BLD-Final | 11/4/2005 | 11/4/2005 | 11/4/2005 | P | PASS |
Mike Jordan
|
|
|
carey ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 11/4/2005 | 11/4/2005 | 11/4/2005 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/27/2005 | 10/28/2005 | 10/28/2005 | A | NR |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles no underfl insul
|
BLD-Energy code compliance | 9/26/2005 | 9/27/2005 | 9/27/2005 | A | PASS |
Mike Jordan
|
|
|
karey; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 9/22/2005 | 9/22/2005 | 9/22/2005 | P | PASS |
Jim Sly
|
|
|
carey; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Foundation | 8/9/2005 | 8/11/2005 | 8/11/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 12:14:25 PM. Contact: ###-####.
|
BLD-Footing | 8/9/2005 | 8/10/2005 | 8/10/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 12:14:06 PM. Contact: ###-####.
|
BLD-Footing | 8/9/2005 | 8/11/2005 | 8/9/2005 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 12:12:40 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 9 2005 12:13PM.
|
BLD-Foundation | 7/28/2005 | 7/29/2005 | 7/29/2005 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 9:36:39 AM. Contact: ###-####. Pulled footing forms.....No footing poured.... they want to start over....flip flop plan because of Electr box would be in driveway.
|
BLD-Footing | 7/28/2005 | 7/28/2005 | 7/28/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 9:36:21 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 7/22/2005 | | DONE |
|
|
|
|
OVERRIDE | | | 7/20/2005 | | |
|
|
|
|
Plan assigned to (SRZ) | 7/20/2005 | 7/20/2005 | 7/20/2005 | | PASS |
|
|
|
7/20/2005 13:10:20 SRZ - activity updated through activity BLDA022 from case BLD05-00959.
|
Plan assigned to (SAM) | 4/11/2005 | 4/11/2005 | 7/20/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/1/2005 | | 7/20/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 7/20/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2005 | | DONE |
|
|
|
ONE SET RED-LINED
|
Permit Ready to Issue | | | 7/20/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/20/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/20/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLANNING | 7/1/2005 | | 7/1/2005 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/1/2005 | | 7/1/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 6/16/2005 | | 6/16/2005 | | FAIL |
|
|
|
Garage must have clear access from street, w/ 22' of backup.
|
Routing - PLANNING | 5/9/2005 | | 5/9/2005 | | FAIL |
|
|
|
At 8:00 a.m. I returned telephone message left by applicant on 5/6/05. Various issues with five sets of plans they had submitted. Requested they stop in to review. As of 3:45 p.m., have not heard back. Spoke w/ another representative of Status Homes last week, and relayed the same information. CER
|
Routing - PLANNING | 4/11/2005 | | 4/12/2005 | | FAIL |
|
|
|
Left message w/ applicant at 9:45a.m. Plans do not meet the front setback, as addressed on the plat. CER
|
Application received | | | 4/11/2005 | | |
|
|
|
|