occupancy Approval Temp11/30/200611/30/200611/30/2006PPASS
DetailsDena Gambrel
Temp sign off. They have installed parking bumpers and In/Out markings. Bonded for the remaining landscaping.
BLD-Aging Inspection10/17/200610/17/200610/17/2006 FAIL
DetailsJim Storey
pending others w/cn idems.
Code Occupancy Approval Temp8/17/20068/17/20068/29/2006AFAIL
DetailsDena Gambrel
08-17-06 Failed inspection. Will need to get bids for in/out marking, parking bumpers and landscape bid for the south part.
FIRE-Final Inspection7/13/20067/14/20067/14/2006AFAIL
DetailsTroy Cobbley
The only life safety items looked at were the exit signs, emergency lights and the exit discharge lights. An exit discharge light is required at the main entry/exit. The overhead sprinkler system needs finaled as well as the fire alarm.
FIRE-Final Inspection7/12/20067/13/20067/13/2006PFAIL
DetailsTroy Cobbley
Life safety is not ready yet since emergency lighting and other permits have not been finaled
BLD-Other7/7/20067/10/20067/10/2006APASS
DetailsJim Storey
ceilling ok need to check spreader bars at final.
BLD-Energy code compliance5/31/20066/1/20066/1/2006APASS
DetailsJim Storey
odie; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in5/31/20066/1/20066/1/2006APASS
DetailsJim Storey
odie; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Aging Inspection5/10/20065/10/20065/11/2006 PASS
DetailsJim Storey
wip
BLD-Final3/10/20063/10/20063/13/2006PCANC
DetailsJim Storey
odie ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
FIRE-Final Inspection3/9/20063/10/20063/10/2006ANR
DetailsForrest France
The project related fire sprinkler and alarm permit work must be finaled prior to life safety final inspection and approval.
Telephone call  3/10/2006 DONE
Telcon from "Odie", Steed Const. ###-#### (3/10/06; 11:30 am). He requested TOC to occupy all of new whse and 3/4 of the new offices tomorrow, indicating this is a phased project and they want to occupy Phase 1. There is no evidence of "phasing" on the building permit. Looked into sprinkler history and found many deficiencies noted at previous inspections and requirements for resubmittals which have not been responded to. So we have known significant sprinkler design/installation deficiencies; no approved plans, therefore we can't inspect; AS contractor has not requested an inspection (presumably because they are aware they are not ready since they don't have approved plans); therefore we cannot allow a TOC with the building known to be improperly protected. Denied request for TOC.
Advised DH (FM) and RC (FI) of their intent to move in this weekend; suggested a drop-in visit to verify they are not occupying illegally.
Code Occupancy Approval Temp3/8/20063/8/20063/8/2006PFAIL
DetailsDena Gambrel
03-08-06 Bond recieved in the amount of $74, 481.00 for landscape and paving.
BLD-Framing/Rough-in2/7/20062/8/20062/8/2006APART
DetailsJim Storey
ceiling inspection//odie; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa wire hvac termanations.
BLD-Energy code compliance12/21/200512/22/200512/22/2005APART
DetailsJim Storey
odie; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in12/21/200512/22/200512/22/2005APASS
DetailsJim Storey
odie; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Energy code compliance11/16/200511/17/200511/17/2005APART
DetailsTom Arcoraci
odi; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles north south wall at south end of building ok insulation, shear and blocking ok at east center
BLD-Framing/Rough-in11/1/200511/1/200511/1/2005APART
DetailsJim Storey
cooller roof welding ok
BLD-Framing/Rough-in10/31/200510/31/200510/31/2005PPART
DetailsJim Storey
hodie; Phone #: ###-#### Internet Inspection Request from: Cathy Chilesok to cover studwalls need sheer atchment insp.
BLD-Aging Inspection10/3/200510/3/200510/3/2005 PASS
DetailsJim Storey
wip
BLD-Footing8/1/20058/1/20058/1/2005PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/1/2005 at 7:14:45 AM. Contact: ###-####. Placement complete upon arriving on site. Did note that reinforcement and concrete inspected by special inspector.
BLD-Footing7/26/20057/27/20057/27/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/26/2005 at 11:50:13 AM. Contact: ###-####.
FIRE-Conference7/19/20057/20/20057/20/2005ADONE
DetailsForrest France
On site discussion with Pat, the GC for this project, in regards to requirements for automatic smoke and heat vent installation as addressed in plan review notes.
FIRE-Conference7/12/20057/13/20057/13/2005PCANC
DetailsForrest France
Cancel inspection per Pat the GC, he will re-schedule the confrence at a later date.
Issue PAID IN FULL permit  6/17/2005 DONE
Permit Ready to Issue  6/14/2005  
Inspection Record Card- Bld  6/14/2005 DONE
Print Occupancy Form  6/14/2005 DONE
Telephone call  6/14/2005 DONE
talked to wesley steele at ###-#### is ready & need achd
Plan assigned to (MLO)3/25/2005 6/13/2005 PASS
6/13/2005 11:26:54 MLO - activity updated through activity BLDA022 from case BLD05-00775.
PLANS/APPL TAKEN TO FRONT DESK  6/13/2005 DONE
Routing - FIRE6/8/2005 6/10/2005 PASS
resubmittal acceptable, review faxed to architect.
Plan resubmittals received  6/8/2005 DONE
Received 1 Letter for Sam R. & 4 Copys of sheet A1.1 Taken to Mike O.
Routing - FIRE5/26/2005 6/6/2005 FAIL
resubmittal assigned to Mary F. to review 6/3/05

Resubmittal requried on the south side fire department access to all exterior portions of the buildings within a maximum of 150'.
Plan resubmittals received  5/26/2005  
Received (4) copies of sheet A1.1, A2.0, A2.1, A2.4, A2.6, A2.7, A2.8, A3.4, A8.1, S1.1, S2.1, S3.2, S3.3, S4.3, S6.2 and M3.0. Also received (1) copy of unit coolers technical data. Routed to Mike O.
Routing - PLAN CHECK5/26/2005 5/26/2005 PASS
Routing - PUBLIC WORKS5/16/2005 5/18/2005 PASS
Routing - PLAN CHECK5/18/2005 5/18/2005 PEND
Routing - PLUMBING5/11/2005 5/16/2005 PASS
per plans and resubmittals dated 4/28/05
Routing - Erosion and Sediment5/10/2005 5/11/2005 PASS
ESC approved with attached conditions.
1st review completed  5/10/2005 FAIL
failed Sturctural, ESC, plumbing, public works, plan check and fire.
Routing - FIRE5/5/2005 5/10/2005 FAIL
See attached review comments; review faxed to architect.
Routing - PLAN CHECK4/26/2005 5/5/2005 FAIL
Plan resubmittals requested  5/5/2005 DONE
IBC corrections.
Plan resubmittals received  5/4/2005 DONE
Received Transmittal & 4 Copys of sheets A0.0,A2.0,A2.4,A2.7,A3.2,A3.3,A3.4,A4.2,A4.7,A9.2 Taken to Mike P.
Routing Off Site - STRUCTURAL5/2/2005 5/3/2005 PASS
Called PDQ for pick up..
Plan resubmittals received  4/28/2005 DONE
Received 2 Document Transmittals ,2 ESC Narratives, 6 Copys of sheets ESC-1,ESC-2 & 4 Copys of sheets P2.0,P3.0 Taken to Mike O.
Routing - PLANNING4/22/2005 4/26/2005 PASS
Sara S. DRH05-00025

Approved [er DRH05-00025.
Plan resubmittals received  4/21/2005 DONE
Received Transmittal 3 Response comments,2 Material testing books, 4 Copys of sheets S1.2,S2.2,S4.4,S6.2, Taken to Mike O.
Routing - PLUMBING4/14/2005 4/14/2005 FAIL
if RPZ is an R.P backflow preventor it must be located in an area with drainage to handle the full discharge. provide a water supply for an automatic soap dispensor at the mop sink if used. provide a vent for the trench drain. flammable liquids interceptor must drain to the sanitary sewer, use approved detail attached.
Routing - Erosion and Sediment4/14/2005 4/14/2005 FAIL
ESC plan does not meet standards set forth in BMC 8-17. Checklist completed. Informed Contractor. Faxed Checklist.
Routing - PUBLIC WORKS4/7/2005 4/14/2005 FAIL
Contact Mike Hunter at ###-#### for conditions of rejection.
Routing Off Site - STRUCTURAL3/26/2005 4/11/2005 FAIL
Called PDQ for pick up. Sent corrections to architect. MLO
Routing - PLANNING Land Div3/29/2005 4/7/2005 PASS
Lots 17 and 18 of Boise Industrial Foundation combined by one Tax Parcel #.
Plan routing begun/NEW & ADDTN  3/29/2005  
Routing - AIRPORT3/28/2005 3/28/2005 PASS
(1) Sent to Matt Petaja via interdepartmental mail.
Pending Assignment by MYS3/24/2005 3/25/2005 DONE
3/25/2005 14:34:18 JCM - activity updated through activity BLDA174 from case BLD05-00775.
Application received  3/24/2005  
Recd Pcfee & Taken To Pln CK  3/24/2005