Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD05-00969
StatusFinaled
Name ASPEN HOMES
Site Address 2455 N CRIBBENS ST
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 1349 sq.ft. One story single family dwelling with a 665 sq.ft. Three car Attached garage and a 99 sq.ft. Covered front porch per approved plans and all red-lining. THE PERMIT HOLDER IS RESPONSIBLE TO COMPLY WITH CURRENT WALL BRACING REQUIREMENTS ADOPTED BY BOISE CITY. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/8/20057/8/20057/8/2005APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/8/2005 at 6:58:06 AM. Contact: ###-####.
DOC - Permit Finaled7/8/20057/8/20057/8/2005PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/8/2005 at 6:58:06 AM. Contact: ###-####.
BLD-Energy code compliance6/2/20056/3/20056/3/2005APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 6/2/2005 at 5:33:35 PM. Contact: ###-####.
BLD-Energy code compliance6/2/20056/2/20056/2/2005PFAIL
DetailsMike Jordan
Scheduled by a contractor via Hello! on 6/2/2005 at 7:47:30 AM. Contact: ###-####. NO APPROVED PLANS ON SITE
BLD-Framing/Rough-in6/1/20056/1/20056/1/2005PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/1/2005 at 7:48:00 AM.
BLD-Framing/Rough-in5/31/20055/31/20055/31/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/31/2005 at 8:21:46 AM. Contact: ###-####.
Re-call for frame when all trades appr.
BLD-Footing4/21/20054/21/20054/21/2005APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/21/2005 at 6:59:37 AM. Contact: ###-####.
Issue PAID IN FULL permit  4/18/2005 DONE
Plan assigned to (SRZ)4/15/20054/15/20054/15/2005 PASS
4/15/2005 13:11:31 SRZ - activity updated through activity BLDA022 from case BLD05-00969.
Plan assigned to (SAM)4/11/20054/11/20054/15/2005 PASS
4/15/2005 13:11:31 SRZ - activity updated through activity BLDA022 from case BLD05-00969.
Routing - PLAN CHECK4/12/2005 4/15/2005 PASS
I spoke with the Builder (Gary Riggs) and the designer (Glenn Johnson) on 4/15/05 and required Lateral design, All beams and Headers, Fire Door, and Garage/dwelling Speration designation
to be able to complete my Plan Review. The designer stated he would provide and bring in corrections A.S.A.P. (SRZ)
Case Summary (BLD)  4/15/2005  
PLANS/APPL TAKEN TO FRONT DESK  4/15/2005 DONE
Inspection Record Card- Bld  4/15/2005 DONE
Permit Ready to Issue  4/15/2005 DONE
Telephone call  4/15/2005 DONE
tlk to secretary ###-#### that permit and fees are ready to be picked up
Telephone call  4/15/2005 DONE
tlk to secretary ###-#### that permit and fees are ready to be picked up
Routing - PLANNING4/11/2005 4/12/2005 PASS
Note: A reduced site plan was not provided.
Routing - PUBLIC WORKS4/12/2005 4/12/2005 PASS
Application received  4/11/2005