BLD-Final | 2/7/2006 | 2/8/2006 | 2/8/2006 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/7/2006 at 4:36:46 PM. Contact: ###-####.
|
DOC - Permit Finaled | 2/8/2006 | 2/8/2006 | 2/8/2006 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 11/4/2005 | 11/4/2005 | 11/4/2005 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/4/2005 at 7:38:33 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/26/2005 | 10/26/2005 | 10/26/2005 | P | FAIL |
Mike Jordan
|
|
|
loren; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 6/21/2005 | 6/22/2005 | 6/22/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/21/2005 at 10:30:04 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 6/17/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 5/3/2005 | 5/3/2005 | 5/3/2005 | | PASS |
|
|
|
5/3/2005 10:59:53 SRZ - activity updated through activity BLDA022 from case BLD05-00954.
|
Plan assigned to (SAM) | 4/11/2005 | 4/11/2005 | 5/3/2005 | | PASS |
|
|
|
5/3/2005 10:59:53 SRZ - activity updated through activity BLDA022 from case BLD05-00954.
|
Routing - PLAN CHECK | 4/13/2005 | | 5/3/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 5/3/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/3/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/3/2005 | | DONE |
|
|
|
called spoke with Emmett Jr permit is ready and fees 5/3/05 2:28pm LEM
|
Routing - PUBLIC WORKS | 4/12/2005 | | 4/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 4/11/2005 | | 4/12/2005 | | PASS |
|
|
|
Setbacks shall be adjusted as redlined at the direction of the applicant to accomodate the window seat.
|
Application received | | | 4/11/2005 | | |
|
|
|
|