Third Notice BLD | 5/25/2007 | 5/25/2007 | 6/21/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/25/2007 | 5/9/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/25/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11551 issued 4-25-07 to Jems Properties.
|
Permanent Occupancy | | 4/24/2007 | 4/24/2007 | | DONE |
|
|
|
|
BLD-Aging Inspection | 3/13/2007 | 3/13/2007 | 3/15/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/10/2007 at 4:49:22 PM. Contact: ###-####. ok pending others
|
Temporary occupancy | | | 1/11/2007 | | DONE |
|
|
|
Temp. Occ. Cert. # 5512 issued 1-11-07 to Jems Properties.
|
FIRE-Final Inspection | 1/9/2007 | 1/10/2007 | 1/10/2007 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, c/n items are complete.
|
FIRE-Final Inspection | 1/8/2007 | 1/9/2007 | 1/9/2007 | A | FAIL |
Forrest France
|
|
|
Relocate smoke alarms per NFPA 72.
|
BLD-Conference | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | NR |
Tom Arcoraci
|
|
|
derrick - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
Print Occupancy Form | | | 12/11/2006 | | DONE |
|
|
|
|
BLD-Conference | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | NR |
Mike Jordan
|
|
|
derick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Need detail from contractor regardig handrail issues. Project is done under IBC and wouold require handrails on either side of stairway with one foot return which if done will encroch on exit passageway at door.
|
BLD-Aging Inspection | 10/23/2006 | 10/23/2006 | 10/23/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 8/21/2006 | 8/21/2006 | 8/21/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 6/20/2006 | 6/20/2006 | 6/20/2006 | P | PASS |
Jim Storey
|
|
|
darek - reinsp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley cn made ok insulation ok
|
BLD-Framing/Rough-in | 6/8/2006 | 6/9/2006 | 6/9/2006 | A | FAIL |
Mike Jordan
|
|
|
derick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs to complete fire caulking at floor/ceiling assemblies. Add strap to top plate at 3rd floor ceiling. Provide two layers of 5/8 " type X around washer box at 3rd floor unit at exterior 1hr. wall aSSEMBLY. ok to insul.
|
BLD-Aging Inspection | 3/23/2006 | 3/23/2006 | 3/23/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 1/18/2006 | 1/18/2006 | 1/18/2006 | | CANC |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 11/16/2005 | 11/17/2005 | 11/17/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/16/2005 at 12:44:31 PM. Contact: ###-####.
|
BLD-Footing | 11/7/2005 | 11/8/2005 | 11/8/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/7/2005 at 3:22:11 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 9/27/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/23/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/23/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/23/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/23/2005 | | DONE |
|
|
|
tlk to brian cooper ###-#### that his permit and fees are ready to be picked up
|
Routing - PLAN CHECK | 9/20/2005 | | 9/22/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/22/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/22/2005 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/29/2005 | | 9/22/2005 | | PASS |
|
|
|
9/22/2005 10:55:40 M_P - activity updated through activity BLDA022 from case BLD05-00805.
|
Routing - PLAN CHECK | 9/19/2005 | | 9/20/2005 | | |
|
|
|
Routing to planning.
|
Routing - PLANNING | 9/19/2005 | | 9/19/2005 | | PASS |
|
|
|
|
Routing - FIRE | 9/1/2005 | | 9/19/2005 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - PLAN CHECK | 8/19/2005 | | 9/1/2005 | | |
|
|
|
Routing to fire.
|
Routing - PLAN CHECK | 8/10/2005 | | 8/19/2005 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Plan resubmittals received | | | 8/11/2005 | | DONE |
|
|
|
Received 1 Transmittal, 2 United Water sheets, & 2 Copys of sheet A2.1 Taken to Mike P.
|
Routing - FIRE | 7/29/2005 | | 8/10/2005 | | FAIL |
|
|
|
Architect did not respond to two of the 4 resubmittal comments. Revised review faxed to architect.
|
Plan resubmittals received | | | 8/5/2005 | | |
|
|
|
Received (2) copies of sheet A2.1, A2.4, A3.1, A3.2, A3.4, A4, A5, EM-1 and EM-2. Routed to Mike P.
|
Routing - PUBLIC WORKS | 7/29/2005 | | 7/29/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/20/2005 | | 7/29/2005 | | FAIL |
|
|
|
2nd review failed sent correction report to architect requesting additional informaiton be submitted for further review prior to issuing permit.
|
Meeting | | | 7/28/2005 | | DONE |
|
|
|
meeting with Larry Knopp regarding alternatives for FD access roadways. Acceptable alternative would be a turnaround between two of the apartment buildings or possibly a legal cross access easement to allow access from an exisitng roadway on the adjoining property to west if that roadway meets FD roadway requirements (he had no information on the that roadway).
|
Routing - PUBLIC WORKS | 7/18/2005 | | 7/20/2005 | | FAIL |
|
|
|
Where sanitary sewer lines connect to public sewer they must be a min of 1 foot apart and be perpendicular to the main line. Contact Jim Pardy at ###-####
|
Routing - PLAN CHECK | 5/27/2005 | | 7/18/2005 | | |
|
|
|
Routing to plumbing.
|
Routing - PLUMBING | 7/18/2005 | | 7/18/2005 | | PASS |
|
|
|
increase water service piping to 1 1/4" . thermol expantion protection required.
|
Routing - PLAN CHECK | 7/18/2005 | | 7/18/2005 | | |
|
|
|
Routing to P.W.
|
Plan resubmittals received | | | 7/8/2005 | | DONE |
|
|
|
Received Transmittal & 2 Copys of sheets C1.1,A1,A2.1,A2.2,A3.1,A3,A3.2,A4,A5,EM-1,EM-2 Taken to Mike P
|
1st review completed | | | 5/27/2005 | | FAIL |
|
|
|
failed planning, public works, plumbing, plan check, and fire.
|
Routing - FIRE | 5/24/2005 | | 5/27/2005 | | FAIL |
|
|
|
review faxed to architect
|
Routing - PLAN CHECK | 5/4/2005 | | 5/24/2005 | | FAIL |
|
|
|
Routed to Mike P. on 5/4/2005
Plan review completed, sent correction report to architect requesting additional informaiton be submitted for further review prior to issuing permit.
Sent submittal letter to architect on 4/5/05 and had meeting with architect stating items which needed to be corrected prior to my review.
|
Case Summary (BLD) | | | 5/24/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 5/24/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 5/4/2005 | | 5/23/2005 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional informaiton be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 5/13/2005 | | DONE |
|
|
|
Received 2 Letters , 2 Design Criterias, 1 Response & 2 Copys of sheets A0,A2.1,A2.4,A3,A3.1,A3.4,A6,P-1,P-2,A4,A5,EM-1,EM-2 Taken to Mike P.
|
Routing - PLANNING | 4/19/2005 | | 4/20/2005 | | FAIL |
|
|
|
Failed for noncompliance w/ conditions of approval #2, 4, 5, 10.
|
Routing - PLUMBING | 4/14/2005 | | 4/19/2005 | | FAIL |
|
|
|
see bld05-00802 for comments
|
Routing - Erosion and Sediment | 4/13/2005 | | 4/14/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING Land Div | 3/29/2005 | | 4/7/2005 | | PASS |
|
|
|
See BLD 05-00804 for approvals
|
Plan Reviewer's activity | | | 4/5/2005 | | HOLD |
|
|
|
Sent submittal letter to architect on 4/5/05 and had meeting with architect stating items which needed to be corrected prior to my review.
|
Pending Assignment by MYS | 3/25/2005 | | 3/29/2005 | | DONE |
|
|
|
3/29/2005 08:54:32 JCM - activity updated through activity BLDA170 from case BLD05-00805.
|
Plan routing begun/NEW & ADDTN | | | 3/29/2005 | | |
|
|
|
|
Application received | | | 3/25/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/25/2005 | | |
|
|
|
|
Fee Review-notes | 3/25/2005 | 3/25/2005 | | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/29/2005 | | | | |
|
|
|
Called PDQ for pick up
|
Routing - PUBLIC WORKS | 4/7/2005 | | | | FAIL |
|
|
|
Failed by Brian Murphy - Requires drainage plan revisions. Contact at ###-####
Failed by Jim Pardy - Each building requires an individual connection to a main line as defined by DEQ.
|