Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD05-00988
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMIC #24B
Customer NumberC7433
ePlanReviewNo
Description
Micron Building #24B - (Remodel for 300 MM Implants) - To remodel approximately 1,250 square feet of existing cleanroom space within an existing H5 Occupancy to accommodate new equipment. The project is located at the extreme Southwest corner of the first floor of building 24B Fabrication space. We will be converting existing H5 rooms 114A-D to accommodate 300MM Implanters. Construction will consist of demolition and reconstruction of cleanroom wall panels, ceiling grid, flooring, HVAC, Fire Sprinkler and Fire Alarm System modifications.

Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD3/1/20063/1/20063/15/2006 DONE
First Notice has not been responded to.
First Notice1/31/20061/31/20063/1/2006 DONE
DetailsJim Storey
BLD-Final1/27/20061/31/20061/31/2006APASS
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
DOC - Permit Finaled1/31/20061/31/20061/31/2006PPASS
DetailsJim Storey
FIRE-Final Inspection1/19/20061/25/20061/25/2006APASS
DetailsTroy Cobbley
life safety finaled
FIRE-Final Inspection11/15/200511/22/200511/22/2005ACANC
DetailsTroy Cobbley
No time for inspection
BLD-Final11/16/200511/23/200511/22/2005ACANC
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes Inspection cancelled from web by: Dennis Holmes
BLD-Aging Inspection11/7/200511/7/200511/7/2005 PASS
DetailsJim Storey
wip pending fire review.
BLD-Aging Inspection9/5/20059/5/20059/6/2005 PASS
DetailsJim Storey
wip
BLD-Conference7/1/20057/6/20057/6/2005APASS
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
Plan Reviewer's activity  5/13/2005 PASS
Reviewed and approved structural calculations and details for removal of the tube steel column. JCM
BLD-Conference5/4/20055/5/20055/5/2005APART
DetailsJim Storey
Jim, I also scheduled the Quartz Clean (BLD04-02270)final. This could work out! Holmes ; Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
BLD-Conference5/2/20055/4/20055/4/2005ACANC
DetailsTony Young
Jim, we can look at the fire separation wall. ; Phone #: ###-#### Internet Inspection Request from: Dennis Holmes
Dennis will reschedule,, I dont have security clearance 5/4/2005 11:57:43 AM
(F) Reprint permit  5/2/2005 DONE
BLD-Framing/Rough-in4/27/20054/28/20054/28/2005APART
DetailsJim Storey
per Jim Storey request. resubmital to jhon for 2 hr wall configuration .
Issue & PRINT to be Invoiced  4/28/2005 DONE
Plan assigned to (JCM)4/13/2005 4/27/2005  
Plan Reviewer's activity  4/25/2005 DONE
Site First Review - Completed 4-21-05. Identified some discrepancies in construction documents. Reviewed with applicant and will review agreed upon revisions on next site visit. JCM
Routing - FIRE4/13/2005 4/21/2005 FAIL
Site visit made. Need to 1) add exit siugn over door to rated corridor; 2) Corraect door ID on A8.1.3 to match thos on A2.1.1; 3) Add smoke seals to door schedule for 45 min roll-up door to corridor. Will approve and stamp "Print Issue" plans when changes are verified at next visit.
1st review completed  4/21/2005 FAIL
Application received  4/13/2005  
Third Notice BLD3/15/20063/15/2006   
Second Notice has not been responded to.
Routing - PLAN CHECK4/13/2005    
The plasn fo rthis project will be reviewed at the Micron site, no plans will be submitted to the City. JCM