BLD-Final | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Tony Young
|
|
|
Rob; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
DOC - Permit Finaled | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 7/27/2006 | 7/28/2006 | 7/28/2006 | P | PART |
Tony Young
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles need to finish exterior rails,,
|
BLD-Grading Inspection | 7/26/2006 | 7/26/2006 | 7/26/2006 | | DONE |
|
|
|
Final grading and drainage complete and approved
|
BLD-Energy code compliance | 2/1/2006 | 2/1/2006 | 2/1/2006 | P | PASS |
Tony Young
|
|
|
Rob -- for framing and insulation reinspection; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 2/1/2006 | 2/1/2006 | 2/1/2006 | P | PASS |
Tony Young
|
|
|
Rob -- for framing and insulation reinspection; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 1/30/2006 | 1/30/2006 | 1/30/2006 | P | FAIL |
Tom Arcoraci
|
|
|
Rob -- framing and shearnail reinspection; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok to insulate see c/notice
|
BLD-Framing/Rough-in | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### c/n posted,,
|
BLD-Framing/Rough-in | 1/25/2006 | 1/25/2006 | 1/25/2006 | P | CANC |
Tony Young
|
|
|
Rob ; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 12/13/2005 | 12/13/2005 | 12/13/2005 | P | FAIL |
Mike Jordan
|
|
|
rob Note: shear; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Missing MSTC straps (floor to floor straps) and stdh48 straps at several locations. Areas were identified on plans.
|
BLD-Framing/Rough-in | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | FAIL |
Mike Jordan
|
|
|
shear nail insp///rob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Approved plans not on site.
|
BLD-Foundation | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | PART |
Tony Young
|
|
|
rich; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Footing | 7/6/2005 | 7/6/2005 | 7/6/2005 | P | PASS |
Mike Jordan
|
|
|
rich; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Conference | 7/5/2005 | 7/5/2005 | 7/5/2005 | P | PART |
Tony Young
|
|
|
rich; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa will have to have extremly deep/tall ftgs to meet top of wall per plans,,, or get engineering for taller walls
|
PubWorks Subgrade Approval | 4/6/2005 | 4/6/2005 | 6/30/2005 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer. 6/30/05
A letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####
|
Override - Activity Holds | 1/1/1900 | 1/1/1900 | 6/29/2005 | | |
|
|
|
|
Override - Activity Holds | | | 6/2/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/2/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 6/1/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 6/1/2005 | | |
|
|
|
|
Override - Activity Holds | | | 6/1/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/1/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2005 | | DONE |
|
|
|
talked to pj smith that permit is ready
|
Plan assigned to (SAM) | 4/5/2005 | 5/25/2005 | 5/31/2005 | | PASS |
|
|
|
5/31/2005 15:53:07 SAM - activity updated through activity BLDA022 from case BLD05-00898.
|
Routing - PLAN CHECK | 5/3/2005 | | 5/31/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 5/26/2005 | | DONE |
|
|
|
8:00 I called and left a message for Mike Carrol to call me. I have a question on the floor framing pop-out over the garage and where all the columns are. Plans are on hold.
|
Case Summary (BLD) | | | 5/25/2005 | | |
|
|
|
|
Routing - FIRE | 5/2/2005 | | 5/3/2005 | | PASS |
|
|
|
No fire sprinklers required.
|
Routing - Erosion and Sediment | 4/29/2005 | | 5/2/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 4/29/2005 | | 4/29/2005 | | PASS |
|
|
|
met with applicant 4/29 and redlined plans. Plans approved as noted with modifications to front balcony and front porch stair and walk. eeg.
|
Routing - PLANNING | 4/6/2005 | | 4/8/2005 | | FAIL |
|
|
|
04/08/05 - front covered patio and front porch with steps within front yard setback - fail
4/13/05 second call to applicant - left message
|
Routing - PUBLIC WORKS | 4/6/2005 | | 4/6/2005 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 4/5/2005 | | 4/6/2005 | | PASS |
|
|
|
APPROVED AS CATEGORY 3
|
Application received | | | 4/5/2005 | | |
|
|
|
|