BLD-Final | 2/1/2011 | 2/2/2011 | 2/2/2011 | A | PASS |
Mike Jordan
|
|
|
chris Phone #: ###-####. All issues have been resolved. ok for perm. occ.
|
Print Occupancy Form | | | 2/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
Permanent Occupancy | | | 2/2/2011 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 1/25/2011 | 1/26/2011 | 1/26/2011 | A | FAIL |
Jim Sly
|
|
|
chris Phone #: ###-#### C/N ..... Need min. 1 1/2" clearance between handrail and exterior wall.......Exterior stairway. Manager (Chris) said his notice and Order deadline is Feb 9th...and will try to get handrail and final inspection done before that date. He emmediately made a call to Contractor. and is going ahead in good faith to meet deadline.
|
FIRE-Final Inspection | 1/21/2011 | 1/25/2011 | 1/25/2011 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 1/18/2011 | 1/19/2011 | 1/21/2011 | A | FAIL |
Troy Cobbley
|
|
|
The storage height for the sprinkler design has been exceeded. Chris is going to make adjustments and institute a height monitoring system for the rack storage. A re-inspection has been set up for next tuesday.
|
Plan Reviewer's activity | | | 1/18/2011 | | DONE |
Jason Blais
|
|
|
Tenant provided documentation for approval of racking in Ada County and by NACFR. Also provided engineering calculations for the racking and a letter from the sprinkler contractor on the design. Fire Inspector Troy Cobbley visited the site today and will go back tomorrow for a final inspection after reviewing the documentation. A Building final inspection is also needed in order to final the permit and issue a Certificate of Occupancy.
|
Plan Reviewer's activity | | | 1/10/2011 | | DONE |
Jason Blais
|
|
|
Sent Notice and Order to tenant and building primary owner. See document attached to this case.
|
Case Summary (BLD) | | | 12/1/2010 | | |
|
|
|
|
BLD-Aging Inspection | 11/26/2010 | 11/26/2010 | 11/30/2010 | P | DONE |
Troy Cobbley
|
|
|
Information has been forwarded to Jason Blais and Scott Arellano as per policy for aging permits.
|
BLD-Aging Inspection | 11/26/2010 | 11/26/2010 | 11/26/2010 | | PEND |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 6/14/2010 | 6/14/2010 | 6/14/2010 | | PEND |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/7/2009 | 8/11/2009 | 8/12/2009 | P | FAIL |
Troy Cobbley
|
|
|
All items except for the racking permit have been corrected. Jay is following up on getting the permit going.
|
FIRE-Conference | 3/16/2009 | 3/16/2009 | 3/16/2009 | A | DONE |
Troy Cobbley
|
|
|
Robert, with Sentry Security, had questions about how to incorporate new zones into the existing four zone fire alarm panel. I deferred him to the fire alarm plan reviewer.
|
FIRE-Final Inspection | 3/2/2009 | 3/3/2009 | 3/4/2009 | A | FAIL |
Troy Cobbley
|
|
|
All items have been addressed except for verification of the cfm for the hvac units, verification that the two fire doors are still functional and provide a racking permit for the steel storage racks that exceed 8'-0" and for any solid pile storage that exceeds 12'-0".
|
BLD-Aging Inspection | 2/25/2008 | 2/26/2008 | 2/27/2008 | A | FAIL |
Troy Cobbley
|
|
|
I did a walk through with Jay. Some of the correction items have been taken care of. See the print off of the job history that is in Jay's posession for items corrected and items still needing corrected.
|
BLD-Aging Inspection | 7/28/2006 | 7/28/2006 | 7/31/2006 | | NR |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 5/25/2006 | 5/25/2006 | 5/25/2006 | | CANC |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/3/2005 | 8/4/2005 | 8/4/2005 | A | FAIL |
Troy Cobbley
|
|
|
Contact: ###-####. Provide knox box per review note #1. Provide additional emergency light in the second floor corridor. Mount fire extinguisher on the second floor no higher than 48" to top of handle. Lower all fire extinguisher in warehouse to 48". Provide exit sign on second floor balcony as marked on sheet A2.0. Provide cfm information for all hvac units and areas served for possible duct smoke detector addition. Provide racking permits for all storage racks over 8' in height. Contact Bill Alexander for information. Provide smoke detector at the fire alarm panel. See approved drawings sheet A1.0 for locations of defiencies which include damaged fire doors and emergency lights/exit signs that need added or repaired. Several doors are also blocked by storage.
|
BLD-Final | 8/3/2005 | 8/4/2005 | 8/4/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/3/2005 at 2:03:34 PM. Contact: ###-####. Need Fire final
|
BLD-Framing/Rough-in | 6/30/2005 | 6/30/2005 | 6/30/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/30/2005 at 9:07:50 AM. Contact: ###-####. grid ok
|
BLD-Framing/Rough-in | 6/6/2005 | 6/7/2005 | 6/7/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 1:19:24 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 5/27/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/2/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/2/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/2/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/2/2005 | | DONE |
|
|
|
tlk to matt rhees ###-#### that permit and fees are ready to be picked up
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/28/2005 | | 4/29/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan assigned to (JCB) | 4/5/2005 | | 4/29/2005 | | PASS |
|
|
|
4/29/2005 15:45:41 JCB - activity updated through activity BLDA022 from case BLD05-00867.
|
Routing - FIRE | 4/26/2005 | | 4/28/2005 | | PASS |
Bill Alexander
|
|
|
|
1st review completed | | | 4/28/2005 | | FAIL |
|
|
|
Failed Plan Check
|
Plan resubmittals received | | | 4/28/2005 | | DONE |
|
|
|
Received Transmittal ,1 Project Letter,1 Transmittal Letter, & 2 Copys of sheets A0.0,A1.0,A2.0,A3.0,A4.0 Taken to Jason B.
|
Plan resubmittals received | | | 4/26/2005 | | DONE |
|
|
|
Received Via Fax 1 Transmittal Letter, 1 Project Start up for special inspections Taken to Jason B.
|
Routing - Erosion and Sediment | 4/25/2005 | | 4/26/2005 | | PASS |
|
|
|
ESC waiver approved with attached conditions.
|
Routing - PLAN CHECK | 4/20/2005 | | 4/25/2005 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans to route to Erosion/Sediment Control and then to the Fire Dept.
|
Plan resubmittals requested | | | 4/25/2005 | | DONE |
|
|
|
Plan resubmittals and written response required for further review.
|
Plan Reviewer's activity | | | 4/20/2005 | | DONE |
|
|
|
Sent Matt Rhees an e-mail stating that an ESC permit is required. An ESC application needs to be completed and submitted with either a waiver letter or ESC plan for approval.
|
Routing - PLANNING | 4/18/2005 | | 4/20/2005 | | PASS |
|
|
|
Approved per CZC05-66 and as noted on sheet A1.0 for landscaping.
|
Routing - PLAN CHECK | 4/6/2005 | | 4/18/2005 | | |
|
|
|
Plans requested in Planning. Routed to Marty Santoyo.
|
Routing - PUBLIC WORKS | 4/5/2004 | | 4/6/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 4/5/2005 | | 4/5/2005 | | FAIL |
|
|
|
Exterior change included in this proposal will require zoning certificate reviewed by Design Review Staff. The CZC was submitted today. CER
|
Pending Assignment by MYS | 4/1/2005 | | 4/5/2005 | | DONE |
|
|
|
4/5/2005 12:45:30 MYS - activity updated through activity BLDA184 from case BLD05-00867.
|
Plans ACCEPTED BY PLAN TECH | | | 4/4/2005 | | |
|
|
|
|
Application received | | | 4/1/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/1/2005 | | |
|
|
|
|
First Notice | | 2/12/2011 | | | |
|
|
|
send final value request to tenant
|
Fee Review-notes | 4/1/2005 | 4/1/2005 | | | |
|
|
|
|