Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-00965
StatusFinaled
Name ASPEN HOMES
Site Address 11541 W PALM ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 1548 sq.ft. Two story single family dwelling (997 sq.ft. Main floor / 551 sq.ft. Upper floor) with a 517 sq.ft. Attached two car garage and a 96 sq.ft. Covered front porch per approved plans and all red-lining. THE PERMIT HOLDER is responsible to comply with current wall bracing requirements adopted by Boise City. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/16/20057/18/20057/18/2005APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/16/2005 at 4:37:55 PM. Contact: ###-####.
DOC - Permit Finaled7/18/20057/18/20057/18/2005PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/16/2005 at 4:37:55 PM. Contact: ###-####.
BLD-Energy code compliance6/13/20056/13/20056/13/2005PPASS
DetailsMike Jordan
chuck; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. hangar at 3-ply micro was reinspected. All nails were added.-ok
BLD-Framing/Rough-in6/10/20056/10/20056/10/2005PFAIL
DetailsJim Sly
chuck; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
C/N nail hanger.
BLD-Footing5/4/20055/4/20055/4/2005PPASS
DetailsJim Sly
chris; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Telephone call  4/27/2005 DONE
left mess that permit is ready
Issue PAID IN FULL permit  4/27/2005 DONE
Plan assigned to (SRZ)4/26/20054/26/20054/26/2005 PASS
4/26/2005 11:22:35 SRZ - activity updated through activity BLDA022 from case BLD05-00965.
Plan assigned to (SAM)4/11/20054/11/20054/26/2005 PASS
4/26/2005 11:22:35 SRZ - activity updated through activity BLDA022 from case BLD05-00965.
Routing - PLAN CHECK4/12/2005 4/26/2005 PASS
Case Summary (BLD)  4/26/2005  
PLANS/APPL TAKEN TO FRONT DESK  4/26/2005 DONE
Inspection Record Card- Bld  4/26/2005 DONE
Permit Ready to Issue  4/26/2005  
Routing - PLANNING4/11/2005 4/12/2005 PASS
Routing - PUBLIC WORKS4/12/2005 4/12/2005 PASS
Application received  4/11/2005